Revision History
Rev. |
Description of Modification |
Date |
1. |
1st Issue |
19/12/2024 |
2. |
2nd Issue |
16/01/2025 |
3. |
3rd Issue |
20/01/2025 |
CONTENTS
|
|
|
|
|
|
Summary of
Exceedance, Complaint, Notification of Summons and Prosecutions 32
|
|
Conclusions
and Recommendations 36
Appendix A |
Master Programme |
Appendix B |
Overview of Desalination Plant in Tseung Kwan O |
Appendix C |
Summary of Implementation Status of Environmental Mitigation |
Appendix D |
Water Quality Monitoring Graphical Presentation |
Appendix E |
Summary of Exceedances |
Appendix F |
Waste Flow Table |
Appendix G |
Complaint Log |
Appendix H |
Event/Action Plan for Water Quality Monitoring |
Appendix I |
Event/Action Plan for Construction Noise Exceedance |
Appendix J |
Event/Action Plan for Coral Monitoring Exceedance |
Acuity Sustainability Consulting Limited
Executive Summary
Introduction
A1. The Project,
Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant
(TKODP), is a Designated Project under the Environmental Impact Assessment
Ordinance (Cap. 499) (EIAO) and is currently governed by a Further
Environmental Permit (EP No. FEP – 01/503/2015/B) for the construction and
operation of the Contract.
A2. In accordance
with the Environmental Monitoring and Audit (EM&A) Manual for the Contract,
EM&A works for marine water quality, noise, waste management and ecology
should be carried out by Environmental Team (ET), Acuity Sustainability
Consulting Limited (ASCL), during the construction phase of the Contract.
A3. According to
the contractor’s information, the works of TKODP were substantially completed
on 30 June 2024 and the plant commenced the operation phase on 1 July 2024. The
outstanding construction works were being carried out during this reporting
period.
A4. This is the 19th Quarterly EM&A Report, prepared by ASCL, for
the Contract summarizing the monitoring results and audit findings of the
EM&A programme at and around Tseung Kwan O Area
137 (TKO 137) during the reporting period from 1 September 2024 to 30 November
2024.
A5. The EM&A programme for this contract has covered environmental
monitoring on construction noise level at selected NSRs and Contractor’s
environmental performance auditing in the aspects of construction dust,
construction noise, water quality, waste management, Landscape and Visual and
Ecology.
Summary of Main Works Undertaken & Key
Mitigation Measures Implemented
A6. Key activities carried out in
this reporting period for the Project included the followings:
All
Area ·
Security Fence footing
construction work ·
Footpath Construction ·
Landscape Construction ·
Irrigation System
Construction ·
Water Pressure Test for FS
and PL system ·
Landscape planting work ·
Traffic signage work · E&M Works and Mechanical Installation |
PWST ·
Water Test in Tank A ·
Waterproofing work at Roof
Slab on Tank A · Installation of building services, electrical switchboards and cables Installation of mechanical equipment, steel pipe, Pressure Test |
Administration
Building ·
External wall aluminum
features installation ·
Finishing works for dog house ·
Minor Installation of
building services, electrical switchboards & cables, Pressure Test,
T&C ·
Fitting out works · Painting Works |
Chemical
building ·
Defect rectification · Repairing the defects inside the dangerous store |
ActiDAFF ·
Installation of access
opening covers for filtered water tank ·
Carrying out finishing works
for staircase no. 3. ·
Minor Installation of
mechanical equipment, piping system · Minor Installation of building services, electrical switchboards and cables, Installation of FRP Enclosure System |
Product
Water Storage Tank Building · Minor Installation of building services, cable laying and termination, PV Panel Installation, Testing & Commissioning |
OSCG
Building ·
Protective Coating for DG
Rooms ·
Installation of Railing on
Brine Maker Tank ·
Minor Installation of
building services, cables and pipe works, T&C · Tank surface cleaning, T&C |
Reverse
Osmosis Building ·
Installation of Signage, AP
doors, sanitary fitting, sanitary ware in toilet, tiling work and water meter
cabinets · Minor Installation of building services, minor cable laying and termination, Testing & Commissioning, PV Panel Installation |
Post
Treatment Building ·
Installation of Cat Ladders
in Water Tanks ·
Placing Soil Mix at Roof · Curb Construction for Rescue Opening at Water Tanks |
· Installation of building services, piping system, mechanical equipment and piping system, Pressure Test |
Inspection
gallery ·
Construction of roof tiling
works ·
Installation of steel
balustrade at roof ·
Installation of movement
joints ·
Construction of block works · Minor Installation of building service, T&C |
RO and
Electrical Building ·
Installation of Glass House ·
Minor Installation of
building services, electrical switchboards and cables ·
Minor Installation of
mechanical pipework and raised Floor, · PV Panel Installation, T&C Chiller plant
& Main Electrical Building · Minor Installation of building services, electrical switchboards and cables, Pressure Test, T&C Others ·
Slope works* · Construction works of extended access road |
Remark:
*The slope works were completed in October 2024, and there was
no site activities related to the slope works conducted in November 2024.
A7. The major environmental impacts brought by the above construction works
and slope works include:
·
Construction
dust and noise generation from excavation works, construction works;
·
Waste
generation from the construction activities
A8. The key environmental mitigation
measures implemented for the Project in this reporting period associated with
the above construction works include:
·
Dust
suppression by regular wetting and water spraying for construction works and
slope works;
·
Reduction
of noise from equipment and machinery on-site and regularly inspection to
machinery and plants/vehicles on-site to ensure proper functioning;
·
Sorting
and storage of general refuse and construction waste;
·
Deployment
of silt curtain at the inshore water outflow; and
·
Deployment
protective fencing for trees.
Summary of Exceedance & Investigation &
Follow-up
A9. No noise
monitoring was conducted during the reporting period since there are no
project- related construction activities undertaken within a radius of 300m
from the monitoring locations. No exceedance of the Action Level was recorded
during the reporting period.
A10. Referring to
EM&A Manual, the general water quality monitoring should be carried out
when there are marine-related construction activities undertaken. General water
quality monitoring at the ten monitoring stations (CE, CF, WSR1, WSR2, WSR3,
WSR4, WSR16, WSR33, WSR36 and WSR37) was ceased from 1 September 2023 due to
the completion of marine-related construction works.
A11. The operation
phase water quality was conducted from 1 September 2024 to 30 November 2024. Thirty-six (36) of the operation phase water quality monitoring results of SS obtained had
exceeded the Action Level. Eighty-five (85) of the
operation phase water quality monitoring results of SS obtained during the
reporting period had exceeded the Limit Level. After investigation, all
exceedances were concluded unrelated to the Project.
A12. The
continuous monitoring of effluent quality was conducted from 1 September 2024 to 30 November
2024 in accordance with the
EM&A Manual. No exceedance of the sampling was obtained during the
reporting period had exceeded the Limit Level. The plant was shut down from 7
a.m. to 7 p.m. on 3 November 2024. No effluent discharge from TKODP occurred
during this period. Due to the plant has suspended production, there was no
effluent discharge from the TKODP during the period between 24 November 2024
and 30 November 2024.
A13. In this
reporting period, 132 times of Construction Phase landfill gas monitoring were
recorded at Wan Po Road (Ch0+390 – Ch0+780) and (Ch0+400 - Ch1+200). No action and
limit level exceedance for methane, oxygen and carbon dioxide was recorded. The
Construction Phase landfill gas monitoring was ceased from 31 October 2024.
A14. In this
reporting period, Operation Phase landfill gas monitoring was conducted on 25, 26 and 27 September 2024, 9 and 10 October 2024, 14 and 15 November 2024. No exceedances of action level and limit
level was observed.
A15. Operation
phase monthly coral monitoring was conducted during the reporting period on 18 September 2024, 21 October
2024, 11 November 2024. There
is no AL/LL exceedance during the monitoring period.
A16. Operation
phase fishery monitoring for wet season 2024 was carried out on 24 and 31 August 2024. The detail of the monitoring was
presented in the 4th Operation Phase Monthly EM&A Report.
A17. Total thirteen (13) times of Weekly site inspections of the
construction works were also carried out by ET to audit the mitigation measures
implementation status. Three (3) times of
monthly Joint site inspections were carried out by ET and IEC.
A18. A summary of
the EM&A activities in this reporting period is listed in Table I and
summary of the environmental exceedance of the reporting period is tabulated in
Table II.
Table I Summary Table for EM&A Activities in
the Reporting Period
EM&A Activities |
Sep 2024 |
Oct 2024 |
Nov 2024 |
Noise Monitoring |
N/A |
N/A |
N/A |
Water Quality Monitoring |
3, 7, 10, 12, 14, 17, 19, 21, 24, 26 and 28 September 2024 |
1, 3, 5, 8, 10, 12, 15, 17, 19, 22, 24, 26, 29 and 31 October 2024 |
2, 5, 7, 9, 12, 16, 19, 21, 23, 26, 28 and 30 November 2024 |
TRC Monitoring for Main Disinfection |
N/A |
N/A |
N/A |
Coral Monitoring |
18 September 2024 |
21 October 2024 |
11 November 2024 |
Fishery Monitoring |
N/A |
N/A |
N/A |
Landfill Gas Monitoring (Construction Phase) |
2, 3, 4, 5, 6, 7, 9, 10, 11, 12, 13, 14, 16, 17, 19, 20, 21, 23, 24, 25, 26, 27, 28 and 30 September 2024 |
1, 2, 3, 4, 5, 7, 8, 9, 10, 12, 14, 15, 16, 17, 18, 19, 21, 22, 23, 24 and 25 October 2024 |
N/A |
Landfill Gas Monitoring (Operation Phase) |
25, 26 and 27 September 2024 |
9 and 10 October 2024 |
14 and 15 November 2024 |
Environmental Site Inspection |
3, 10, 17 and 24 September 2024 |
3, 8, 15, 22 and 28 October 2024 |
5, 14, 18 and 26 November 2024 |
Continuous Monitoring of Effluent Quality |
From 1 to 30 September 2024 |
From 1 to 31 October 2024 |
From 1 to 30 November 2024 |
Table II Summary Table for Exceedance in the
Reporting Period
Environmental Monitoring |
Parameter |
No. of non- Project related exceedance |
Total No. of non-Project related exceedance |
No. of Project related exceedance |
Total No. of Project related exceedance |
||
AL |
LL |
AL |
LL |
||||
Noise |
Leq (30min) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Water |
DO |
0 |
0 |
0 |
0 |
0 |
0 |
Turbidity |
0 |
0 |
0 |
0 |
0 |
0 |
Environmental Monitoring |
Parameter |
No. of non- Project related exceedance |
Total No. of non-Project related exceedance |
No. of Project related exceedance |
Total No. of Project related exceedance |
||
AL |
LL |
AL |
LL |
||||
SS |
36 |
85 |
121 |
0 |
0 |
0 |
|
pH |
0 |
0 |
0 |
0 |
0 |
0 |
|
Salinity |
0 |
0 |
0 |
0 |
0 |
0 |
|
TRC |
0 |
0 |
0 |
0 |
0 |
0 |
|
Landfill Gas |
O2 |
0 |
0 |
0 |
0 |
0 |
0 |
CH4 |
0 |
0 |
0 |
0 |
0 |
0 |
|
CO2 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Continuous Monitoring of Effluent Quality |
Temperature |
0 |
0 |
0 |
0 |
0 |
0 |
pH |
0 |
0 |
0 |
0 |
0 |
0 |
|
Salinity |
0 |
0 |
0 |
0 |
0 |
0 |
|
Total Residual Chlorine |
0 |
0 |
0 |
0 |
0 |
0 |
|
Suspended Solids |
0 |
0 |
0 |
0 |
0 |
0 |
|
Iron-Soluble |
0 |
0 |
0 |
0 |
0 |
0 |
|
Total Inorganic Nitrogen |
0 |
0 |
0 |
0 |
0 |
0 |
|
Total Phosphorus |
0 |
0 |
0 |
0 |
0 |
0 |
|
Sodium Metabisulphite |
0 |
0 |
0 |
0 |
0 |
0 |
|
Anti-scalant as Reactive Phosphorus* |
0 |
0 |
0 |
0 |
0 |
0 |
|
Coral Monitoring |
/ |
0 |
0 |
0 |
0 |
0 |
0 |
Fisheries Monitoring |
/ |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
*Remark: Anti-scalant
water quality testing will only be conducted whenever anti-scalant
dosage is adopted.
Complaint Handling and Prosecution
A19. No environmental complaint was received
during the reporting period. No notifications of summons or prosecution was
received during the reporting period.
Reporting Change
A20. There was no change to be
reported that may affect the on-going EM&A programme.
A21. According to
the contractor’s information, the TKODP commenced operation phase on 1 July
2024. The outstanding construction works were being carried out during this
reporting period.
|
Basic Project Information
1.
Background
The Acciona Agua, S.A. Trading, Jardine Engineering Corporation
Limited and China State Construction Engineering (Hong Kong) Limited and as AJC
Joint Venture (AJCJV) is contracted to carry out the Design, Build and Operate
First Stage of Tseung Kwan O Desalination Plant (TKODP) under Contract No.
13/WSD/17 (the Contract).
Acuity
Sustainability Consulting Limited (ASCL) is commissioned by AJCJV to undertake
the Environmental Team (ET) services as required and/or implied, both
explicitly and implicitly, in the Environmental Permit (EP), Environmental
Impact Assessment Report (EIA Report) (Register No. AEIAR-192/2015) and
Environmental Monitoring and Audit Manual (EM&A Manual) for the Contract;
and to carry out the Environmental Monitoring and Audit (EM&A) programme in fulfillment of the EIA Report’s EM&A
requirements and Contract No. 13/WSD/17 Specification requirements.
Pursuant to the
Environmental Impact Assessment Ordinance (EIAO), the Director of Environmental
Protection granted the Environmental Permit (No. EP-01/503/2015) and Variation
of Environmental Permit (No. EP-01/503/2015/B) to Water Supplies Department
(WSD); and granted the Further Environmental Permit (No. FEP-01/503/2015/B) to
AJCJV for the Contract.
2.
The
Reporting Scope
This is the 19th Quarterly EM&A Report for the Project which
summarizes the key findings of the EM&A programme
during the reporting period from 1 September 2024 to 30 November 2024.
3.
Project
Organization
The Project Organization structure for
Construction Phase is presented in Figure 1.1.
|
Figure 1.1 Project Organization Chart
Contact
details of the key personnel are presented in Table 1.1 below:
Table 1.1 Contact Details of Key Personnel
Party |
Position |
Name |
Telephone no. |
Remark |
Project Proponent |
SE/CM2 |
Milton Law |
2634-3573 |
/ |
Supervising Officer (Binnies Hong Kong Limited) |
Project Manager |
Augustine Li |
2608-7671 |
/ |
Chief Resident Engineer |
David Wong |
5229-8638 |
/ |
|
The Jardine Engineering Corporation, Limited, China State Construction Engineering (Hong Kong) Limited and Acciona Agua, S.A. Trading |
Project Manager |
Stephen Yeung |
2807-4665 |
/ |
Environmental Monitoring Manager |
Brian Kam |
9456-9541 |
/ |
|
Operation Manager |
Arnes Parra, Victor |
6468-6710 |
/ |
|
Environmental Monitoring Manager |
Tommy Law |
6468-1782 |
/ |
|
Aurecon Hong Kong Limited |
Environmental Team Leader |
Toby Wan |
9719-5422 |
/ |
Lam Environmental Services Limited |
Independent Environmental Checker (IEC) |
Serena Shek |
6149-6683 |
/ |
4.
Summary
of Construction Works
Details of the major construction activities undertaken in this reporting
period are shown as below. The construction programme
is presented in Appendix A.
Administration Building
§
External
wall aluminum features installation
§
Finishing
works for dog house
§ Minor Installation of building services,
electrical switchboards & cables, Pressure Test, T&C
§
Installation
of AP Door, Wall finishing, Ceiling, Tile, Internal partition wall, cat ladder,
wood decking;
§
Painting
works and external finishing works;
§
Minor
Installation of minor cables laying and termination, T&C, and electrical
switchboards & cables
· External wall aluminum features installation |
PWST ·
Water Test in Tank A ·
Waterproofing work at Roof
Slab on Tank A ·
Installation of building
services, electrical switchboards and cables · Installation of mechanical equipment, steel pipe, Pressure Test |
Chemical
building ·
Defect rectification · Repairing the defects inside the dangerous store |
Combined
Shaft & Pump House ·
Internal finishing, defect
rectification ·
Construction of hose reel
cabinet · T&C |
ActiDAFF ·
Installation of access
opening covers for filtered water tank ·
Carrying out finishing works
for staircase no. 3. ·
Minor Installation of
mechanical equipment, piping system · Minor Installation of building services, electrical switchboards and cables, Installation of FRP Enclosure System |
Product
Water Storage Tank Building · Minor Installation of building services, cable laying and termination, PV Panel Installation, Testing & Commissioning |
OSCG
Building ·
Protective Coating for DG
Rooms ·
Installation of Railing on
Brine Maker Tank ·
Minor Installation of
building services, cables and pipe works, T&C · Tank surface cleaning, T&C |
Reverse
Osmosis Building ·
Installation of Signage, AP
doors, sanitary fitting, sanitary ware in toilet, tiling work and water meter
cabinets · Minor Installation of building services, minor cable laying and termination, Testing & Commissioning, PV Panel Installation |
Post
Treatment Building ·
Installation of Cat Ladders
in Water Tanks ·
Placing Soil Mix at Roof ·
Curb Construction for Rescue
Opening at Water Tanks · Installation of building services, piping system, mechanical equipment and piping system, Pressure Test |
Inspection
gallery ·
Interior fitting out works
and painting works ·
Minor Installation of
building services, Lift Installation, T&C ·
Construction of roof tiling
works ·
Installation of steel
balustrade at roof ·
Installation of movement
joints ·
Construction of block works · Construction of roof tiling works |
RO and
Electrical Building ·
Installation of Glass House ·
Minor Installation of
building services, electrical switchboards and cables ·
Minor Installation of
mechanical pipework and raised Floor, · PV Panel Installation, T&C Chiller plant
& Main Electrical Building · Minor Installation of building services, electrical switchboards and cables, Pressure Test, T&C Others ·
Slope works* · Construction works of extended access road |
Remark: *The slope works were completed in
October 2024, and there were no site activities related to the slope works
conducted in November 2024.
1.
Summary
of Environmental Status
A
summary of the valid permits, licences, and /or
notifications on environmental protection for this Project is presented in Table
1.2.
Table 1.2 Summary of the Status of Valid
Environmental Licence, Notification, Permit and
Documentations
Permit/ Licences |
Valid Period |
Status |
Remark |
|
From |
To |
|||
Environmental Permit |
||||
EP – 503/2015/B |
Throughout the Contract |
Valid |
-Issued on 3 April 2024 |
|
FEP – 01/503/2015/B |
Throughout the Contract |
Valid |
-Issued on 3 April 2024 |
|
Notification of Construction Works under the Air Pollution Control (Construction Dust) Regulation (Form NA) |
||||
451539 |
Throughout the Contract |
Valid |
- |
|
Billing Account for Disposal of Construction Waste |
||||
7036276 |
Throughout the Contract |
Valid |
- |
|
Sludge (Special Waste) Disposal (Admission Ticket) |
||||
17674 |
12/06/2024 |
31/12/2024 |
Valid |
- |
17913 |
01/07/2024 |
24/12/2024 |
Valid |
- |
Chemical Waste Producer Registration |
||||
5213-839-A2987-01 |
Throughout the Contract |
Valid |
- |
|
Wastewater Discharge Licence (Land and Marine works) |
||||
WT00035775-2020 |
23/08/2021 |
31/07/2025 |
Valid |
- |
WT00044188-2023 |
16/06/2023 |
30/06/2028 |
Valid |
· For Plant T&C and operation. · Variation of sampling point S.P.1 is approved by the EPD on 25 June 2024. (EPD ref.: EP640/W3/D1358/462874). |
Construction Noise Permit |
||||
GW-RE0667-24 |
22/06/2024 |
20/12/2024 |
Valid |
- |
The status for all environmental
aspects is presented in Table 1.3
Table 1.3 Summary of Status
for Key Environmental Aspects under the EM&A Manual
Parameters |
Status |
Water Quality |
|
Baseline Monitoring under EM&A Manual |
The baseline water quality monitoring was conducted between 12 May 2020 and 6 June 2020 |
Construction Phase Impact Monitoring |
Ceased from 1 September 2023 |
TRC Monitoring for Main Disinfection |
Completed |
Operation Phase Impact Monitoring |
On-going |
Continuous Monitoring of Effluent Quality |
On-going, the plant was shut down from 7 a.m. to 7 p.m. on 3 November 2024. No effluent discharge from TKODP occurred during this period. Due to the plant has suspended production, there was no effluent discharge from the TKODP during the period between 24 November 2024 and 30 November 2024. |
Noise |
|
Baseline Monitoring |
The baseline noise monitoring result has been reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
Impact Monitoring |
Completed |
Waste Management |
|
Mitigation Measures in Waste Management Plan |
On-going |
Landfill Gas |
|
(Construction Phase) Regular Monitoring when Construction Works are within the 250m Consultation Zone |
In this reporting period, 132 times of Construction Phase landfill gas monitoring were recorded at Wan Po Road (Ch0+390 – Ch0+780) and (Ch0+400 - Ch1+200). No exceedance of action or limit level for methane, oxygen and carbon dioxide was observed. Construction Phase landfill gas monitoring were ceased from 31 October 2024. |
(Operation Phase) Monthly Monitoring for buildings, manholes and utility pits within the Project Site and along the fresh water mains |
In this reporting period, Operation Phase landfill gas monitoring was conducted on 25, 26, 27 September 2024, 9, 10 October 2024 and 14, 15 November 2024. No exceedances of action level and limit level was observed. |
Ecology (Coral) |
|
Operation phase Regular Coral Monitoring (Monthly) |
Operation phase coral monitoring works was conducted on 18 September 2024, 21 October 2024 and 11 November 2024. |
Parameters |
Status |
There is no AL/LL exceedance during the monitoring period. |
|
Ecology (Fishery) |
|
Operation phase Regular Fishery Monitoring (Seasonally) |
Operation phase fishery monitoring for wet season 2024 was carried out on 24 and 31 August 2024. |
Ecology (Landscape) |
|
Operation phase Landscape and Visual Site Inspection |
On-going |
Environmental Audit |
|
Site Inspection covering Measures of Air Quality, Noise Impact, Water Quality, Waste, Ecological Quality, Fisheries, Landscape and Visual |
On-going |
Other than the EM&A work by ET,
environmental briefings, trainings and regular environmental management
meetings were conducted, in order to enhance environmental awareness and
closely monitor the environmental performance of the contractors.
The EM&A programme
has been implemented in accordance with the recommendations presented in the
approved EIA Report and the EM&A Manual. A summary of implementation status
of the environmental mitigation measures for the construction phase and
operation phase of the Project during the reporting period is provided in Appendix
C.
|
Noise
1.
Monitoring
Requirements
To ensure no
adverse noise impact, construction noise monitoring is recommended to be
carried out within 300m radius from the nearby noise sensitive receivers
(NSRs), during construction phase. The NSRs selected as monitoring station are
(i) NSR4 – Creative Secondary School, (ii) NSR24 –
PLK Laws Foundation College, and (iii) NSR31 – School of Continuing and
Professional Studies – CUHK respectively.
No impact
construction noise monitoring was conducted in the reporting period due to the
overly distant monitoring station from the works location, where they were
farther than 1 km from the closet monitoring station NSR4 to the works
location.
2.
Monitoring
Parameters, Frequency and Duration
Construction noise
level would be measured in terms of the A-weighted equivalent continuous sound pressure level (LAeq). Leq 30min was used as the
monitoring parameter for the time period between 0700 and 1900 on normal weekdays. Table
2.1 summarizes the monitoring parameters, frequency and duration of the
impact noise monitoring.
Table 2.1 Noise Monitoring Parameters,
Time, Frequency and Duration
Time |
Duration |
Interval |
Parameters |
Daytime: 0700-1900 |
Day time: 0700-1900 (during normal weekdays) |
Continuously in Leq 5min/Leq 30min (average of 6 consecutive Leq 5min) |
Leq 30min L10 30min & L90 30min |
3.
Monitoring
Locations
The monitoring
locations should normally be made at a point 1m from the exterior of the NSRs
building façade and be at a position 1.2m above the ground. A correction of
+3dB(A) should be made to the free-field measurements.
According to the
environmental findings detailed in the EIA report and Baseline Monitoring
Report, the designated locations for the construction noise monitoring are
listed in Table 2.2 below.
Table 2.2 Noise Sensitive Receivers
NSR ID |
Noise Sensitive Receivers |
Monitoring Location |
Position |
NSR 4 |
Creative Secondary School |
Roof Floor |
1 m from facade |
NSR 24 |
PLK Laws Foundation College |
Pedestrian Road on Ground Floor |
Free-field |
NSR 31 |
School of Continuing and Professional Studies - CUHK |
Roof Floor |
1 m from facade |
The monitoring
locations should normally be made at a point 1m from the exterior of the NSRs
building façade and be at a position 1.2m above the ground. A correction of
+3dB(A) should be made to the free-field measurements. Three noise monitoring
locations for impact monitoring at the nearby sensitive receivers are shown in Figure
2.1-2.3.
|
||
Figure 2.1 NSR4 Creative Secondary School |
||
|
||
Figure 2.2 NSR24 PLK Laws Foundation College |
|
||
Figure 2.3 NSR31 School of Continuing and Professional Studies - CUHK |
4.
Action
and Limit Levels
The Action/Limit
Levels are in line with the criteria of Practice Note for Professional Persons
(ProPECC PN 2/93) “Noise from Construction Activities
– Non-statutory Controls” and Technical Memorandum on Environmental Impact
Assessment Process issued by HKSAR Environmental Protection Department [“EPD”]
under the Environmental Impact Assessment Ordinance, Cap 499,
S.16 are presented in Table 2.3.
Table 2.3 Action and Limit Levels for
Construction Noise Monitoring per EM&A Manual
Time Period |
Action Level |
Limit Level (dB(A)) |
0700-1900 on normal weekdays |
When one documented complaint is received from any one of the noise sensitive receivers |
§
70
dB(A) for school and
§ 65 dB(A) during examination period
Notes: Limits specified in the GW-TM and
IND-TM for construction and operation noise, respectively.
If exceedances
were found during noise monitoring, the actions in accordance with the Event
and Action Plan shall be carried out according to Appendix E.
5.
Monitoring
Results and Observations
Referring to EM&A manual Section
4.1.2, the impact noise monitoring should be carried out when there are
project-related construction activities undertaken within a radius of 300m from
the monitoring stations. As no Contract-related construction activities were
undertaken in the reporting period within a radius of 300m from the monitoring
stations of the Project site as shown in Figure 2.4, no impact noise
monitoring was conducted in the reporting period.
|
|
|
|
Figure 2.4 Site Layout Plan with Noise Sensitive
Receivers and Desalination Plant
|
WATER QUALITY
In accordance with the recommendations of
the EIA, water quality monitoring is required during dredging for the submarine
pipelines and, during operation phase. In addition, baseline water quality
monitoring was conducted prior to the commencement of marine construction
activities.
The following Section provides details of
the water quality monitoring to be undertaken by the Environmental Team (ET) to
verify the distance of sediment and brine plume dispersion and to identify
whether the potential exists for any indirect impacts to occur to ecological
sensitive receivers. The water quality monitoring programme
was carried out to allow any deteriorating water quality to be readily detected
and timely action taken to rectify the situation.
Water quality monitoring for the Project can be
divided into the following stages:
·
Dredging
activities during construction phase;
·
Discharge
of effluent from main disinfection during construction phase;
·
Operation
phase – first year upon operation; and,
·
Continuous
monitoring of effluent quality.
1.
Water
Quality Parameters
Parameters to be
measured in the marine water quality monitoring and the Continuous Monitoring
of Effluent Quality are listed in Table 3.1 and Table 3.2 respectively.
1.
Operation
phase Marine Water Quality Monitoring
The parameters
that have been selected for measurement in situ and in the laboratory are those
that were either determined in the EIA to be those with the most potential to
be affected by the operation works or are a standard check on water quality conditions.
Parameters measured in the monitoring are listed in Table 3.1
Table 3.1 Parameters measured in the
marine water quality monitoring
Parameters |
Unit |
Abbreviation |
In-situ measurements |
||
Dissolved oxygen |
mg/L |
DO |
Temperature |
oC |
- |
pH |
pH |
- |
Turbidity |
NTU |
- |
Salinity |
0/00 |
- |
Total Residual Chlorine |
mg/L |
TRC |
Total Residual Chlorine (Disinfection) |
mg/L |
TRC |
Laboratory measurements |
||
Suspended Solids |
mg/L |
SS |
Iron |
mg/L |
|
Anti-scalant |
mg/L |
- |
NOTE 1: Monitoring of Total Residual Chlorine
(Disinfection) will be conducted when cleaning and sterilization of the new
freshwater main is carried out.
2.
Continuous
Monitoring of Effluent Quality
The monitoring
requirement for the continuous effluent quality monitoring shall be conducted
in accordance with the effluent parameters and standards stipulated by the
Water Pollution Control Ordinance Discharge License (No.: WT00044188-2023)
conditions.
Table 3.2 Parameters measured in the Continuous Monitoring of Effluent
Quality
Parameters |
Unit |
Abbreviation |
In-situ measurements |
||
Temperature |
oC |
- |
pH |
pH |
- |
Salinity |
0/00 |
- |
Total Residual Chlorine |
mg/L |
TRC |
Laboratory measurements |
||
Suspended Solids |
mg/L |
SS |
Iron-Soluble |
mg/L |
Fe |
Total Inorganic Nitrogen |
mg/L |
- |
Total Phosphorus |
mg/L |
- |
Sodium Metabisulphite |
mg/L |
SMBS |
Anti-scalant as Reactive Phosphorus * |
mg/L |
PO4 as P- |
*Remark: Anti-scalant water quality testing will
only be conducted whenever anti-scalant dosage is
adopted.
In addition to the
water quality parameters, other relevant data were measured and recorded in
Water Quality Monitoring Logs, including the location of the sampling stations,
water depth, time, weather conditions, sea conditions, tidal stage, current
direction and velocity, special phenomena and work activities undertaken around
the monitoring and works area that may influence the monitoring results.
2.
Monitoring
Locations
1. Operation phase Marine Water Quality
Monitoring
The water quality monitoring locations are
detailed in Table 3.2 and shown in Figure 3.1 below.
Table 3.3 Location of Water Quality
Monitoring Station
Station |
Easting |
Northing |
Description |
CE |
843550 |
815243 |
Upstream control station at ebb tide |
CF |
846843 |
810193 |
Upstream control station at flood tide |
WSR1 |
846864 |
812014 |
Ecological sensitive receiver at Tung Lung Chau |
WSR2 |
847645 |
812993 |
Fisheries sensitive receiver at Tung Lung Chau |
WSR3 |
848023 |
813262 |
Ecological sensitive receiver at Tung Lung Chau |
WSR4 |
847886 |
814154 |
Ecological sensitive receiver at Tai Miu Wan |
WSR16 |
845039 |
815287 |
Ecological sensitive receiver at Fat Tong Chau |
WSR33 |
847159 |
814488 |
Ecological sensitive receiver at Tai Miu Wan |
WSR36 |
846878 |
814081 |
Ecological sensitive receiver at Kwun Tsai |
WSR37 |
846655 |
813810 |
Ecological sensitive receiver at Tit Cham Chau |
NF1 |
846542 |
813614 |
Edge of mixing zone, ~ 200m west of outfall diffuser |
NF2 |
846942 |
813614 |
Edge of mixing zone, ~ 200m east of outfall diffuser |
NF3 |
846742 |
813414 |
Edge of mixing zone, ~ 200m south of outfall diffuser |
|
Figure 3.1 Water Quality Monitoring Locations under EM&A Manual
2.
Continuous
Monitoring of Effluent Quality
In accordance with the discharge license, the Continuous Monitoring shall
be sampling at Brine Outfall Shaft.
|
|
|
Figure 3.2 Continuous Monitoring locations
3.
Monitoring
Equipment, Methodology and QA/QC Procedures
The monitoring methodology, equipment used, and QA/QC procedures could be
referred to Section 3.1.2 -3.1.4, 3.1.6-3.1.7 and 3.2 of the Monthly EM&A
Report.
4.
Action
and Limit levels
The Action and Limit Levels have been set based on the derivation criteria
specified in the EM&A Manual. The Action/Limit Levels have been derived and
are presented in Table 3.4 and Table 3.5.
1. Operation phase Marine Water Quality
Monitoring
Table 3.4 Derived Action and Limit Levels for Water Quality
Parameters |
Action |
Limit |
Operation Phase Monitoring |
||
DO in mg/L |
Surface and Middle |
Surface and Middle |
7.30 mg L-1 |
4 mg L-1 |
|
Bottom |
Bottom |
|
7.31 mg L-1 |
2 mg L-1 |
|
Tung Lung Chau Fish Culture Zone |
Tung Lung Chau Fish Culture Zone |
|
5.1 mgL-1 or level at control station |
5.0 mgL-1 or level at control station |
|
(Whichever the lower) |
(Whichever the lower) |
Parameters |
Action |
Limit |
Operation Phase Monitoring |
||
SS in mg/L (Depth- averaged) |
5.00 mg L-1 or 20% exceedance of value at any impact station compared with corresponding data from control station |
6.00 mg L-1 or 30% exceedance of value at any impact station compared with corresponding data from control station |
Turbidity in NTU (Depth- averaged) |
2.41 NTU or 20% exceedance of value at any impact station compared with corresponding data from control station |
2.84 NTU or 30% exceedance of value at any impact station compared with corresponding data from control station |
Salinity in PSU (Depth- averaged) |
34.28 PSU or 9% exceedance of value at any impact station compared with corresponding data from control station |
34.60 PSU or 10% exceedance of value at any impact station compared with corresponding data from control station |
Iron in mg/L (Depth- averaged) |
0.3 mg/L |
0.3 mg/L |
Total residual chlorine in mg/L |
0.01 mg/L |
0.01 mg/L |
Total residual chlorine in mg/L (Disinfection) |
0.1 mg/L |
0.1 mg/L |
Notes:
1.
"Depth-averaged"
is calculated by taking the arithmetic means of reading of all three depths.
2.
For
DO, non-compliance of the water quality limits occurs when monitoring result is
lower than the limits.
3.
For
Turbidity, SS, iron and Salinity, non-compliance of the water quality limits
occurs when monitoring result is higher than the limits.
2.
Continuous
Monitoring of Effluent Quality
Table 3.5 Derived Limit Levels for Water Quality
Parameters |
Limit |
Continuous Monitoring of Effluent Quality |
|
Flow Rate in m3/day |
216841 |
Temperature in °C |
Maximum 40 |
Salinity |
71347 |
SS in mg/L |
13 |
pH |
6-9 |
Iron in mg/L |
0.6 |
Total residual chlorine in mg/L |
0.1 |
Total Inorganic Nitrogen in mg/L |
2 |
Total Phosphorous in mg/L |
1 |
Parameters |
Limit |
Continuous Monitoring of Effluent Quality |
|
Sodium Metabisulphite in mg/L |
0.5 |
Anti scalant in mg/L* |
2.2 |
*Remark:
1. Anti-scalant water quality testing will only
be conducted whenever anti-scalant dosage is adopted.
5.
Monitoring
Results and Observations
Construction
Phase
Referring to EM&A Manual, the general
water quality monitoring should be carried out when there are marine-related
construction activities undertaken. General water quality monitoring at the ten
monitoring stations (CE, CF, WSR1, WSR2, WSR3, WSR4, WSR16, WSR33, WSR36 and WSR37)
was ceased from 1 September 2023 due to the completion of marine-related
construction works.
Operation
Phase
The first-year operation phase marine
water quality monitoring was carried out during the reporting period, the
monitoring was conducted at the thirteen monitoring stations (CE, CF, WSR1,
WSR2, WSR3, WSR4, WSR16, WSR33, WSR36, WSR37, NF1, NF2 and NF3). The Action and
Limit
Level would be referred to the approved EM&A Manual Table 5.4 First-year
Operation Phase Marine Water Monitoring.
The operation phase marine water
quality monitoring was conducted on 3, 7, 10, 12, 14, 17, 19,
21, 24, 26 and 28 September 2024
, 1, 3, 5, 8, 10, 12, 15, 17, 19, 22, 24, 26, 29 and 31 October 2024
and 2, 5, 7, 9, 12, 16, 19, 21, 23, 26, 28 and 30 November 2024. The result of the reporting quarterly is
presented in Table 3.6.
Thirty-six (36) of the operation phase marine water quality monitoring results of SS
obtained had exceeded the Action Level. Eighty-five (85) of the operation phase water quality monitoring results of SS obtained
during the reporting period had exceeded the Limit Level.
Investigation on the reason of exceedance
has been carried out, where the exceedances of SS were concluded to be
unrelated to the Contract as detailed in the Incident Reports on Action Level
or Limit Level. Summary of the exceedance is presented in Appendix E.
Continuous
Monitoring of Effluent Quality
Continuous Monitoring of Effluent Quality
was conducted sampling point in the reporting period. No exceedance of the sampling was obtained during the
reporting period had exceeded the Limit Level. The detailed results are
summarized in Table 3.7.
The plant was shut down from 7 a.m. to 7
p.m. on 3 November 2024. No effluent discharge from TKODP occurred during this
period.
Due to the plant has suspended production,
there was no effluent discharge from the TKODP during the period between 24
November 2024 and 30 November 2024.
Table 3.6 Summary of
Operation Phase Water Quality Monitoring Results
Location |
Parameter |
|||||||||||||||||||||||||||
Salinity (ppt) |
Dissolved Oxygen (mg/L) |
pH |
Turbidity (NTU) |
Suspended Solids (mg/L) |
Temp. (oC) |
TRC (mg/L) |
Iron (mg/L) |
|||||||||||||||||||||
Surface & Middle |
Bottom |
|||||||||||||||||||||||||||
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
||
CE |
Avg. |
32.49 |
32.40 |
32.06 |
8.71 |
8.90 |
8.48 |
8.73 |
8.89 |
8.51 |
8.14 |
8.19 |
8.18 |
2.52 |
2.44 |
2.41 |
3.41 |
4.60 |
3.29 |
28.84 |
28.64 |
26.55 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
Min. |
31.63 |
30.94 |
31.27 |
8.12 |
7.90 |
8.05 |
8.04 |
7.89 |
8.05 |
8.03 |
8.08 |
8.00 |
1.98 |
2.01 |
2.05 |
2.50 |
2.50 |
2.50 |
27.94 |
27.78 |
25.10 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
Max.. |
33.66 |
33.12 |
33.14 |
9.54 |
9.64 |
8.98 |
9.58 |
9.67 |
8.96 |
8.27 |
8.31 |
8.36 |
2.85 |
2.79 |
2.69 |
7.00 |
37.00 |
6.00 |
29.85 |
29.38 |
27.57 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
CF |
Avg. |
32.19 |
32.55 |
32.14 |
8.62 |
8.83 |
8.69 |
8.60 |
8.82 |
8.69 |
8.27 |
8.24 |
8.14 |
2.40 |
2.28 |
2.32 |
3.55 |
7.68 |
3.76 |
28.94 |
28.65 |
26.41 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
Min. |
31.20 |
31.71 |
31.52 |
7.91 |
7.98 |
8.12 |
7.92 |
7.80 |
8.04 |
8.12 |
8.09 |
7.94 |
2.13 |
1.86 |
2.06 |
2.00 |
2.50 |
2.50 |
28.02 |
27.81 |
25.06 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
Max.. |
33.55 |
33.56 |
33.23 |
9.57 |
9.84 |
9.21 |
9.51 |
9.74 |
9.26 |
8.40 |
8.40 |
8.41 |
2.96 |
2.68 |
2.66 |
9.00 |
86.00 |
8.00 |
29.98 |
29.38 |
27.59 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
WSR1 |
Avg. |
31.97 |
32.21 |
32.07 |
8.59 |
8.67 |
8.48 |
8.60 |
8.67 |
8.50 |
8.19 |
8.24 |
8.17 |
1.71 |
1.83 |
1.77 |
3.30 |
7.90 |
3.44 |
28.91 |
28.60 |
26.55 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
Min. |
31.33 |
31.41 |
31.40 |
7.81 |
7.70 |
7.96 |
7.80 |
7.72 |
7.95 |
8.08 |
8.05 |
7.98 |
1.32 |
1.30 |
1.34 |
2.50 |
2.50 |
2.50 |
28.14 |
27.73 |
25.25 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
Max.. |
33.09 |
33.04 |
32.42 |
9.08 |
9.36 |
9.22 |
9.13 |
9.40 |
9.33 |
8.31 |
8.40 |
8.32 |
2.10 |
2.22 |
2.18 |
6.00 |
65.00 |
9.00 |
29.69 |
29.26 |
27.81 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
WSR2 |
Avg. |
32.34 |
32.52 |
32.07 |
8.66 |
8.87 |
8.71 |
8.66 |
8.85 |
8.73 |
8.20 |
8.21 |
8.14 |
1.84 |
1.65 |
1.73 |
3.28 |
5.01 |
3.38 |
28.92 |
28.59 |
26.49 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
Min. |
31.54 |
31.59 |
31.05 |
7.52 |
7.99 |
7.91 |
7.53 |
7.95 |
7.91 |
8.05 |
8.04 |
8.00 |
1.52 |
1.34 |
1.40 |
2.50 |
2.50 |
2.50 |
28.12 |
27.69 |
25.00 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
Max.. |
33.17 |
33.59 |
33.30 |
9.66 |
9.64 |
9.15 |
9.72 |
9.65 |
9.25 |
8.32 |
8.33 |
8.30 |
2.17 |
2.22 |
2.20 |
6.00 |
63.00 |
10.00 |
29.74 |
29.30 |
27.60 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
WSR3 |
Avg. |
32.34 |
32.52 |
32.13 |
8.75 |
8.91 |
8.68 |
8.74 |
8.90 |
8.69 |
8.23 |
8.22 |
8.16 |
1.77 |
1.68 |
1.76 |
3.44 |
4.10 |
3.62 |
28.82 |
28.59 |
26.47 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
Min. |
30.93 |
31.52 |
31.29 |
7.54 |
8.16 |
8.21 |
7.58 |
8.13 |
8.28 |
7.98 |
8.03 |
7.98 |
1.45 |
1.22 |
1.42 |
2.50 |
2.50 |
2.50 |
27.85 |
27.91 |
24.94 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
Max.. |
33.59 |
33.05 |
32.90 |
9.46 |
9.86 |
9.24 |
9.57 |
9.86 |
9.25 |
8.39 |
8.39 |
8.36 |
2.21 |
2.08 |
2.09 |
8.00 |
12.00 |
12.00 |
29.80 |
29.22 |
27.80 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
WSR4 |
Avg. |
32.24 |
32.52 |
32.07 |
8.61 |
8.96 |
8.52 |
8.61 |
8.99 |
8.52 |
8.20 |
8.21 |
8.15 |
1.68 |
1.81 |
1.86 |
3.63 |
4.40 |
3.53 |
28.91 |
28.64 |
26.56 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
Min. |
31.27 |
31.56 |
31.00 |
8.08 |
7.75 |
8.02 |
8.15 |
7.78 |
8.00 |
8.10 |
8.00 |
7.91 |
1.34 |
1.31 |
1.47 |
2.50 |
2.00 |
2.50 |
27.88 |
27.93 |
25.15 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
Max.. |
33.62 |
33.33 |
32.84 |
9.27 |
9.60 |
9.27 |
9.36 |
9.61 |
9.19 |
8.28 |
8.41 |
8.33 |
1.96 |
2.16 |
2.21 |
10.00 |
13.00 |
7.00 |
29.74 |
29.33 |
27.71 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
WSR16 |
Avg. |
32.24 |
32.35 |
32.24 |
8.56 |
8.76 |
8.62 |
8.55 |
8.75 |
8.63 |
8.21 |
8.20 |
8.18 |
1.76 |
1.76 |
1.67 |
3.48 |
4.29 |
4.07 |
28.93 |
28.58 |
26.51 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
Min. |
31.21 |
31.24 |
31.20 |
7.68 |
8.14 |
8.09 |
7.73 |
8.12 |
8.05 |
8.06 |
8.06 |
7.94 |
1.34 |
1.44 |
1.37 |
2.50 |
2.50 |
2.50 |
27.88 |
27.72 |
25.19 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
Max.. |
32.97 |
33.13 |
33.07 |
9.52 |
9.49 |
9.05 |
9.39 |
9.55 |
9.11 |
8.40 |
8.34 |
8.33 |
2.10 |
2.14 |
2.10 |
7.00 |
11.00 |
9.00 |
29.83 |
29.19 |
27.44 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
WSR33 |
Avg. |
32.29 |
32.42 |
32.10 |
8.66 |
8.59 |
8.47 |
8.66 |
8.59 |
8.49 |
8.26 |
8.21 |
8.20 |
1.72 |
1.74 |
1.77 |
3.52 |
4.03 |
3.53 |
28.93 |
28.66 |
26.55 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
Min. |
31.64 |
30.89 |
31.27 |
7.77 |
7.82 |
7.83 |
7.80 |
7.89 |
7.97 |
8.12 |
8.03 |
7.92 |
1.33 |
1.32 |
1.23 |
2.50 |
2.50 |
2.50 |
27.83 |
28.01 |
25.14 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
Max.. |
32.90 |
33.56 |
33.09 |
9.47 |
9.16 |
9.28 |
9.49 |
9.15 |
9.38 |
8.37 |
8.34 |
8.36 |
2.13 |
2.19 |
2.20 |
8.00 |
14.00 |
8.00 |
30.05 |
29.32 |
27.88 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
WSR36 |
Avg. |
32.27 |
32.34 |
31.80 |
8.44 |
8.93 |
8.66 |
8.45 |
8.94 |
8.68 |
8.22 |
8.21 |
8.16 |
1.82 |
1.77 |
1.78 |
3.64 |
3.83 |
3.69 |
28.97 |
28.59 |
26.46 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
Min. |
30.94 |
31.31 |
31.17 |
7.73 |
7.73 |
8.14 |
7.73 |
7.75 |
8.21 |
8.05 |
8.09 |
7.97 |
1.54 |
1.34 |
1.46 |
2.50 |
2.50 |
2.50 |
28.05 |
27.82 |
24.84 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
Max.. |
33.51 |
33.14 |
32.54 |
9.29 |
9.68 |
9.14 |
9.32 |
9.66 |
9.13 |
8.35 |
8.35 |
8.32 |
2.19 |
2.15 |
2.13 |
7.00 |
9.00 |
11.00 |
29.87 |
29.20 |
27.36 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
WSR37 |
Avg. |
31.88 |
32.43 |
32.00 |
8.56 |
8.83 |
8.52 |
8.59 |
8.84 |
8.52 |
8.22 |
8.23 |
8.20 |
1.77 |
1.78 |
1.76 |
4.25 |
3.85 |
4.46 |
28.93 |
28.62 |
26.55 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
Min. |
30.72 |
31.23 |
31.04 |
8.08 |
7.90 |
7.75 |
8.10 |
7.93 |
7.72 |
8.07 |
8.12 |
8.04 |
1.29 |
1.37 |
1.48 |
2.50 |
2.00 |
2.50 |
27.77 |
28.05 |
25.13 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
Max.. |
33.21 |
33.49 |
32.79 |
9.42 |
9.41 |
9.10 |
9.47 |
9.49 |
9.18 |
8.34 |
8.40 |
8.32 |
2.12 |
2.14 |
2.21 |
8.00 |
11.00 |
13.00 |
30.12 |
29.30 |
27.88 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
Location |
Parameter |
|||||||||||||||||||||||||||
Salinity (ppt) |
Dissolved Oxygen (mg/L) |
pH |
Turbidity (NTU) |
Suspended Solids (mg/L) |
Temp. (oC) |
TRC (mg/L) |
Iron (mg/L) |
|||||||||||||||||||||
Surface & Middle |
Bottom |
|||||||||||||||||||||||||||
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
Sep- 2024 |
Oct- 2024 |
Nov- 2024 |
||
NF1 |
Avg. |
32.37 |
32.35 |
32.27 |
8.70 |
8.76 |
8.67 |
8.69 |
8.75 |
8.68 |
8.21 |
8.21 |
8.16 |
1.81 |
1.77 |
1.74 |
3.79 |
4.19 |
3.47 |
28.88 |
28.64 |
26.51 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
Min. |
31.55 |
31.55 |
31.59 |
7.87 |
8.27 |
8.11 |
7.81 |
8.22 |
8.11 |
8.02 |
8.11 |
7.96 |
1.58 |
1.33 |
1.39 |
2.50 |
2.50 |
2.50 |
27.99 |
27.76 |
25.04 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
Max.. |
33.04 |
33.36 |
33.24 |
9.54 |
9.28 |
9.21 |
9.42 |
9.22 |
9.14 |
8.32 |
8.39 |
8.30 |
2.08 |
2.18 |
2.04 |
8.00 |
13.00 |
9.00 |
29.70 |
29.38 |
27.87 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
NF2 |
Avg. |
32.26 |
32.31 |
32.05 |
8.53 |
8.76 |
8.49 |
8.54 |
8.75 |
8.48 |
8.19 |
8.21 |
8.13 |
1.73 |
1.71 |
1.71 |
3.77 |
4.00 |
4.14 |
28.96 |
28.61 |
26.49 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
Min. |
31.51 |
31.34 |
31.38 |
7.89 |
8.19 |
7.99 |
7.84 |
8.19 |
8.02 |
8.01 |
8.05 |
7.99 |
1.39 |
1.25 |
1.43 |
2.50 |
2.00 |
2.50 |
27.94 |
27.75 |
25.14 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
Max.. |
32.90 |
33.27 |
32.84 |
9.14 |
9.35 |
9.24 |
9.19 |
9.33 |
9.11 |
8.33 |
8.39 |
8.28 |
2.09 |
2.20 |
2.14 |
7.00 |
11.00 |
15.00 |
29.98 |
29.20 |
27.57 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
NF3 |
Avg. |
32.18 |
32.25 |
32.11 |
8.79 |
8.75 |
8.72 |
8.82 |
8.73 |
8.70 |
8.21 |
8.24 |
8.15 |
1.66 |
1.83 |
1.67 |
3.83 |
3.64 |
3.78 |
28.93 |
28.60 |
26.50 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
Min. |
31.14 |
31.45 |
31.25 |
7.97 |
7.81 |
8.05 |
7.98 |
7.78 |
8.08 |
8.04 |
8.07 |
7.98 |
1.41 |
1.47 |
1.42 |
2.50 |
2.00 |
2.50 |
28.04 |
27.81 |
24.99 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
|
Max.. |
32.92 |
33.08 |
32.83 |
9.21 |
9.61 |
9.33 |
9.31 |
9.55 |
9.33 |
8.34 |
8.36 |
8.25 |
1.96 |
2.22 |
2.22 |
8.00 |
11.00 |
10.00 |
29.77 |
29.30 |
27.74 |
<0.01 |
<0.01 |
<0.01 |
<0.1 |
<0.1 |
<0.1 |
Table 3.7 Summary of Continuous Effluent
Monitoring Results
Salinity (ppt) |
pH |
Temp (°C) |
Total Residual Chlorine (mg/L) |
Suspended Solids (mg/L) |
Total Inorganic Nitrogen (mg/L) |
Total Phosphorus (mg/L) |
*Sodium Metabisulphite (mg/L) |
Iron (mg/L) |
||
Sep-2024 |
Avg. |
54.88 |
7.68 |
29.67 |
0.03 |
3.00 |
0.54 |
0.01 |
<2 |
<0.1 |
Min. |
51.05 |
7.27 |
24.50 |
0.00 |
<2 |
0.08 |
<0.01 |
<2 |
<0.1 |
|
Max. |
58.25 |
7.85 |
31.06 |
0.20 |
2 |
0.49 |
0.02 |
<2 |
<0.1 |
|
Oct-2024 |
Avg. |
55.19 |
7.55 |
27.77 |
0.04 |
3.00 |
0.54 |
0.01 |
<2 |
<0.1 |
Min. |
51.05 |
7.14 |
24.50 |
0.01 |
<2 |
0.08 |
<0.01 |
<2 |
<0.1 |
|
Max. |
58.26 |
7.86 |
31.15 |
0.07 |
2 |
0.49 |
0.02 |
<2 |
<0.1 |
|
Nov-2024 |
Avg. |
53.82 |
7.32 |
26.01 |
0.04 |
2.00 |
0.21 |
0.01 |
<2 |
<0.1 |
Min. |
49.80 |
6.68 |
24.01 |
0.01 |
<2 |
0.02 |
<0.01 |
<2 |
<0.1 |
|
Max. |
58.57 |
8.00 |
28.60 |
0.09 |
2 |
0.42 |
0.02 |
<2 |
<0.1 |
* Remark: As confirmed by various
laboratories in Hong Kong, the lowest detection limit for Sodium Metabisulphite is <2 mg/L. Due to the limitation of the
laboratory, the lowest result for Sodium Metabisulphite
will only be shown as < 2 mg/L.
|
|
|
Waste
The waste generated from this Project
includes inert construction and demolition (C&D) materials, and non-inert
C&D materials. Non-inert C&D materials are made up of general refuse,
vegetative wastes, and recyclable wastes such as plastics and paper/cardboard
packaging waste. Steel materials generated from the project are also grouped
into non-inert C&D materials as the materials were not disposed of with
other inert C&D materials. With reference to relevant handling records and
trip tickets of this Project, the quantities of different types of waste
generated in the reporting period are summarized in Table 4.1. Details
of cumulative waste management data are presented as a waste flow table in Appendix
F.
Table
4.1 Quantities of Waste Generated from the Project during reporting period
Reporting Months |
Actual Quantities of Inert C&D Materials Generated Monthly |
Actual Quantities of C&D Wastes Generated Monthly |
|||||||||
Total Quantity Generated |
Hard Rock and Large Broken Concrete |
Reused in the Contract |
Reused in other Projects |
Disposed as Public Fill |
Imported Fill |
Metals |
Paper / cardboard packaging |
Plastics (1) |
Chemical Waste |
Others, e.g. general refuse |
|
(in ,000kg) |
(in ,000kg) |
(in ,000kg) |
(in ,000kg) |
(in ,000kg) |
(in ,000kg) |
(in ,000kg) |
(in ,000kg) |
(in ,000kg) |
(in ,000kg) |
(in ,000kg) |
|
Sep 2024 |
834.890 |
0.000 |
0.000 |
0.000 |
834.890 |
0.000 |
0.000 |
0.000 |
0.000 |
0.805 |
27.020 |
Oct 2024 |
78.140 |
0.000 |
0.000 |
0.000 |
78.140 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
71.810 |
Nov 2024 |
237.790 |
0.000 |
0.000 |
0.000 |
237.790 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
62.300 |
Notes: (1) Plastics refer to plastic bottles /
containers, plastic sheets / foam from packaging material
|
LANDFILL GAS MONITORING
1.
Monitoring
Requirement
In accordance with
Section 11 of the EM&A Manual, monitoring of landfill gas is required for
construction works within the 250m Consultation Zone. Part of the desalination
plant and the indicative area of natural slope mitigation works fall within the
SENT Landfill Extension Consultation Zone; and part of the 1,200 mm diameter
fresh water mains along Wan Po Road falls within the SENT Landfill and SENT
Landfill Extension Consultation Zones, TKO Stage II/III Restored Landfill and
TKO Stage I Restored Landfill Consultation Zones.
Routine monitoring
is required at buildings within the Project Site and consultation zones. The
monitoring frequency will be monthly for the first year of operation.
For the manholes
and utility pits within the Project Site and along the fresh water mains, each
manhole/ utility pit should be monitored with two measurements (at mid depth
and base). Each measurement should be monitored for a minimum of 10 minutes. A
steady reading and peak reading should be recorded at each manhole/ utility pit
and for each measurement.
Monitoring of
oxygen, methane, carbon dioxide and barometric pressure would be performed
monthly during the operation phase.
2.
Monitoring
Location
Monitoring of
oxygen, methane, carbon dioxide and barometric pressure was performed for
excavations at 1m depth or more within the consultation Zone.
During
construction of works within the consultation zones, excavations of 1m depth or
more was monitored:
§
At
the ground surface before excavation commences;
§
Immediately
before any worker enters the excavation;
§
At
the beginning of each working day for the entire period the excavation remains
open; and
§
Periodically
through the working day whilst workers are in the excavation.
For excavations between 300mm and 1m deep,
measurements should be carried out:
§
Directly
after the excavation has been completed; and
§
Periodically
whilst the excavation remains open.
3.
Monitoring
Parameters
LFG monitoring was carried out to identify any migration between the
landfill and the Project and to ensure the safety of the construction,
operation and maintenance personnel working on- site, visitors and any other
person within the Project area.
The
following parameters were monitored:
§
Methane.
§
Oxygen.
§
Carbon
Dioxide.
§
Barometric
Pressure.
4.
Monitoring
Location
The
area required to be monitored for landfill gas in the reporting period is shown
in Figure 5.1,
5.2 and 5.3.
|
|
|
Figure 5.1 Overview of the SENT Extension Consultation Zone and the Project
Site Area
29
The copyright of this document is owned by Acuity
Sustainability Consulting Limited. It may not be reproduced except with prior
written approval from the Company.
|
|
|
Figure 5.2 Landfill Gas Monitoring Location for
Building
|
|
Figure 5.3 Landfill Gas Monitoring Location for
Manholes/Pits
5.
Action
and Limit Level
Action
and Limit Level are provided in Table 5.1.
Table
5.1 Action and Limit Level for Landfill Gas Monitoring
Parameters |
Action Level |
Limit Level |
Oxygen (O2) |
<19% O2 |
<19% O2 |
Methane (CH4) |
>10% LEL |
>20% LEL |
Carbon Dioxide (CO2) |
>0.5% CO2 |
>1.5% CO2 |
6.
Monitoring
Equipment
The monitoring
equipment used during the construction phase in this reporting period is
detailed in Section 5.8 of the Construction Phase Monthly EM&A Report and
the monitoring equipment used during the operation phase in the reporting
period is detailed in Section 4.7 – 4.8 of the Operation Phase Monthly EM&A
Report.
7.
Monitoring
Results and Observations
In this reporting period, 132 times of Construction Phase landfill gas monitoring were
recorded at Wan Po Road (Ch0+390 – Ch0+780) and (Ch0+400 - Ch1+200). No
exceedance of action and limit levels for methane, oxygen and carbon dioxide
was observed. Monitoring was conducted during excavations at 1m depth or more
within the consultation zone and whenever workers entered the excavation on the
day. The landfill gas monitoring was ceased from 31 October 2024.
In this reporting period, Operation Phase
landfill gas monitoring was conducted on 25, 26 and 27 September 2024, 9 and 10 October 2024
and 14 and 15 November 2024. No exceedances of action level and limit level was observed.
|
SUMMARY OF EXCEEDANCE, COMPLAINT, NOTIFICATION OF SUMMONS AND
Prosecutions
The Environmental Complaint
Handling Procedure is shown in below Figure 6.1:
|
|
Figure 6.1 Environmental
Complaint Handling Procedures
No noise monitoring was conducted during
the reporting period since there are no Contract- related construction
activities undertaken within a radius of 300m from the monitoring locations. No
Action Level exceedance was recorded during the reporting period.
Referring to EM&A Manual, the general
water quality monitoring should be carried out when there are marine-related
construction activities undertaken. General water quality monitoring at the ten
monitoring stations (CE, CF, WSR1, WSR2, WSR3, WSR4, WSR16, WSR33, WSR36 and
WSR37) was ceased from 1 September 2023 due to the completion of marine-related
construction works.
Thirty-six (36) of the operation phase water quality monitoring results of SS obtained had
exceeded the Action Level. Eighty-five
(85) of the
operation phase water quality monitoring results of SS obtained during the
reporting period had exceeded the Limit Level. After investigation, all
exceedances were considered non-project related.
In this reporting period, 132 times of Construction Phase landfill gas monitoring were
recorded at Wan Po Road (Ch0+390 – Ch0+780) and (Ch0+400 - Ch1+200). No
exceedance of action and limit levels for methane, oxygen and carbon dioxide
was observed. Monitoring was conducted during excavations at 1m depth or more
within the consultation zone and whenever workers entered the excavation on the
day. The landfill gas monitoring was ceased from 31 October 2024.
In this reporting period, Operation Phase
landfill gas monitoring was conducted on 25, 26 and 27 September 2024, 9 and 10 October 2024
and 14, 15 November 2024. No
exceedances of action level and limit level was observed.
Operation phase monthly coral monitoring
was conducted during the reporting period on 18 September 2024, 21 October 2024 and
11 November 2024. No
sediment, bleaching or increased mortality in the general condition of all
other tagged coral colonies were observed during the monthly operation phase
monitoring period. No deterioration of the coral community was observed in the
ecological monitoring results when compared with the baseline ecological
monitoring results. There is no AL/LL exceedance during the monitoring period.
Operation phase fishery monitoring for wet
season 2024 was carried out on 24 and 31 August 2024. The detail of the monitoring was presented in
the 4th Operation Phase Monthly EM&A Report.
Continuous Monitoring of Effluent Quality
was conducted sampling point from 1 September 2024 to 30 November 2024. No exceedance of the sampling was obtained during
the reporting period had exceeded the Limit Level.
The plant was shut down from 7 a.m. to 7
p.m. on 3 November 2024. No effluent discharge from TKODP occurred during this
period.
Due to the plant has suspended production,
there was no effluent discharge from the TKODP during the period between 24
November 2024 and 30 November 2024.
ET will keep closely monitoring the
performance of Contractor, implementation of water quality mitigation measure
and other contamination issue around the Project site, to ensure the EM&A
requirement is properly implemented.
No environmental complaint was received in the reporting
period. No notification of summons and prosecution was received in the
reporting period.
Statistics on complaints and
regulatory compliance are summarized in Appendix G.
|
EM&A SITE INSPECTION
Site inspections were carried out on a
weekly basis to monitor the implementation of proper environmental pollution
control and mitigation measures under the Contract.
No trespass by the Contractor outside the
works area of the Project and Clear Water Bay Country Park, and no damage to
the vegetation and rocky shore outside the Project area was observed in the
reporting period. All plants were observed to be in satisfactory condition in
the reporting period.
ET weekly site inspections were carried out by ET
on 3, 10, 17 and
24 September 2024, 3, 8, 15,
22 and
28 October 2024 and 5, 14, 18 and 26 November 2024.
Joint site inspections were also carried
out by ET and IEC on 24 September 2024, 28 October 2024 and 26 November 2024.
According to the EIA Study Report,
Environmental Permit, contract documents and EM&A Manual, the mitigation
measures detailed in the documents should be implemented as much as practical
during the reporting period. An updated Implementation Status of Environmental
Mitigation Measures (EMIS) is provided in Appendix C.
|
CONCLUSIONS AND RECOMMENDATIONS
This is the 19th Quarterly EM&A Report for the Project which
summarizes the key findings of the EM&A programme
during the reporting period from 1 September 2024 to 30 November 2024, in accordance with the EM&A Manual and the
requirement under FEP-01/503/2015/B.
According to the contractor’s information,
the works of TKODP were substantially completed on 30 June 2024 and the plant
commenced the operation phase on 1 July 2024. The outstanding construction
works were being carried out during this reporting period.
No noise monitoring was conducted in the
reporting period due to the over distant monitoring station from the works
location.
Referring to EM&A Manual, the general
water quality monitoring should be carried out when there are marine-related
construction activities undertaken. General water quality monitoring at the ten
monitoring stations (CE, CF, WSR1, WSR2, WSR3, WSR4, WSR16, WSR33, WSR36 and
WSR37) was ceased from 1 September 2023 due to the completion of marine-related
construction works.
Thirty-six (36) of the operation phase water quality monitoring results of SS obtained had
exceeded the Action Level. Eighty-five
(85) of the
operation phase water quality monitoring results of SS obtained during the
reporting period had exceeded the Limit Level. After investigation, all
exceedances were considered non-project related.
Continuous Monitoring of Effluent Quality
was conducted sampling point 1 September 2024 to 30 November 2024. No exceedance of the sampling was obtained during
the reporting period had exceeded the Limit Level.
The plant was shut down from 7 a.m. to 7
p.m. on 3 November 2024. No effluent discharge from TKODP occurred during this
period.
Due to the plant has suspended production,
there was no effluent discharge from the TKODP during the period between 24
November 2024 and 30 November 2024.
In this reporting period, 132 times of Construction Phase landfill gas monitoring were
recorded at Wan Po Road (Ch0+390 – Ch0+780) and (Ch0+400 - Ch1+200). No
exceedance of action and limit levels for methane, oxygen and carbon dioxide
was observed. Monitoring was conducted during excavations at 1m depth or more
within the consultation zone and whenever workers entered the excavation on the
day. The landfill gas monitoring was ceased from 31 October 2024.
In this reporting period, Operation Phase
landfill gas monitoring was conducted on 25, 26, 27 September 2024, 9, 10 October 2024 and
14, 15 November 2024. No
exceedances of action level and limit level was observed.
Operation phase monthly coral monitoring was
conducted during the reporting period on 18 September 2024, 21 October 2024 and 11 November
2024. No sediment, bleaching
or increased mortality in the general condition of all other tagged coral
colonies were observed during the monthly operation phase monitoring period. No
deterioration of the coral community was 36
The copyright of this document is owned by Acuity
Sustainability Consulting Limited. It may not be reproduced except with prior
written approval from the Company.
observed in the ecological monitoring
results when compared with the baseline ecological monitoring results. There is
no AL/LL exceedance during the monitoring period.
Operation phase fishery monitoring for wet
season 2024 was carried out on 24 and 31 August 2024. The detail of the monitoring was presented in
the 4th Operation Phase Monthly EM&A Report.
Weekly environmental site inspection was
conducted during the reporting period. Minor deficiency was observed during
site inspection and was rectified. The environmental performance of the project
was therefore considered satisfactory.
According to the environmental site
inspections performed in the reporting period, the Contractor is reminded to
pay attention on maintaining proper materials storage.
Two (2) environmental
complaints were received of Contract since commencement of the Contract. No
notification of summons or prosecution was received of the Contract since
commencement of the Contract quarter.
The ET will keep track on the construction
and operation works to confirm compliance of environmental requirements and the
proper implementation of all necessary mitigation measures.
|
|
Contract
No. 13/WSD/17
Design, Build and Operate First
Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report
Appendix A
Master Programme
13/WSD/17 Design, Build and Operate Stage 1 of Tesung Kwan O Desalination Plant 31 Jul 24
Activity ID Activity Name Baseline
Baseline Start Baseline Finish Remaining
Actual / Planned
Actual / Planned
Actual %
Variance
Total
2020 2021 2022 2023 2024
Project Programme
Updated as at 31 Jul 2024
Project Programme
Updated as at 31 Jul 2024
Key Dates
Key Dates
Commencement and Completion Date
Commencement and Completion Date
Duration
Duration
Start
Finish
Complete
Finish Date
Float N D J F M A M J J A S O N D J F M A M J J A S O N
D J
F M A M J
J A S O N D J
F M A M J J A S O N D J
F M A M J J A S O N D
KD0000100
Letter of Acceptance
0 15-Nov-19
0 15-Nov-19 A
100% 0
Letter of Acceptance
KD0000110
Commencement of the Works
0 30-Dec-19
0 30-Dec-19 A
100% 0
Commencement of the Works
KD0000120
Original Completion of the Works (1170 Days)
0 13-Mar-23 0
1. Mar-23 A
100% 0
Original Completion of the Works (1170 Days)
KD0000130
Revised Completion of the Works (324 Days EOT Granted) 0
0 14-Mar-23 A
31-Jan-24 A
100%
Revised Completion of the Work
KD0000510
Planned Completion of the Works
0 0 30-Jun-24 A
100%
Planned Comple
Possession of Site
Possession of Site
KD0000200
Possession of First Stage Portion A
0 30-Dec-19
0 30-Dec-19 A
100% 0
Possession of First Stage Portion A
KD0000210
Possession of First Stage Portion B
0 30-Dec-19
0 30-Dec-19 A
100% 0
Possession of First Stage Portion B
KD0000220
Possession of Area for Access Road
0 30-Dec-19
0 30-Dec-19 A
100% 0
Possession of Area for Access Road
KD0000230
Possession of Temporary Works Area 1
0 30-Dec-19
0 30-Dec-19 A
100% 0
Possession of Temporary Works Area 1
KD0000240
Possession of Temporary Works Area 2
0 30-Dec-19
0 30-Dec-19 A
100% 0
Possession of Temporary Works Area 2
KD0000250
Possession of Temporary Works Area 3
0 30-Dec-19
0 30-Dec-19 A
100% 0
Possession of Temporary Works Area 3
KD0000260
Possession of Temporary Works in Clear Water Bay Country Park
0 30-Dec-19
0 30-Dec-19 A
100% 0
Possession of Temporary Works in Clear Water Bay Country Park
Executive Summaries
Preliminary Setup
Civil Design AIP and DDA
M&E Design AIP and DDA
Executive Summaries Preliminary Setup
ES0001000 |
Mobilization and Preliminary Set Up |
191 |
30-Dec-19 |
07-Jul-20 |
0 |
30-Dec-19 A |
20-Jul-20 A |
100% |
-13 |
Civil Design AIP and DDA |
|||||||||
ES0001010 |
AIP Civil Design Submission and Approval |
330 |
30-Dec-19 |
23-Nov-20 |
0 |
30-Dec-19 A |
31-Aug-20 A |
100% |
84 |
ES0001020 |
DDA Civil Design Submission and Approval |
414 |
28-Feb-20 |
16-Apr-21 |
0 |
22-Jan-20 A |
01-Sep-21 A |
100% |
-138 |
M&E Design AIP and DDA |
|||||||||
ES0002000 |
M&E AIP Process Mechanical Submission and Approval |
477 |
30-Dec-19 |
19-Apr-21 |
0 |
30-Dec-19 A |
22-Dec-20 A |
100% |
118 |
ES0002010 |
M&E DDA Process Mechanical Submission and Approval |
679 |
08-Feb-20 |
17-Dec-21 |
0 |
21-Jul-20 A |
02-Sep-21 A |
100% |
106 |
ES0002020 |
M&E AIP Instrumentation & Control Submission and Approval |
607 |
31-Jan-20 |
28-Sep-21 |
0 |
04-Feb-20 A |
25-Feb-20 A |
100% |
581 |
ES0002030 |
M&E DDA Instrumentation & Control Submission and Approval |
514 |
22-Jul-20 |
17-Dec-21 |
0 |
13-Feb-21 A |
14-Apr-23 A |
100% |
-482 |
ES0002050 |
M&E DDA Renewable Energy Submission and Approval |
382 |
16-Aug-20 |
01-Sep-21 |
0 |
17-Aug-20 A |
31-Dec-20 A |
100% |
244 |
ES0002060 |
M&E AIP Building Services Submission and Approval |
226 |
30-Dec-19 |
11-Aug-20 |
0 |
30-Dec-19 A |
30-Oct-20 A |
100% |
-80 |
ES0002065 |
M&E Design Basis & Civil Guidance Dwg |
112 |
30-Dec-19 |
19-Apr-20 |
0 |
30-Dec-19 A |
24-Jul-20 A |
100% |
-96 |
ES0002070 |
M&E DDA Building Services Submission and Approval |
306 |
28-Feb-20 |
29-Dec-20 |
0 |
01-Mar-20 A |
30-Jun-21 A |
100% |
-183 |
ES0002085 |
M&E AIP Site Wide Electrical Submission and Approval |
155 |
09-Jun-20 |
10-Nov-20 |
0 |
21-Mar-20 A |
22-Jul-20 A |
100% |
111 |
ES0002090 |
M&E CMS Lift Submission and Approval |
140 |
27-Aug-20 |
13-Jan-21 |
0 |
01-Oct-20 A |
20-Jul-21 A |
100% |
-188 |
ES0002095 |
M&E DDA Site Wide Electrical Submission and Approval |
140 |
11-Nov-20 |
30-Mar-21 |
0 |
23-Jul-20 A |
04-Jun-21 A |
100% |
-66 |
ES0002100 |
M&E DDA T&C Design Submission and Approval |
155 |
29-Mar-22 |
30-Aug-22 |
0 |
01-Aug-21 A |
05-Oct-23 A |
100% |
-401 |
Procurement of Major Plant & Equipment Schedule |
|||||||||
ES0002320 |
M&E Procurement of Major Plant, Equipment, Material and Delivery |
901 |
14-Mar-20 |
31-Aug-22 |
0 |
04-Feb-20 A |
16-Jan-23 A |
100% |
-137 |
ES2420 |
M&E Procurement of Mechanical Equipment - Intake Pumps |
595 |
18-May-20 |
02-Jan-22 |
0 |
04-Feb-20 A |
11-May-22 A |
100% |
-128 |
ES2430 |
M&E Procurement of Mechanical Equipment - ActiDAFF Underdrain |
333 |
30-Oct-20 |
27-Sep-21 |
0 |
02-Aug-20 A |
14-Mar-22 A |
100% |
-168 |
ES2440 |
M&E Procurement of Mechanical Equipment - ActiDAFF Media |
298 |
15-Mar-21 |
06-Jan-22 |
0 |
23-Jul-20 A |
14-Oct-22 A |
100% |
-281 |
ES2450 |
M&E Procurement of Mechanical Equipment - RO and ERD Rack |
274 |
22-Feb-21 |
22-Nov-21 |
0 |
22-Jul-20 A |
28-Dec-21 A |
100% |
-36 |
ES2460 |
M&E Procurement of Mechanical Equipment - RO Membrane |
755 |
29-Mar-20 |
22-Apr-22 |
0 |
12-Feb-20 A |
28-Dec-22 A |
100% |
-249 |
ES2470 |
M&E Procurement of Electrical Equipment - CLP Substation for LV Switchboard / Genset / Building Services |
300 |
14-Mar-20 |
07-Jan-21 |
0 |
14-Mar-20 A |
28-Feb-21 A |
100% |
-52 |
Procurement of Major Plant & Equipment
Schedule
Summary Bar
Actual Level of Effort Target Bar
Actual Work Early Bar Critical Bar
Target Milestone Milestone
Page 1 of 5
Appendix D - Critical Path
file: MPR202407_c
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13/WSD/17 Design, Build and Operate Stage 1 of Tesung
Kwan O Desalination Plant 31 Jul 24
Activity ID Activity Name Baseline
Baseline Start Baseline Finish Remaining
Actual / Planned
Actual / Planned
Actual %
Variance
Total
2020 2021 2022 2023 2024
132kV Substation
132kV Substation
Duration
Duration
Start
Finish
Complete
Finish Date
Float N D J
F M A M J
J A S O N D J
F M A M J
J A S O N D J
F M A M J
J A S O N D J
F M A M J
J A S O N D J
F M A M J
J A S
O N D
ES0001460
Excavation and Formation Works for 132kV Substation
15 16-Mar-20
30-Mar-20
0 19-Feb-20 A
23-Apr-20 A
100%
-24
ES0001470
Construction of 132kV Substation
233
31-Mar-20
18-Nov-20
0 27-Apr-20 A
30-Dec-20 A
100%
-42
ES0001480
Architectural Finishes for 132kV Substation
126
11-Sep-20
2. Jan-21
0 23-Nov-20 A
22-Mar-21 A
100%
-67
Combine Shaft
Intake
OutFall
ActiDAFF
Reverse Osmosis Building
ES0002240
M&E Installation of 132kV Substation
93 20-Nov-20
20-Feb-21
0 01-Dec-20 A
22-Mar-21 A
100%
-30
Combine Shaft |
|||||||||
ES0001060 |
Construction of Combine Shaft |
257 |
27-Mar-20 |
08-Dec-20 |
0 |
02-May-20 A |
30-Jun-21 A |
100% |
-204 |
ES0002120 |
M&E Installation at Combine Shaft |
160 |
03-Jan-22 |
11-Jun-22 |
0 |
11-Oct-22 A |
06-May-23 A |
100% |
-328 |
Intake |
|||||||||
ES0001070 |
DN2500 Pipe Jacking for Intake Pipeline |
163 |
09-Dec-20 |
20-May-21 |
0 |
02-Jul-21 A |
28-Mar-22 A |
100% |
-312 |
ES0001080 |
Receiving Pit and Marine Intake Structure |
416 |
11-Nov-20 |
31-Dec-21 |
0 |
22-Mar-21 A |
30-Dec-22 A |
100% |
-364 |
ES0001110 |
Construction of Intake Land Structure (Combined Shaft) |
193 |
21-May-21 |
29-Nov-21 |
0 |
17-Feb-22 A |
10-Oct-22 A |
100% |
-315 |
ES0001120 |
Architectural Finishes for Intake Land Structure |
32 |
30-Nov-21 |
31-Dec-21 |
0 |
24-Oct-22 A |
08-Dec-22 A |
100% |
-342 |
OutFall |
|||||||||
ES0001090 |
DN1650 Pipe Jacking for Outfall Pipeline |
140 |
29-Dec-20 |
17-May-21 |
0 |
01-Sep-21 A |
24-Mar-22 A |
100% |
-311 |
ES0001100 |
Receiving Pit, Outfall and Diffuser Pipeline |
343 |
18-Dec-20 |
25-Nov-21 |
0 |
08-Apr-21 A |
25-Apr-23 A |
100% |
-516 |
ActiDAFF |
|||||||||
ES0001140 |
Excavation for ActiDAFF |
97 |
02-May-20 |
06-Aug-20 |
0 |
22-Apr-20 A |
15-Aug-20 A |
100% |
-9 |
ES0001150 |
Construction of ActiDAFF Structure |
393 |
11-Sep-20 |
08-Oct-21 |
0 |
10-Aug-20 A |
03-Aug-22 A |
100% |
-299 |
ES0001160 |
Architectural Finishes for ActiDAFF |
183 |
07-Jul-21 |
05-Jan-22 |
0 |
28-Apr-22 A |
10-Oct-22 A |
100% |
-278 |
ES0002130 |
M&E Installation at ActiDAFF |
257 |
28-Sep-21 |
11-Jun-22 |
0 |
22-Jan-22 A |
20-May-24 A |
100% |
-708 |
ES0002140 |
M&E Installation of Filter Water Tank and Pumping Station |
137 |
29-Nov-21 |
14-Apr-22 |
0 |
01-Jul-22 A |
24-Aug-23 A |
100% |
-496 |
Reverse Osmosis Building |
|||||||||
ES0001170 |
Excavation at RO Building |
270 |
24-Jun-20 |
20-Mar-21 |
0 |
18-Jun-20 A |
10-Oct-20 A |
100% |
161 |
ES0001180 |
Construction of RO Building |
321 |
16-Nov-20 |
02-Oct-21 |
0 |
25-Aug-20 A |
11-Dec-21 A |
100% |
-70 |
ES0001190 |
Architectural Finishes for RO Building |
106 |
09-Aug-21 |
22-Nov-21 |
0 |
20-Sep-21 A |
21-Oct-22 A |
100% |
-333 |
ES0002150 |
M&E Installation of RO Building |
315 |
23-Nov-21 |
03-Oct-22 |
0 |
24-Nov-21 A |
05-Dec-23 A |
100% |
-428 |
Product Water Storage Tank |
|||||||||
ES0001240 |
Excavation and Soil Nail System for Product Water Storage Tank |
106 |
10-Aug-20 |
23-Nov-20 |
0 |
24-Jun-20 A |
01-Dec-20 A |
100% |
-8 |
ES0001250 |
Construction of Product Water Storage Tank |
276 |
24-Nov-20 |
26-Aug-21 |
0 |
21-Oct-20 A |
18-Dec-21 A |
100% |
-114 |
ES0001260 |
Architectural Finishes for Product Water Storage Tank |
70 |
27-Aug-21 |
04-Nov-21 |
0 |
16-May-22 A |
07-Jun-22 A |
100% |
-215 |
ES0002210 |
M&E Installation of Product Water Tank |
78 |
12-Jan-22 |
30-Mar-22 |
0 |
31-Jul-21 A |
04-Apr-24 A |
100% |
-736 |
Product Water Pumping Station |
|||||||||
ES0001270 |
Excavation for Product Water Pump Station |
47 |
22-Oct-20 |
07-Dec-20 |
0 |
08-Mar-21 A |
07-Apr-21 A |
100% |
-121 |
ES0001280 |
Construction of Product Water Pump Station |
270 |
22-Jan-21 |
18-Oct-21 |
0 |
17-Apr-21 A |
18-Dec-21 A |
100% |
-61 |
ES0001290 |
Architectural Finishes for Product Water Pumping Station |
106 |
25-Sep-21 |
08-Jan-22 |
0 |
10-Feb-22 A |
16-Jul-22 A |
100% |
-189 |
ES0002215 |
M&E Installation of Product Water Pump Station |
78 |
12-Jan-22 |
30-Mar-22 |
0 |
20-Jun-22 A |
14-Dec-23 A |
100% |
-624 |
Chemical Building |
|||||||||
ES0001300 |
Excavation for Chemical Building |
42 |
12-Aug-20 |
22-Sep-20 |
0 |
17-Jun-21 A |
17-Jul-21 A |
100% |
-298 |
ES0001310 |
Construction of Chemical Building |
255 |
23-Sep-20 |
04-Jun-21 |
0 |
17-Jul-21 A |
09-Jun-22 A |
100% |
-370 |
ES0001320 |
Architectural Finishes for Chemical Building |
73 |
05-Jun-21 |
16-Aug-21 |
0 |
09-Jun-22 A |
30-Nov-22 A |
100% |
-470 |
ES0002220 |
M&E Installation of Chemical Building |
264 |
02-Sep-21 |
23-May-22 |
0 |
15-Aug-22 A |
10-Aug-23 A |
100% |
-443 |
Product Water Storage Tank
Product Water Pumping Station
Chemical Building
Administration Building
Administration Building
Summary Bar
Actual Level of Effort Target Bar
Actual Work Early Bar Critical Bar
Target Milestone Milestone
Page 2 of 5
Appendix D - Critical Path
file: MPR202407_c
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13/WSD/17 Design, Build and Operate Stage 1 of Tesung
Kwan O Desalination Plant 31 Jul 24
Activity ID
Activity Name
Baseline
Baseline Start
Baseline Finish
Remaining
Actual / Planned
Actual / Planned
Actual %
Variance
Total
2020 2021 2022 2023 2024
ES0001330
Piling Works for Administration Building
Duration
110
19-Oct-20
05-Feb-21
Duration
0
Start
03-Oct-20 A
Finish
16-Jan-21 A
Complete
100%
Finish Date
20
Float N D J
F M A M J
J A S O N D J
F M A M J
J A S
O N D J
F M A M J
J A S O N D J
F M A M J
J A S O N D J
F M A M J
J A S O N D
ES0001340
Excavation for Administration Building
31 06-Feb-21
08-Mar-21
0 28-Dec-20 A
3. Mar-21 A
100% -7
ES0001350
Construction of Administration Building
339
09-Mar-21
1. Feb-22
0 28-Jan-21 A
1. Aug-22 A
100%
-200
ES0001360
Architectural Finishes for Administration Building
204
1. Aug-21
17-Mar-22
0 19-Apr-22 A
22-May-23 A
100%
-431
ES0002230
M&E Installation of Admin Building
184
4. Nov-21
18-May-22
0 15-Jul-22 A
18-Feb-23 A
100%
-276
Building Services & Lift Installation
Building Services & Lift Installation
ES0002270
Lift Installation
147
1. Mar-22
1. Aug-22
0 02-Feb-23 A
28-Jun-24 A
100%
-686
ES0002280
Building Services Installation
676
1. Nov-20
1. Oct-22
12 01-Dec-20 A
2. Aug-24
85%
-679
-194
Building Ser
OSCG Building
OSCG Building
ES0001400
Excavation for On-site Chlorine Generation Building
25 11-Dec-20
3. Jan-21
0 01-Apr-21 A
09-Apr-22 A
100%
-460
ES0001410
Construction of On-site Chlorine Generation Building
291
4. Jan-21
22-Oct-21
0 05-Jul-21 A
15-Jun-22 A
100%
-236
ES0001420
Architectural Finishes for On-site Chlorine Generation Building
59 23-Oct-21
5. Dec-21
0 16-Jun-22 A
1. Sep-22 A
100%
-282
Post Treatment Building
Sludge Thickener
Workshop
Inspection Corridor
ES0002200
BS Installation of On-site Chlorine Generation Building (DG inspection)
162
6. Dec-21
31-May-22
12 11-Oct-22 A
12-Aug-24
90%
-804
-194
BS Installatio
Post Treatment Building |
|||||||||
ES0001210 |
Excavation and ELS for Post Treatment Building |
126 |
19-Dec-20 |
23-Apr-21 |
0 |
03-Dec-20 A |
01-Sep-21 A |
100% |
-131 |
ES0001220 |
Construction of Post Treatment Building |
209 |
14-Apr-21 |
08-Nov-21 |
0 |
17-Dec-20 A |
19-May-22 A |
100% |
-192 |
ES0001230 |
Architectural Finishes for Post Treatment Building |
59 |
11-Oct-21 |
08-Dec-21 |
0 |
22-Jul-22 A |
16-Sep-22 A |
100% |
-282 |
ES0002180 |
M&E Installation of Post Treatment Building |
199 |
09-Dec-21 |
25-Jun-22 |
0 |
14-Jul-22 A |
04-Apr-24 A |
100% |
-649 |
Sludge Thickener |
|||||||||
ES0001680 |
Excavation for Sludge Thickener |
73 |
19-Apr-21 |
30-Jun-21 |
0 |
02-Oct-21 A |
16-Oct-21 A |
100% |
-108 |
ES0001690 |
Construction of Sludge Thickener |
121 |
02-Jul-21 |
30-Oct-21 |
0 |
08-Oct-21 A |
26-Jul-22 A |
100% |
-269 |
ES0001700 |
Architectural Finishes for Sludge Thickener |
44 |
01-Nov-21 |
14-Dec-21 |
0 |
29-Jul-22 A |
31-Jan-24 A |
100% |
-778 |
ES0002190 |
M&E Installation of Sludge Thickener |
141 |
15-Dec-21 |
04-May-22 |
0 |
06-Feb-23 A |
28-Mar-24 A |
100% |
-693 |
Workshop |
|||||||||
ES0001560 |
Excavation for Workshop |
7 |
21-May-21 |
27-May-21 |
0 |
06-Nov-23 A |
07-Nov-23 A |
100% |
-894 |
ES0001570 |
Construction of Workshop |
179 |
28-May-21 |
22-Nov-21 |
0 |
08-Nov-23 A |
15-Mar-24 A |
100% |
-844 |
ES0001580 |
Architectural Finishes for Workshop |
81 |
17-Nov-21 |
05-Feb-22 |
0 |
16-Mar-24 A |
26-Jun-24 A |
100% |
-872 |
Inspection Corridor |
|||||||||
ES0001590 |
Piling for Inspection Corridor (Elevated Walkway) |
60 |
09-Jan-21 |
09-Mar-21 |
0 |
15-Dec-20 A |
19-Jan-21 A |
100% |
49 |
ES0001600 |
Excavation for Inspection Corridor |
121 |
14-Apr-21 |
12-Aug-21 |
0 |
26-Mar-21 A |
28-May-22 A |
100% |
-289 |
ES0001610 |
Construction of Inspection Corridor |
299 |
06-May-21 |
28-Feb-22 |
0 |
12-Apr-21 A |
16-Nov-23 A |
100% |
-626 |
ES0001620 |
Architectural Finishes for Inspection Corridor |
99 |
08-Feb-22 |
17-May-22 |
0 |
03-Oct-23 A |
29-Jun-24 A |
100% |
-774 |
ES0001625 |
Building Services for Inspection Corridor |
0 |
0 |
03-Jan-23 A |
01-Feb-24 A |
100% |
|||
Main Electrical and Central Chiller Plant Building |
|||||||||
ES0001430 |
Excavation for Main Electrical and Central Chiller Plant Building |
20 |
11-Jan-21 |
30-Jan-21 |
0 |
18-Jan-21 A |
06-Feb-21 A |
100% |
-7 |
ES0001440 |
Construction of Main Electrical and Central Chiller Plant Building |
227 |
01-Feb-21 |
15-Sep-21 |
0 |
01-Feb-21 A |
20-Oct-21 A |
100% |
-35 |
ES0001450 |
Architectural Finishes for Main Electrical and Central Chiller Plant Building |
99 |
20-Jul-21 |
26-Oct-21 |
0 |
06-Nov-21 A |
25-Jun-22 A |
100% |
-242 |
ES0002260 M&E Installation for Main Electrical and Central Chiller Plant Building Guard House |
152 |
25-Jan-22 |
25-Jun-22 |
0 |
27-Jul-22 A |
14-Apr-23 A |
100% |
-293 |
|
ES0001490 |
Excavation for Guard House at Main Gate |
7 |
15-Sep-21 |
21-Sep-21 |
0 |
16-May-23 A |
17-May-23 A |
100% |
-603 |
ES0001500 |
Construction of Guard House at Main Gate |
149 |
23-Sep-21 |
18-Feb-22 |
0 |
18-May-23 A |
26-Aug-23 A |
100% |
-554 |
ES0001510 |
Architectural Finishes for Guard House at Main Gate |
76 |
19-Feb-22 |
05-May-22 |
0 |
18-Aug-23 A |
15-Sep-23 A |
100% |
-498 |
ES0001520 |
Excavation for Guard House near Pier |
8 |
21-May-21 |
28-May-21 |
0 |
07-Jun-23 A |
09-Jun-23 A |
100% |
-742 |
Main Electrical and Central Chiller Plant Building
Guard House
Summary Bar
Actual Level of Effort Target Bar
Actual Work Early Bar Critical Bar
Target Milestone Milestone
Page 3 of 5
Appendix D - Critical Path
file: MPR202407_c
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13/WSD/17 Design, Build and Operate Stage 1 of Tesung
Kwan O Desalination Plant 31 Jul 24
Activity ID
Activity Name
Baseline
Baseline Start
Baseline Finish
Remaining
Actual / Planned
Actual / Planned
Actual %
Variance
Total
2020 2021 2022 2023 2024
ES0001530
Construction of Guard House near Pier
Duration
147
1. May-21
7. Oct-21
Duration
0
Start
10-Jun-23 A
Finish
1. Oct-23 A
Complete
100%
Finish Date
-718
Float N D J
F M A M J
J A S O N D J
F M A
M J J A S O N D J F M A M J
J A S O N D J
F M A M J J A S
O N D J
F M A M J
J A S O N D
CO2 Tanks Areas
Diesel Emergency Generator
ES0001540
Architectural Finishes for Guard House near Pier
74 23-Oct-21
1. Jan-22
0 05-Oct-23 A
8. Mar-24 A
100%
-809
Switch Room and Transformer Installation
Miscellaneous
CO2 Tanks Areas |
||||||||||
ES0001370 |
Filling to Formation for CO2 Tanks Area |
29 |
22-Jun-21 |
20-Jul-21 |
0 |
14-Dec-21 A |
17-Dec-21 A |
100% |
-150 |
|
ES0001380 |
Construction of CO2 Tanks Area |
116 |
21-Jul-21 |
13-Nov-21 |
0 |
21-Dec-21 A |
10-Mar-22 A |
100% |
-117 |
|
ES0002170 |
M&E Installation of CO2 Tanks Area |
84 |
27-Jan-22 |
20-Apr-22 |
0 |
11-Mar-22 A |
03-Oct-23 A |
100% |
-531 |
|
Diesel Emergency Generator |
||||||||||
ES0002250 |
M&E Diesel Emergency Generator |
57 |
25-Feb-22 |
22-Apr-22 |
0 |
18-Jan-23 A |
28-Jul-23 A |
100% |
-462 |
|
Switch Room and Transformer Installation |
||||||||||
ES0002300 |
M&E Installation of HV/LV Switchroom and Transformer (Admin) |
242 |
16-Nov-21 |
15-Jul-22 |
0 |
27-Jul-22 A |
20-Apr-23 A |
100% |
-279 |
|
Miscellaneous |
||||||||||
ES0001630 |
Remaining Architectural Finishes for All Buildings |
322 |
11-Jan-22 |
28-Nov-22 |
0 |
09-Dec-22 A |
29-Jun-24 A |
100% |
-579 |
|
ES0001640 |
External Process and Non Process Pipe |
655 |
18-Dec-20 |
03-Oct-22 |
0 |
27-May-21 A |
23-Nov-23 A |
100% |
-416 |
|
ES0001650 |
Drainage and Cable Duct |
518 |
04-Jun-21 |
03-Nov-22 |
0 |
25-Apr-22 A |
18-Jul-23 A |
100% |
-257 |
|
ES0001660 |
Slope Mitigation Works |
684 |
23-Nov-20 |
07-Oct-22 |
76 |
28-Sep-21 A |
15-Oct-24 |
50% |
-739 |
-258 |
ES0001670 |
Landscaping Works |
469 |
28-Oct-21 |
08-Feb-23 |
0 |
01-Mar-23 A |
18-May-24 A |
100% |
-465 |
|
ES0002290 |
M&E PV Panels |
215 |
23-Nov-21 |
25-Jun-22 |
0 |
05-Jan-23 A |
29-Jul-24 A |
100% |
-764 |
|
ES0002310 |
M&E Chiller & Irrigation System Installation |
298 |
27-Oct-21 |
20-Aug-22 |
0 |
25-Aug-23 A |
30-May-24 A |
100% |
-648 |
|
ES0002350 |
M&E Installation of Surge Vessel |
70 |
24-Feb-22 |
04-May-22 |
0 |
15-Sep-23 A |
30-Oct-23 A |
100% |
-544 |
|
ES0002390 |
M&E Installation of Thickened Sludge Holding Tank |
42 |
09-Dec-21 |
19-Jan-22 |
0 |
27-Mar-23 A |
31-Jan-24 A |
100% |
-742 |
Slope
Statutory Submission & Inspection
Statutory Submission & Inspection
ES0002330 Statutory Submission & Inspection 1148 11-Jan-20 03-Mar-23 2
03-Dec-19 A 02-Aug-24 100% -518 -184
Statutory Sub
Testing and Commissioning
Testing and Commissioning
ES0002400 |
M&E Precomissioning |
229 |
12-Jun-22 |
26-Jan-23 |
0 |
22-Apr-23 A |
29-Mar-24 A |
100% |
-428 |
ES0002410 |
M&E Commissioning |
213 |
04-Jul-22 |
01-Feb-23 |
0 |
02-Jun-23 A |
30-Jul-24 A |
100% |
-544 |
ES0002420 |
M&E Performance Test |
40 |
02-Feb-23 |
13-Mar-23 |
0 |
28-Nov-23 A |
26-Apr-24 A |
100% |
-409 |
Procurement of Major Plant & Equipment
Schedule
Pipes, Fittings and Valves
Procurement of Major Plant & Equipment
Schedule Pipes,
Fittings and Valves
Pressure Relief Valves
Pressure Relief Valves
P-PV-A51IK-0 NR Receipt - Pressure relief valves
0 08-Sep-21 0
02-Oct-20 A
100%
341
NR Receipt - Pressure relief valves
P-PV-A51IK-0 Receipt of offers - Pressure relief valves
30 09-Sep-21
08-Oct-21
0 03-Oct-20 A
27-Oct-20 A
100%
346
Receipt of offers - Pressure relief valves
P-PV-A51IK-0 Technical Validation - Pressure relief valves
30 09-Oct-21
07-Nov-21
0 28-Oct-20 A
9. Mar-21 A
100%
248
Technical Validation - Pressure relief valves
P-PV-A51IK-0 Negotiation and Award / Client Approval - Pressure relief
valves
60 08-Nov-21
10.Jan-22
0 06-Mar-21 A
2. Nov-21 A
100% 49
Negotiation and Award / Client Approval - Pressure relief valves
P-PV-A51IK-0 Manufacture and FAT - Pressure relief valves
187
1. Jan-22
12-Jul-22
0 20-Nov-21 A
22-Jul-22 A
100% -9
Manufacture and FAT - Pressure relief valves
P-PV-A51IK-0 Transport & Customs - Pressure relief valves
50 13-Jul-22
31-Aug-22
0 23-Jul-22 A
31-Jul-22 A
100% 32
Transport & Customs - Pressure relief valves
P-PV-A51IK-0 1st delivery date to site - Pressure relief valves
0 31-Aug-22 0
31-Jul-22 A
100% 32
1st delivery date to site - Pressure relief valves
Instrumentation, Control & Automation
Instrumentation, Control & Automation
Bypass Level Indicators
Bypass Level Indicators
P-IC-A08FK2- NR Receipt - Bypass Level Indicators
0 12-Apr-21 0
16-Sep-20 A
100%
208
NR Receipt - Bypass Level Indicators
P-IC-A08FK2- Receipt of offers - Bypass Level Indicators
30 13-Apr-21
12-May-21
0 17-Sep-20 A
3. Oct-20 A
100%
205
Receipt of offers - Bypass Level Indicators
P-IC-A08FK2- Technical Validation - Bypass Level
Indicators
30 13-May-21
1. Jun-21
0 21-Oct-20 A
25-Nov-20 A
100%
199
Technical Validation - Bypass Level Indicators
P-IC-A08FK2- Negotiation and Award / Client Approval - Bypass Level
Indicators
60 12-Jun-21
10-Aug-21
0 26-Nov-20 A
1. Jun-21 A
100% 42
Negotiation and Award / Client Approval - Bypass Level Indicators
P-IC-A08FK2- Manufacture and FAT - Bypass Level Indicators
90 11-Aug-21
1. Nov-21
0 01-Jul-21 A
22-Jul-22 A
100%
-255
Manufacture and FAT - Bypass Level Indicators
P-IC-A08FK2- Transport & Customs - Bypass Level Indicators
50 09-Nov-21
28-Dec-21
0 18-Sep-22 A
26-Oct-22 A
100%
-301
Transport & Customs - Bypass Level Indicators
Summary Bar
Actual Level of Effort Target Bar
Actual Work Early Bar Critical Bar
Target Milestone Milestone
Page 4 of 5
Appendix D - Critical Path
file: MPR202407_c
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13/WSD/17 Design, Build and Operate Stage 1 of Tesung
Kwan O Desalination Plant 31 Jul 24
Activity ID
Activity Name
Baseline
Baseline Start
Baseline Finish
Remaining
Actual / Planned
Actual / Planned
Actual %
Variance
Total
2020 2021 2022 2023 2024
P-IC-A08FK2- 1st delivery date to site - Bypass Level Indicators
Duration
0
28-Dec-21
Duration
0
Start
Finish
26-Oct-22 A
Complete
100%
Finish Date
-301
Float N D J
F M A M J
J A S O N D J
F M A
M J J A S O N D J F M A M J J
A S O N D J F M A M J J A S O N D J F M A M J J A S
1st delivery date to site - Bypass Level Indicators
O N D
Level Transmitters
Level Transmitters
P-IC-A08FK1- NR Receipt - Level Transmitters
0 12-Apr-21 0
16-Sep-20 A
100%
208
NR Receipt - Level Transmitters
P-IC-A08FK1- Receipt of offers - Level Transmitters
30 13-Apr-21
2. May-21
0 17-Sep-20 A
20-Oct-20 A
100%
204
Receipt of offers - Level Transmitters
P-IC-A08FK1- Technical Validation - Level
Transmitters
30 13-May-21
11-Jun-21
0 21-Oct-20 A
26-Nov-20 A
100%
198
Technical Validation - Level Transmitters
P-IC-A08FK1- Negotiation and Award / Client
Approval - Level Transmitters
60 12-Jun-21
10-Aug-21
0 26-Nov-20 A
02-Dec-21 A
100%
-113
Negotiation and Award / Client Approval - Level
Transmitters
P-IC-A08FK1- Manufacture and FAT - Level
Transmitters
90 11-Aug-21
08-Nov-21
0 03-Dec-21 A
1. Mar-22 A
100%
-142
Manufacture and FAT - Level Transmitters
P-IC-A08FK1- Transport & Customs - Level
Transmitters
50 09-Nov-21
28-Dec-21
0 02-Apr-22 A
01-Jun-22 A
100%
-154
Transport & Customs - Level Transmitters
P-IC-A08FK1- 1st delivery date to site - Level
Transmitters
0 28-Dec-21 0
01-Jun-22 A
100%
-154
1st delivery date to site - Level Transmitters
Construction
Construction
Civil & Structure Construction
Civil & Structure Construction
ActiDAFF Structure (DAF)
ActiDAFF Structure (DAF)
CC0200906k DAF: Remedial Work at Cell No. 1 and 3
after Water Test 0 0 30-Nov-21 A 27-Jun-22 A 100%
DAF: Remedial Work at Cell No. 1 and 3 after Water
Test
Yard Piping - Process & Non Process
Yard Piping - Combined Shaft Zone
Yard Piping -
Process & Non Process Yard Piping - Combined Shaft
Zone
CC2401356k GRP Combined Shaft S - DN500 Tee at
+3.214mPD 0 0 01-Apr-23 A 06-Apr-23 A 100%
GRP Combined Shaft S - DN500 Tee at +3.214mPD
Yard Piping - ActiDAFF
Zone
Yard Piping - ActiDAFF
Zone
CC2401311k GRP West ActiDAFF:
(Covid-19) Limited Resources Effect to GRP Works 0
0 08-Feb-22 A
19-Apr-22 A
100%
GRP West ActiDAFF:
(Covid-19) Limited Resources Effect to GRP Works
CC2401349k GRP South ActiDAFF:
DN400 at 5.490mPD at C10/CD~CF 0
0 14-May-22 A
18-Jun-22 A
100%
GRP South ActiDAFF:
DN400 at 5.490mPD at C10/CD~CF
Summary Bar
Actual Level of Effort Target Bar
Actual Work Early Bar Critical Bar
Target Milestone Milestone
Page 5 of 5
Appendix D - Critical Path
file: MPR202407_c
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contract
No. 13/WSD/17
Design, Build and Operate First
Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report
Appendix B
Overview of Desalination Plant in Tseung
Kwan O
|
TEMPORARY
GLA—TSK
692
TGLA
SKE PHASING
ALLOCATED LAI4D BOUNDARIES
NOTE: TEMPORARY
WORKS AREA 1 \YILL BE
TOLERAMCC OC *500mm.
A 07/I 8 UPDATE COORDINATES
YLc YLC
YLC |
CKH |
SZ |
TLS |
|
°°t' |
o2/ 8 |
o2/18 |
o2/18 |
o2/18 |
FOR
PORTION 8
CE 8/ 2015 (W s)
ROINT |
EASTING |
NORTHINC |
||
A |
8465B I.93 |
8l4S0â.03 |
||
B |
8‹6610.11 |
813979.23 |
||
C |
8466 I ‹.73 |
813975.I 2 |
||
D |
%662909 |
8139978 |
||
E |
8466+1.75 |
813986.74 |
||
F |
8‹66 6.80 |
8i 3985.28 |
||
G |
846677.2A |
8\4034.67 |
13/¥/S D/ 17
DESIGN,
BUILD AND OPERATE FIRST STA6E OF TSEUN6 KWAN 0 DESALINATION PLANT
)
SITE HANDOVER WORKS AREAS
LA/TRD
NHCATVE L SMñATER
I
INDICATIVE LOCATION OF PROPOSED OUTFALL
OPOSED
8*6766.21
J 8+6+59.65
81*53ll
81 \\+8.83
190495 K TEND 10 0005
l4 |
84661 4.60 |
814117.96 |
H |
846676.B4 |
81T207.77 |
0 |
846756.68 |
81416T.57 |
Water Supplies
Department
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
M.L.
100
C.L. A.U.T.
MV/AL F.E.
H.R. A D
P.D.
MAIN ELECTRICAL AND CENTRAL CHILLER PLANT
BUILDING
TOTAL G.F.A. TOTAL SITE COVERAGE |
= = |
|
PLOT RATIO |
= = |
25092.141 / 56108 0.447 < PERMITTED |
SITE COVERAGE |
= = |
21414.841 / 56108 x 100 38.167% |
FIRST STAGE
82
20
JOSS HOUSE BAY ( TAI MIU WAN )
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contract
No. 13/WSD/17
Design, Build and Operate First
Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report
Appendix C
Summary of Implementation Status of
Environmental Mitigation
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Air Quality |
||||||||
S4.8.1 |
Impervious dust screen or sheeting will be provided to enclose scaffolding from the ground floor level of building for construction of superstructure of the new buildings. |
Land site/ During Construction |
Contractor(s) |
ü |
Implemented |
Air Pollution Control (Construction Dust) |
||
S4.8.1 |
Impervious sheet will be provided for skip hoist for material transport. |
Land site/ During Construction |
Contractor(s) |
ü |
NA |
- |
||
S4.8.1 |
The area where dusty work takes place should be sprayed with water or a dust suppression chemical immediately prior to, during and immediately after dusty activities as far as practicable. |
Land site/ During Construction |
Contractor(s) |
ü |
Implemented |
- |
||
S4.8.1 |
All dusty materials should be sprayed with water or a dust suppression chemical immediately prior to any loading, unloading or transfer operation. |
Land site/ During Construction |
Contractor(s) |
ü |
Implemented |
- |
||
S4.8.1 |
Dropping heights for excavated materials should be controlled to a practical height to minimize the fugitive dust arising from unloading. |
Land site/ During Construction |
Contractor(s) |
ü |
Implemented |
- |
||
S4.8.1 |
During transportation by truck, materials should not be loaded to a level higher than the side and tail boards and should be dampened or covered before transport. |
Land site/ During Construction |
Contractor(s) |
ü |
Implemented |
- |
||
S4.8.1 |
Wheel washing device should be provided at the exits of the work sites. Immediately before leaving a construction site, every vehicle shall be washed to remove any dusty material from its body and wheels as far as practicable. |
Land site/ During Construction |
Contractor(s) |
ü |
Implemented |
- |
||
S4.8.1 |
Road sections between vehicle-wash areas and vehicular entrance will be paved. |
Land site/ During Construction |
Contractor(s) |
ü |
Implemented |
- |
||
S4.8.1 |
Hoarding of not less than 2.4m high from ground level will be provided along the length of the Project Site boundary. |
Land site/ During construction |
Contractor(s) |
ü |
ü |
N/A |
- |
|
S4.8.1 |
Haul roads will be kept clear of dusty materials and will be sprayed with water so as to maintain the entire road surface wet at all times. |
Land site/ During construction |
Contractor(s) |
ü |
Implemented after reminder |
- |
||
S4.8.1 |
Temporary stockpiles of dusty materials will be either covered entirely by impervious sheets or sprayed with water to maintain the entire surface wet all the time. |
Land site/ During construction |
Contractor(s) |
ü |
Implemented after reminder |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S4.8.1 |
Stockpiles of more than 20 bags of cement, dry pulverized fuel ash and dusty construction materials will be covered entirely by impervious sheeting sheltered on top and 3-sides. |
Land site/ During construction |
Contractor(s) |
ü |
N/A |
- |
||
S4.8.1 |
All exposed areas will be kept wet always to minimize dust emission. |
Land site/ During construction |
Contractor(s) |
ü |
Implemented after reminder |
- |
||
S4.8.1 |
Ultra-low-Sulphur diesel (ULSD) will be used for all construction plant on-site, as defined as diesel fuel containing not more than 0.005% Sulphur by weight) as stipulated in Environment, Transport and Works Bureau Technical Circular (ETWB-TC(W)) No 19/2005 on Environmental Management on Construction Sites. |
Land site/ During construction/ During Operation |
Contractor(s) |
ü |
ü |
Implemented |
Environment, Transport and Works Bureau Technical Circular (ETWB- TC(W)) No 19/2005 on Environmental Management on Construction Sites |
|
S4.8.1 |
The engine of the construction equipment during idling will be switched off. |
Land site/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S4.8.1 |
Concrete batching plant will be required on site. control measures recommended in the Guidance Note on a Best Practicable Means for Cement Works (Concrete Batching Plant) (BPM 3/2 (93)) will be implemented. The control measures recommended in the Guidance Note on a Best Practicable Means for Cement Works (Concrete Batching Plant) (BPM 3/2 (93)) will be implemented. |
Land site/ During construction |
Contractor(s) |
ü |
N/A |
- |
||
S4.8.1 |
Regular maintenance of construction equipment deployed on- site will be conducted to prevent black smoke emission. |
Land site/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S4.10 |
To ensure proper implementation of the recommended dust mitigation measures and good construction site practices during the construction phase, environmental site audits on weekly basis is recommended throughout the construction period. |
Land site/ During construction |
Contractor(s)/ Environmental Team (ET) & Independent Environmental Checker (IEC) |
ü |
Implemented |
- |
||
Noise |
||||||||
S5.7 |
Only well-maintained plant will be operated on-site, and plant will be serviced regularly during the construction phase. |
All area/ During construction |
Contractor(s) |
ü |
Implemented |
A Practical Guide for the Reduction of Noise from Construction Works A Practical Guide for the Reduction of Noise from Construction Works |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S5.7 |
Silencers or mufflers on construction equipment will be utilized and will be properly maintained during the construction phase. |
Noise control/ During construction |
Contractor(s) |
ü |
N/A |
- |
||
S5.7 |
Mobile plant, if any, will be sited as far away from NSRs as possible. |
Noise control/ During construction |
Contractor(s) |
ü |
N/A |
- |
||
S5.7 |
Machines and plant (such as trucks) that may be in intermittent use will be shut down between work periods or will be throttled down to a minimum. |
Noise control/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S5.7 |
Plants known to emit noise strongly in one direction will, wherever possible, be orientated so that the noise is directed away from the nearby NSRs. |
Noise control/ During construction |
Contractor(s) |
ü |
N/A |
- |
||
S5.7 |
Material stockpiles and other structures will be effectively utilized, wherever practicable, in screening noise from on-site construction activities. |
Noise control/ During construction |
Contractor(s) |
ü |
N/A |
- |
||
S5.7 |
Use of Quite Powered Mechanical Equipment (QPME). |
Noise control/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S5.7 |
Movable noise barriers of 3m in height with skid footing should be used and located within a few meters of stationary plant and mobile plant such that the line of sight to the NSR is blocked by the barriers. The length of the barrier should be at least five times greater than its height. The noise barrier material should have a superficial surface density of at least 7 kg m-2 and have no o or gappeningss. |
Noise control/ During construction |
Contractor(s) |
ü |
N/A |
- |
||
S5.7 |
The noise insulating sheet should be deployed such that there would be no opening or gaps on the joints. |
Noise control/ During construction |
Contractor(s) |
ü |
N/A |
- |
||
S5.7 |
Construction activities (e.g., excavation/shoring, reinstatement (asphalt), and pipe jacking) will be planned and carried out in sequence, such that items of PME proposed for these activities will not be operated simultaneously. |
Noise control/ During construction |
Contractor(s) |
ü |
ü |
Implemented |
- |
|
S5.7 |
PMEs will not be used at the works areas near educational institutions with residual impact (i.e., the “influence area” within a radius of 40m) during school hours in order to reduce impact to the educational institutions. |
Noise control / During construction |
Contractor(s) |
ü |
N/A |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S5.7 |
Noise enclosures or acoustic sheds would be used to cover stationary PME such as generators. Portable/Movable noise enclosure made of material with superficial surface density of at least 7 kg m-2 may be used for screening the noise from operation of the saw/groover, concrete. |
Noise control/ Pre- construction/ During construction |
Contractor(s) |
ü |
ü |
N/A |
- |
|
5.9 |
Sawcutting pavement, breaking up of pavement, excavation /shoring, pipe laying, backfilling, reinstatement (concrete) and pipe jacking shall be scheduled outside the examination period. |
Noise control/ Pre- construction/ During construction |
Contractor(s) |
ü |
ü |
N/A |
- |
|
S5.9 |
In view the duration of noise exceedance at Creative Secondary School, PLK Laws Foundation College, TKO Kei Tak Primary School and School of Continuing and Professional Studies-CUHK is limited to 8 weeks, the construction work in the influence areas near the four schools shall be scheduled during long school holidays (eg summer holiday, Easter holiday or Christmas holiday, etc) as far as practicable. Scheduling the construction work for the four schools. |
Noise control/ Pre- construction/ During construction |
Contractor(s) |
ü |
ü |
N/A |
- |
|
S5.10 |
A noise monitoring programme shall be implemented for the construction phase. |
Designated monitoring stations as defined in EM&A Manual/During construction phase |
Environmental Team |
ü |
N/A |
- |
||
S5.10 |
The effectiveness of on-site control measures could also be evaluated through the regular site audits. |
All facilities/ During construction |
Contractor(s)/ ET & IEC |
ü |
Implemented |
- |
||
Water Quality |
||||||||
S6.9 |
Dredged marine sediment will be disposed of in a gazette marine disposal area in accordance with marine dumping permit conditions of the Dumping at Sea Ordinance (DASO). |
Marine Dredging/ During construction |
Contractor(s) |
ü |
Implemented |
Dumping at Sea Ordinance (DASO) |
||
S6.9 |
Disposal vessels will be fitted with tight bottom seals in order to prevent leakage of material during transport. |
Marine Dredging/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S6.9 |
Barges will be filled to a level, which ensures that material does not spill over during transport to the disposal site and that adequate freeboard is maintained to ensure that the decks are not washed by wave action. |
Marine Dredging/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S6.9 |
After dredging, any excess materials will be cleaned from decks and exposed fittings before the vessel is moved from the dredging area. |
Marine Dredging/ During construction |
Contractor(s) |
ü |
Implemented |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S6.9 |
All vessels should be well maintained and inspected before use to limit any potential discharges to the marine environment. |
Marine Dredging/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S6.9 |
All vessels must have a clean ballast system. |
Marine Dredging/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S6.9 |
No discharge of sewage/grey wastewater should be allowed. Wastewater from potentially contaminated area on working vessels should be minimized and collected. These kinds of wastewater should be brought back to port and discharged at appropriate collection and treatment system. |
Marine Dredging/ During construction |
Contractor(s) |
ü |
Implemented |
|||
S6.9 |
No soil waste is allowed to be disposed overboard. |
Marine Dredging/ During construction |
Contractor(s) |
ü |
N/A |
|||
S6.9 |
Silt removal facilities such as silt traps or sedimentation facilities will be provided to remove silt particles from runoff to meet the requirements of the TM standard under the WPCO. The design of silt removal facilities will be based on the guidelines provided in ProPECC PN 1/94. All drainage facilities and erosion and sediment control structures will be inspected on a regular basis and maintained to confirm proper and efficient operation at all times and particularly during rainstorms. Deposited silt and grit will be removed regularly. |
Land site & drainage/ During construction |
Contractor(s) |
ü |
Implemented |
ProPECC PN 1/94 TM Standard under the WPCO |
||
S6.9 |
Earthworks to form the final surfaces will be followed up with surface protection and drainage works to prevent erosion caused by rainstorms. |
Land site & drainage/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S6.9 |
Appropriate surface drainage will be designed and provided where necessary. |
Land site & drainage/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S6.9 |
The precautions to be taken at any time of year when rainstorms are likely together with the actions to be taken when a rainstorm is imminent or forecasted and actions to be taken during or after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94. |
Land site & drainage/ During construction |
Contractor(s) |
ü |
ü |
Implemented |
ProPECC PN 1/94 |
|
S6.9 |
Oil interceptors will be provided in the drainage system where necessary and regularly emptied to prevent the release of oil and grease into the storm water drainage system after accidental spillages. |
Land site & drainage/ During construction |
Contractor(s) |
ü |
N/A |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S6.9 |
Temporary and permanent drainage pipes and culverts provided to facilitate runoff discharge, if any, will be adequately designed for the controlled release of storm flows. |
Land site & drainage/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S6.9 |
The temporary diverted drainage, if any, will be reinstated to the original condition when the construction work has finished or when the temporary diversion is no longer required. |
Land site & drainage/ During construction |
Contractor(s) |
ü |
N/A |
- |
||
S6.9 |
Appropriate numbers of portable toilets shall be provided by a licensed contractor to serve the construction workers over the construction site to prevent direct disposal of sewage into the water environment. |
Land site & drainage/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S6.9 and S6.12 |
The sterilization water should be dechlorinated with total residual chlorine (TRC) level below 1 mg/L before discharge to public sewer. In situ testing of TRC should also be conducted for the discharge of chlorinated water for pipeline disinfection to ensure sufficient dechlorination before discharge to public sewer. |
Sterilization of water mains prior to commissioning |
Contractor(s) |
ü |
ü |
N/A |
Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems Inland and Coastal Waters |
|
S6.9 |
The cleaning and flushing water should also be treated and desilted to the relevant discharge requirement stipulated in TM-DSS before discharging. |
Sterilization of water mains prior to commissioning |
Contractor(s) |
ü |
ü |
Implemented |
||
S6.9 |
Site drainage should be well maintained, and good construction practices should be observed to ensure that oil, fuels, solvents and other chemicals are managed, stored and handled properly and do not enter the nearby water streams. |
Land site & drainage/ During construction/ During operation |
Contractor(s) |
ü |
ü |
Implemented after reminder |
- |
|
S6.12 |
Regular site inspections will be carried out in order to confirm that regulatory requirements are being met and that contractors are implementing the standard site practice and mitigation measures as proposed to reduce potential impacts to water quality. |
During construction |
Contractor(s)/ ET & IEC |
ü |
Implemented |
- |
||
Waste Management |
||||||||
S8.5 |
Nomination of approved personnel to be responsible for standard site practices, arrangements for collection and effective disposal to an appropriate facility of all wastes generated at the site. |
Contract mobilization/ During construction |
Contractor(s) |
ü |
Implemented |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S8.5 |
Training of site personnel in proper waste management and chemical handling procedures. Training will be provided to workers on the concepts of site cleanliness and appropriate waste management procedures, including waste reduction, reuse and recycling at the beginning of the construction works. |
Contract mobilization/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S8.5 |
Provision of sufficient waste disposal points and regular collection for disposal. |
All area/ During construction/ During operation |
Contractor(s) |
ü |
ü |
Implemented |
DEVB TC(W) No. 8/2010, Enhanced Specification for Site Cleanliness and Tidiness. |
|
S8.5 |
Appropriate measures to reduce windblown litter and dust transportation of waste by either covering trucks or by transporting wastes in enclosed containers. |
All area/ During construction |
Contractor(s) |
ü |
Implemented |
|||
S8.5 |
A waste management plan (WMP) as stated in the “ETWB TC(W) No. 19/2005, Environmental Management on Construction Sites” for the amount of waste generated, recycled and disposed of (including the disposal sites) will be established and implemented during the construction phase as part of the Environmental Management Plan (EMP). The Contractor will be required to prepare the EMP and submits it to the Architect/ Engineer under the Contract for approval prior to implementation. |
All area/ During construction |
Contractor(s) |
ü |
Implemented |
ETWB TC(W) No. 19/2005, Environmental Management on Construction Sites |
||
S8.5 |
Separation of chemical wastes for special handling and appropriate treatment at the Chemical Waste Treatment Centre at Tsing Yi. |
All area/ During construction |
Contractor(s) |
ü |
Implemented |
Chapters 2 & 3 Code of Practice on the Packaging, Labelling & Storage of Chemical Wastes published under the Waste Disposal Ordinance (Cap 354), |
||
S8.5 |
Regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors. |
Land site/ During construction |
Contractor(s) |
ü |
Implemented |
Waste Disposal Ordinance (Cap 354) |
||
S8.5 |
A recording system for the amount of waste generated/ recycled and disposal sites. The trip- ticket system will be included as one of the contractual requirements and implemented by the contractor(s). |
Land site/ During construction |
Contractor(s) |
ü |
Implemented |
DEVB TC(W) No. 6/2010, Trip Ticket System for Disposal of Construction & |
||
S8.5 |
Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of material and their proper disposal. |
Land site/ During construction/ During operation |
Contractor(s) |
ü |
Implemented |
WBTC 32/92, The Use of Tropical Hard Wood on Construction Site |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S8.5 |
Encourage collection of aluminium cans and wastepaper by individual collectors during construction with separate labelled bins provided to segregate these wastes from other general refuse by the workforce. |
Land site/ During construction |
Contractor(s) |
ü |
Implemented |
ETWB TCW No. 33/2002, Management of Construction and |
||
S8.5 |
Any unused chemicals and those with remaining functional capacity will be recycled as far as possible. |
Land site/ During construction |
Contractor(s) |
ü |
N/A |
- |
||
S8.5 |
Use of reusable non-timber formwork to reduce the amount of C&D materials. |
All areas/ During construction |
Contractor(s) |
ü |
Implemented |
WBTC 32/92, The Use of Tropical Hard Wood on Construction Site |
||
S8.5 |
Prior to disposal of construction waste, wood, steel and other metals will be separated to the extent practical, for re-use and/or recycling to reduce the quantity of waste to be disposed of to landfill. |
All areas/ During construction |
Contractor(s) |
ü |
Implemented |
DEVB TC(W) No. 6/2010, Trip Ticket System for Disposal of Construction & Demolition Materials |
||
S8.5 |
Proper storage and site practices to reduce the potential for damage or contamination of construction materials. |
All areas/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S8.5 |
Plan and stock construction materials carefully to reduce amount of waste generated and avoid unnecessary generation of waste. |
All areas/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S8.5 |
A Sediment Quality Report (SQR) for sampling and chemical testing of the sediment will be prepared and submitted to the EPD for approval. The approved detailed sampling and chemical testing will be carried out prior to the commencement of the dredging activities to confirm the sediment disposal method. |
Marine works/ During construction |
Contractor(s) |
ü |
N/A |
ETWB TC(W) No. 34/2002 and Dumping at Sea Ordinance (DASO) |
||
S8.5 |
The management of dredged/ excavated sediment management requirement from ETWB TC(W) No. 34/2002 will be incorporated in the Specification of the Contract Documents. |
Marine works/ During construction |
WSD/ Contractor(s) |
ü |
Implemented |
ETWB TC(W) No. 34/2002 and Dumping at Sea Ordinance (DASO) |
||
S8.5 |
The contractor will open a billing account with EPD in accordance with the Waste Disposal (Charges for Disposal of Construction Waste) Regulation for the payment of disposal charges. |
Contract mobilization/ During construction |
Contractor(s) |
ü |
Implemented |
Cap 354N Waste Disposal (Charges for Disposal of Construction Waste) Regulation |
||
S8.5 |
A trip-ticket system will be established in accordance with DEVB TC(W) No. 6/2010 to monitor the reuse of surplus excavated materials off-site and disposal of construction waste and general refuse at transfer facilities/ landfills, and to control fly-tipping. |
Contract mobilization/ During construction |
Contractor(s) |
ü |
Implemented |
DEVB TC(W) No. 6/2010, Trip Ticket System for Disposal of Construction & Demolition Materials |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S8.5 |
The project proponent will also conduct regular inspection of the waste management measures implemented on site as described in the Waste Management Plan. |
All area/ During construction |
Contractor(s)/ Environmental Team (ET) & Independent Environmental Checker (IEC) |
ü |
Implemented |
ETWB TC(W) No. 19/2005, Environmental Management on Construction Sites |
||
S8.5 |
A recording system (similar to summary table as shown in Annex 5 and Annex 6 of Appendix G of ETWB TC(W) No. 19/2005) for the amount of waste generated, recycled and disposed of (including the disposal sites) will be established during the construction phase. |
All area/ During construction |
Contractor(s) |
ü |
Implemented |
Annex 5 and Annex 6 of Appendix G of ETWB TC(W) No. 19/2005 |
||
S8.5 |
Inert C&D materials (public fill) will be reused within the Project as far as practicable. |
All area/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S8.5 |
Public fill and construction waste shall be segregated and stored in different containers or skips to facilitate reuse or recycling of materials and their proper disposal. |
All area/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S8.5 |
Specific areas of the work site will be designated for such segregation and storage if immediate use is not practicable. |
All area/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S8.5 |
To reduce the potential dust and water quality impacts of site formation works, C&D materials will be wetted as quickly as possible to the extent practice after filling. |
All area/ During construction |
Contractor(s) |
ü |
Implemented |
Air Pollution Control (Construction Dust) Regulation (Cap 311R); WPCO (Cap 358) |
||
S8.5 |
Open stockpiles of excavated/ fill materials or construction wastes on-site should be covered with tarpaulin or similar fabric. |
Land site/ During Construction, particularly dry season |
Contractor(s) |
ü |
Implemented |
Air Pollution Control (Construction Dust) Regulation (Cap 311R) |
||
S8.5 |
Chemical waste container shall be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
ü |
ü |
Implemented |
Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes |
|
S8.5 |
Chemical waste container shall have a capacity of less than 450 L unless the specifications have been approved by the EPD. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
ü |
ü |
Implemented |
||
S8.5 |
A label in English and Chinese shall be displayed on the chemical container in accordance with instructions prescribed in Schedule 2 of the Regulations. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
ü |
ü |
Implemented |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S8.5 |
Storage areas for chemical waste shall be enclosed on at least 3 sides. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
ü |
ü |
Implemented |
||
S8.5 |
Storage areas for chemical waste shall have an impermeable floor and bunding, of capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in that area, whichever is the greatest. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
ü |
ü |
Implemented |
||
S8.5 |
Storage areas for chemical waste shall have adequate ventilation. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
ü |
ü |
Implemented |
||
S8.5 |
Storage areas for chemical waste shall be covered to prevent rainfall entering (water collected within the bund must be tested and disposed of as chemical waste, if necessary). |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
ü |
ü |
Implemented |
||
S8.5 |
Storage areas for chemical waste shall be arranged so that incompatible materials are appropriately separated. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
ü |
ü |
Implemented |
||
S8.5 |
General refuse will be stored in enclosed bins or compaction units separately from construction and chemical wastes. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
ü |
ü |
Implemented after reminder |
||
S8.5 |
Adequate number of waste containers will be provided to avoid over-spillage of waste. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
ü |
ü |
Implemented |
DEVB TC(W) No. 8/2010 Enhanced Specification for Site Cleanliness and Tidiness. |
|
S8.5 |
A reputable waste collector will be employed by the Contractor to remove general refuse from the site, separately from construction and chemical wastes, on a daily basis to minimise odour, pest and litter impacts. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
ü |
ü |
Implemented after reminder |
- |
|
S8.5 |
Recycling bins will be provided at strategic locations within the Site to facilitate recovery of recyclable materials (including aluminum can, waste paper, glass bottles and plastic bottles) from the Site. Materials recovered will be sold for recycling. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
ü |
ü |
Implemented |
- |
|
S8.5 |
To avoid any odour and litter impact, accurate number of portable toilets will be provided for workers on-site. |
All area/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S8.5 |
The burning of refuse on construction sites is prohibited by law. |
All area/ During construction |
Contractor(s) |
ü |
Implemented |
Air Pollution Control Ordinance (Cap 311) |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S8.7 |
To facilitate monitoring and control over the contractors’ performance on waste management, a waste inspection and audit programme will be implemented throughout the construction phase. |
All facilities/ During construction |
ET/ IEC |
ü |
Implemented |
- |
||
Ecology |
||||||||
S9.7 |
For slope mitigation works within the Clear Water Bay Country Park, to avoid tree felling and damages to trees, the exact locations of the flexible barrier foundation plates, soil nails and rock dowels can be adjusted during detailed design, and a setback distance from existing trees is recommended to be maintained as far as practical. A detailed specification describing the exact locations of the flexible barrier foundation plates, soil nails and rock dowels will be prepared to illustrate how the setback distance from existing trees would be implemented for tree avoidance. |
Slope mitigation works area/ During detailed design/ During construction |
Contractor(s) |
ü |
ü |
Implemented |
- |
|
S9.7 |
Pruning of tree canopies along the alignment of the flexible barriers shall be limited to a minimum. |
Slope mitigation works area/ During construction |
Contractor(s) |
ü |
Implemented |
|||
S9.7 |
The alignment of flexible barriers shall be optimized to preserve all species of conservation interest and minimize the impact to the existing vegetation as far as practicable. All individuals of Marsdenia lachnostoma within the slope mitigation areas shall be retained in- situ, by positioning the alignment of flexible barrier at a minimum 1.5m in a radius away from these individuals. |
Slope mitigation works area/ During detailed design/ During construction |
Contractor(s) |
ü |
ü |
Implemented |
- |
|
S9.7 and 9.10 |
At the detailed design stage prior to the commencement of the slope mitigation works, a vegetation survey shall be carried out at the slope mitigation areas within the Clear Water Bay Country Park to assess the condition and identify the location of each individual of Marsdenia lachnostoma and other flora species of conservation interest that may be directly affected by the construction works. |
Slope mitigation works area/ During detailed design/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S9.7 |
Temporary fencing will be installed to fence off the concerned species either in groups of individually within the works area and in the close proximity to prevent from being damaged and disturbed during construction. A sign identifying the site shall be attached to the fence and flagging tape shall be attached to the individuals to visualize their locations. |
Slope mitigation works area/ During construction |
Contractor(s) |
ü |
Implemented |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S9.7 and S9.10 |
A specification for fencing and demarcating individuals of Marsdenai lachnostoma (or other flora species of conservation interest, if found) adjacent to the proposed alignment of the flexible barriers will be prepared to protect the species. |
Slope mitigation works area/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S9.7 |
Induction training shall also be provided to all site personnel in order to brief them on this flora of conservation interest including the locations and their importance. |
Slope mitigation works area/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S9.7 |
The resident site supervisory staff will closely monitor the conditions of concerned individuals during construction of flexible barriers in the close proximity. |
Slope mitigation works area/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S9.7 |
Erect fences along the boundary of the works area before the commencement of works to prevent vehicle movements and encroachment of personnel onto adjacent areas. |
All area/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S9.7 |
Regularly check the work site boundaries to ensure that they are not breached and that damage does not occur to surrounding areas. |
All area/ During construction |
Contractor(s)/ ET |
ü |
Implemented after reminder |
- |
||
S9.7 |
Avoid any damage and disturbance, particularly those caused by filling and illegal dumping, to the surrounding habitats through proper management of waste disposal. |
All area/ During construction |
Contractor(s) |
ü |
Implemented |
- |
||
S9.7 |
Reinstate temporarily affected areas, particularly the habitats of plantation and shrubland-grassland immediately after completion of construction works, through on-site tree/shrub planting. The tree/shrub species will be chosen with reference to those in the surrounding area. |
All area/ During construction |
Contractor(s) |
ü |
To be Implemented |
- |
||
S9.7 |
Affected habitats within the Clear Water Bay Country Bay shall be reinstated by hydro-seeding and planting of climbers and native shrub seedlings where practical upon completion of the slope mitigation works. |
All area/ During construction |
Contractor(s) |
ü |
To be Implemented |
- |
||
Landscape & Visual |
||||||||
S11.10 & 11.11 |
The construction area and area allowed for temporary structures, such as the contractor’s office, will be minimized to a practical minimum. (MM1) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S11.10 & 11.11 |
At the detailed design stage, the design team will seek to minimize the landscape footprint of the Project and above ground facilities, while satisfying all other requirements. (MM2) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S11.10 & 11.11 |
Design principles will be
adopted to take into account the surrounding area,
particularly Clear Water Bay Country Park behind and the nearby waterfront,
with due consideration given to: ·
green roofs where practical
(i.e. without equipment on the roof); · roadside planting; · aesthetic treatment of all structures; · vertical greening; · screen planting along application site; and · landscape enhancement with amenity planting where practical including planting along the edge (site boundary) fence with native shrubs where feasible, to reduce their visual impact and blend them into the surrounding landscape. (MM3) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
-- |
S11.10 & 11.11 |
All trees within the Project Site or the potential slope mitigation works area will be carefully protected during construction according to DEVB TCW No. 10/2013 – Tree Preservation (MM4) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented after reminder |
ETWB TCW No. 3/2006 - Tree Preservation. |
S11.10 & 11.11 |
No tree within the Country Park will be felled. Trees within the Site unavoidably affected by the works will be transplanted where necessary and practical. For trees that need to be felled, compensatory planting will be provided to the satisfaction of relevant Government departments. A compensatory tree planting proposal including locations of tree compensation will be submitted to seek relevant government department’s approval, in accordance with DEVB TC(W) No. 10/2013. (MM5) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
DEVB TC(W) No. 10/2013 |
S11.10 & 11.11 |
Any slope mitigation works necessary to address natural terrain hazards, will be minimized to minimize any potential environmental impact to the Country Park e.g. soil nailing and rock stabilization will aim to avoid existing trees e.g. should any restoration of vegetation be necessary, the best planting matrix with native species will be established, with the aim of resembling the existing vegetation. (MM6) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
N/A |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S11.10 & 11.11 |
Dredging works for the installation of intake structures and outfall diffusers should be minimized to avoid or reduce any potential environmental impacts to as low as reasonably practicable (ALARP). The intake and outfall structures (e.g. intake openings and diffuser heads) will be prefabricated and transferred to site for installation. (MM7) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S11.10 & 11.11 |
All night-time lighting will be reduced to a practical minimum both in terms of number of level and will be hooded and directional. (MM8) units and lux level and will be hooded and directional. (MM8) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
Landfill Gas Hazard |
||||||||
S12.7 |
During all works, safety procedures should be implemented to minimise the risks of fires and explosions, asphyxiation of workers and toxicity effects resulting from contact with contaminated soil and groundwater. |
All area/ Detailed design/ During construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
During trenching and excavation as well as creation of confined spaces at near to or below ground level, precautions should be clearly laid down and rigidly Gas detection equipment and appropriate breathing apparatus should be available and used when entering confined spaces or trenches deeper than 1 meter. |
All area/ Detailed design/ During construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
The Contractor should make the workers are aware of potential hazards of working in confined spaces (any chamber, manhole or culvert which is large enough to permit access to personnel). Such work in confined spaces is controlled by the Factories and Industrial Undertakings (Confined Spaces) Regulations of the Factories and Industrial Undertakings Ordinance. Following the Safety Guide to Working in Confined Spaces ensures compliance with the above regulations. |
All area/ Detailed design/ During construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
Safety officers, specifically trained with regard to landfill gas and leachate related hazards and the appropriate actions to take in adverse circumstances, should be present on the site throughout the works, in particular, when works are undertaken below grade. |
All area/ Detailed design/ During construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
All personnel who work on site and all visitors to the site should be made aware of the possibility of ignition of gas in the vicinity of the works, the possible presence of contaminated water and the need to avoid physical contact with it. |
All area/ Detailed design/ During construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S12.7 |
Monitoring for landfill gas should be undertaken in all excavations, manholes, chambers (particularly during pipe jacking) and any confined spaces through the use of an intrinsically safe portable instrument, appropriately calibrated and capable of measuring the concentrations of methane. carbon dioxide and oxygen. |
All area/ Detailed design/ During construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
Monitoring frequency and areas to be monitored should be specified prior to commencement of groundwork, either by the Safety Officer, or by an appropriately qualified person. All measurements should be recorded and documented. |
All area/ Detailed design/ During construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
Proceed drilling with adequate care and precautions against the potential hazards which may be encountered. |
All area/ Detailed design/ During construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
Prior to the commencement of the site works, the drilling contractor should devise a 'method-of- working' statement covering all normal and emergency procedures (including but not limited to number of operatives, experience and special skills of operatives, normal method of operations, emergency procedures, supervisors responsibilities, storage and use of safety equipment, safety procedures and signs, barriers and guarding). The site supervisor and all operatives must be familiar with this statement. |
All area/ During construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
Where below ground service entries are necessary to the Incoming Switchgear Room, 132 kV Substation and Chlorine Store (I) and (II), the entry point should be sealed to prevent gas entry. In addition, any below grade cable trenches entering the Incoming Switchgear Room and 132 kV Substation can become the pathway for landfill gas and hence grilled metal covers should be used. |
All area/ Detailed design/ During construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
N/A |
- |
S12.7 |
It is recommended regular landfill gas monitoring should be carried out at the Incoming Switchgear Room, 132 kV Substation and Chlorine Store (I) and (II). The monitoring frequency will be monthly for the first year of operation. If the monitoring results show no sign of landfill gas migration, reduce the monitoring frequency to once every six months. |
All area/ Detailed design/ During construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
N/A |
- |
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S12.7 |
The manholes and utility pits within the Project Site and along the freshwater mains. Each manhole/ utility pit should be monitored with two measurements (at mid depth and base). Each measurement should be monitored for a minimum of 10 minutes. A steady reading and peak reading should be recorded at each manhole/ utility pit and for each measurement. The need for venting the manhole/ utility pit and further monitoring will be reviewed after the initial monitoring. |
All area/ Detailed design/ During construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
All construction, operation and maintenance personnel working on-site as well as visitors should be made aware of the hazards of landfill gas and its possible presence on-site. This should be achieved through a combination of posting warning signs in prominent places and also by access to detailed information on landfill gas hazards and the designs and procedural means by which these hazards are being minimized on-site. |
All area/ Detailed design/ During construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
Note: D – Design stage C – Construction O –
Operation
|
Contract
No. 13/WSD/17
Design, Build and Operate First
Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report
Appendix D
Water Quality Monitoring Graphical
Presentation
·
Appendix
D.1 Weather Condition
·
Appendix
D.2 Key Activities Carried Out During the Reporting Quarter
·
Appendix
D.3 Other Factor Might Affect the Monitoring Results
|
|
Dissolved Oxygen
11
10
9
8
7
6
5
4
3
2
1
0
DO
Date
|
Turbidity
4
3
2
1
0
Date
Turb
|
|
Suspended Solids
20
18
16
14
12
10
8
6
4
2
0
Date
Date SS
|
|
|
Salinity
35
34
33
32
31
30
29
28
Date
Series1
|
|
Concentration, mg/L
Concentration, NTU
Concentration, NTU
Concentration, NTU
Iron
0.3
0.25
0.2
0.15
0.1
0.05
0
Date
Iron
|
|
Total Residual
Chlorine
0.3
0.25
0.2
0.15
0.1
0.05
0
Date
TRC
|
Concentration, mg/L
Concentration, mg/L
Remark: The lowest detection limit of the Iron is
0.1mg/L. All result of iron monitoring are lower than
the detection limit.
Remark: The lowest detection limit of the Total
Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring
are lower than the detection limit.
|
Dissolved Oxygen
12
10
8
6
4
2
0
Date
DO
Turbidity
3
3
2
2
1
1
0
Date
Turb
Suspended Solids
60
50
40
30
20
10
0
Date
SS
|
|
|
|
Salinity
34
34
33
33
32
32
31
31
30
Date
Sal.
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Monitoring Location: CF
|
Iron
0.3
0.25
0.2
0.15
0.1
0.05
0
Date
Iron
|
Concentration, mg/L
Monitoring Location: CF
Total Residual
Chlorine
0.3
0.25
0.2
0.15
0.1
0.05
0
Date
TRC
|
Concentration, mg/L
Remark: The lowest detection limit of the Iron is
0.1mg/L. All result of iron monitoring are lower than
the detection limit.
Remark: The lowest detection limit of the Total
Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring
are lower than the detection limit.
DO
Action Level
Limit Level
Dissolved Oxygen
10
9
8
7
6
5
4
3
2
1
0
Date
Turbidity
3
3
2
2
1
1
0
Date
Turb
Action Level (Baseline) Limit Level
(Baseline)
Suspended Solids
60
50
40
30
20
10
0
Date
SS
Action Level (Baseline) Limit
Level (Baseline)
|
|
|
|
Salinity
35
34
33
32
31
30
29
Date
Sal.
Action Level (Baseline) Limit
Level (Baseline)
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
|
Iron
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Date
Iron
Action Level
Total Residual
Chlorine
0.012
0.01
0.008
0.006
0.004
0.002
0
Date
TRC
Action Level
|
|
Concentration, mg/L
Concentration, mg/L
Remark: The lowest detection limit of the Iron is
0.1mg/L. All result of iron monitoring are lower than
the detection limit.
Remark: The lowest detection limit of the Total
Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring
are lower than the detection limit.
DO
Action Level
Limit Level
Dissolved Oxygen
12
10
8
6
4
2
0
Date
|
|
Turbidity
3
3
2
2
1
1
0
Date
Turb
Action Level (Baseline) Limit Level
(Baseline)
|
Suspended Solids
20
18
16
14
12
10
8
6
4
2
0
Date
SS
Action Level (Baseline) Limit
Level (Baseline)
|
|
|
|
Salinity
35
34
33
32
31
30
29
Date
Sal.
Action Level (Baseline)
Limit Level (Baseline)
|
|
|
|
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
|
Iron
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Date
Iron
Action Level
Total Residual
Chlorine
0.012
0.01
0.008
0.006
0.004
0.002
0
Date
TRC
Action Level
|
|
Concentration, mg/L
Concentration, mg/L
Remark: The lowest detection limit of the Iron is
0.1mg/L. All result of iron monitoring are lower than
the detection limit.
Remark: The lowest detection limit of the Total
Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring
are lower than the detection limit.
|
DO
Action Level
Limit Level
Dissolved Oxygen
12
10
8
6
4
2
0
Date
|
Suspended Solids
18
16
14
12
10
8
6
4
2
0
Date
SS
Action Level (Baseline)
Limit Level (Baseline)
|
|
|
|
|
Turbidity
3
3
2
2
1
1
0
Date
Turb
Action Level (Baseline) Limit Level
(Baseline)
|
Salinity
35
34
33
32
31
30
29
Date
Sal.
Action Level (Baseline) Limit
Level (Baseline)
|
|
|
|
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
|
Iron
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Date
Iron
Action Level
Total Residual
Chlorine
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Date
Iron
Action Level
|
|
Concentration, mg/L
Concentration, mg/L
Remark: The lowest detection limit of the Iron is
0.1mg/L. All result of iron monitoring are lower than
the detection limit.
Remark: The lowest detection limit of the Total
Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring
are lower than the detection limit.
|
|
DO
Action Level
Limit Level
Dissolved Oxygen
12
10
8
6
4
2
0
Date
|
Turbidity
3
3
2
2
1
1
0
Date
Turb
Action Level (Baseline)
Limit Level (Baseline)
|
Suspended Solids
18
16
14
12
10
8
6
4
2
0
Date
SS
Action Level (Baseline) Limit
Level (Baseline)
|
|
|
|
|
Salinity
35
34
33
32
31
30
29
28
Date
Sal.
Action Level (Baseline) Limit Level
(Baseline)
|
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
|
Iron
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Date
Iron
Action Level
Total Residual
Chlorine
0.012
0.01
0.008
0.006
0.004
0.002
0
Date
TRC
Action Level
|
|
Concentration, mg/L
Concentration, mg/L
Remark: The lowest detection limit of the Iron is
0.1mg/L. All result of iron monitoring are lower than
the detection limit.
Remark: The lowest detection limit of the Total
Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring
are lower than the detection limit.
|
DO
Action Level
Limit Level
Dissolved Oxygen
10
9
8
7
6
5
4
3
2
1
0
Date
|
Turbidity
3
3
2
2
1
1
0
Date
Turb
Action Level (Baseline)
Limit Level (Baseline)
|
Suspended Solids
18
16
14
12
10
8
6
4
2
0
Date
SS
Action Level (Baseline)
Limit Level (Baseline)
|
|
|
|
|
Salinity
35
34
33
32
31
30
29
28
Date
Sal.
Action Level (Baseline) Limit Level
(Baseline)
|
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
|
Iron
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Date
Iron
Action Level
Total Residual
Chlorine
0.012
0.01
0.008
0.006
0.004
0.002
0
Date
TRC
Action Level
|
|
Concentration, mg/L
Concentration, mg/L
Remark: The lowest detection limit of the Iron is
0.1mg/L. All result of iron monitoring are lower than
the detection limit.
Remark: The lowest detection limit of the Total
Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring
are lower than the detection limit.
DO
Action Level
Limit Level
Dissolved Oxygen
10
9
8
7
6
5
4
3
2
1
0
Date
|
Turbidity
3
3
2
2
1
1
0
Date
Turb
Action Level (Baseline)
Limit Level (Baseline)
|
Suspended Solids
16
14
12
10
8
6
4
2
0
Date
SS
Action Level (Baseline)
Limit Level (Baseline)
|
|
|
|
Salinity
35
34
33
32
31
30
29
Date
Sal.
Action Level (Baseline)
Limit Level (Baseline)
|
|
|
|
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
|
Iron
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Date
Iron
Action Level
Total Residual
Chlorine
0.012
0.01
0.008
0.006
0.004
0.002
0
Date
TRC
Action Level
|
|
Concentration, mg/L
Concentration, mg/L
Remark: The lowest detection limit of the Iron is
0.1mg/L. All result of iron monitoring are lower than
the detection limit.
Remark: The lowest detection limit of the Total
Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring
are lower than the detection limit.
|
DO
Action Level
Limit Level
Dissolved Oxygen
12
10
8
6
4
2
0
Date
|
Turbidity
3
3
2
2
1
1
0
Date
Turb
Action Level (Baseline)
Limit Level (Baseline)
|
Suspended Solids
20
18
16
14
12
10
8
6
4
2
0
Date
SS
Action Level (Baseline) Limit
Level (Baseline)
|
|
|
|
|
|
Salinity
35
34
33
32
31
30
29
Date
Sal.
Action Level (Baseline)
Limit Level (Baseline)
|
|
|
|
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
|
Iron
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Date
Iron
Action Level
Total Residual
Chlorine
0.012
0.01
0.008
0.006
0.004
0.002
0
Date
TRC
Action Level
|
|
Concentration, mg/L
Concentration, mg/L
Remark: The lowest detection limit of the Iron is
0.1mg/L. All result of iron monitoring are lower than
the detection limit.
Remark: The lowest detection limit of the Total
Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring
are lower than the detection limit.
|
DO
Action Level
Limit Level
Dissolved Oxygen
10
9
8
7
6
5
4
3
2
1
0
Date
|
Turbidity
3
3
2
2
1
1
0
Date
Turb
Action Level (Baseline)
Limit Level (Baseline)
|
|
|
Suspended Solids
20
18
16
14
12
10
8
6
4
2
0
Date
SS
Action Level (Baseline)
Limit Level (Baseline)
|
|
|
|
|
Salinity
35
34
33
32
31
30
29
28
Date
Sal.
Action Level (Baseline)
Limit Level (Baseline)
|
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Monitoring Location: WSR37
Iron
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Date
Iron
Action Level
Total Residual
Chlorine
0.12
0.1
0.08
0.06
0.04
0.02
0
Date
TRC
Action Level
|
|
Concentration, mg/L
Remark: The lowest detection limit of the Iron is
0.1mg/L. All result of iron monitoring are lower than
the detection limit.
Remark: The lowest detection limit of the Total
Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring
are lower than the detection limit.
|
DO
Action Level
Limit Level
Dissolved Oxygen
10
9
8
7
6
5
4
3
2
1
0
Date
|
Turbidity
3
3
2
2
1
1
0
Date
Turb
Action Level (Baseline) Limit Level
(Baseline)
|
Suspended Solids
18
16
14
12
10
8
6
4
2
0
Date
SS
Action Level (Baseline)
Limit Level (Baseline)
|
|
|
|
|
Salinity
35
34
33
32
31
30
29
28
Date
Sal.
Action Level (Baseline) Limit Level
(Baseline)
|
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
The lowest detection limit of the Iron is
0.1mg/L. All result of iron monitoring are lower than
the detection limit.
Iron
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Date
Iron
Action Level
Total Residual
Chlorine
0.12
0.1
0.08
0.06
0.04
0.02
0
Date
TRC
Action Level
|
|
Concentration, mg/L
Concentration, mg/L
Remark:
Remark: The lowest detection limit of the Total
Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring
are lower than the detection limit.
|
DO
Action Level
Limit Level
Dissolved Oxygen
10
9
8
7
6
5
4
3
2
1
0
Date
|
Turbidity
3
3
2
2
1
1
0
Date
Turb
Action Level (Baseline) Limit Level
(Baseline)
|
Suspended Solids
18
16
14
12
10
8
6
4
2
0
Date
SS
Action Level (Baseline)
Limit Level (Baseline)
|
|
|
|
|
Salinity
35
34
33
32
31
30
29
Date
Sal.
Action Level (Baseline) Limit
Level (Baseline)
|
|
|
|
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Iron
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Date
Iron
Action Level
Total Residual
Chlorine
0.12
0.1
0.08
0.06
0.04
0.02
0
Date
TRC
Action Level
|
|
Concentration, mg/L
Concentration, mg/L
Remark: The lowest detection limit of the Iron is
0.1mg/L. All result of iron monitoring are lower than
the detection limit.
Remark: The lowest detection limit of the Total
Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring
are lower than the detection limit.
|
DO
Action Level
Limit Level
Dissolved Oxygen
12
10
8
6
4
2
0
Date
|
Turbidity
3
3
2
2
1
1
0
Date
Turb
Action Level (Baseline) Limit Level
(Baseline)
|
Suspended Solids
20
18
16
14
12
10
8
6
4
2
0
Date
SS
Action Level (Baseline)
Limit Level (Baseline)
|
|
|
|
|
Salinity
35
34
33
32
31
30
29
Date
Sal.
Action Level (Baseline)
Limit Level (Baseline)
|
|
|
|
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
|
The lowest detection limit of the Iron is
0.1mg/L. All result of iron monitoring are lower than
the detection limit.
Iron
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Date
Iron
Action Level
Total Residual
Chlorine
0.12
0.1
0.08
0.06
0.04
0.02
0
Date
TRC
Action Level
|
|
Concentration, mg/L
Concentration, mg/L
Remark:
Remark: The lowest detection limit of the Total
Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring
are lower than the detection limit.
Salinity
80
70
60
50
40
30
20
10
0
Month
Sal (ppt) Limit Level
|
|
|
|
pH
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Month
pH
Limit Level
|
|
|
|
Temperature
45
40
35
30
25
20
15
10
5
0
Month
Temp (°C) Limit Level
|
|
|
|
pH
Concentration, mg/L
Temp (°C)
Total Residual
Chlorine
0.16
0.14
0.12
0.10
0.08
0.06
0.04
0.02
0.00
Month
Total Residual Chlorine (mg/L)
Limit Level
|
|
|
|
Suspended Solids
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
0
Month
Suspended Solids (mg/L)
Limit Level
|
|
|
|
Total Inorganic
Nitrogen
2.2
2.0
1.8
1.6
1.4
1.2
1.0
0.8
0.6
0.4
0.2
0.0
Month
Total Inorganic Nitrogen (mg/L)
Limit Level
|
|
|
|
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Total Phosphorus
1.20
1.10
1.00
0.90
0.80
0.70
0.60
0.50
0.40
0.30
0.20
0.10
0.00
Month
Total Phosphorus (mg/L)
Limit Level
|
|
|
|
Sodium Metabisulphite
5.00
4.50
4.00
3.50
3.00
2.50
2.00
1.50
1.00
0.50
0.00
Month
Sodium Metabisulphite (mg/L)
Limit Level
|
|
|
|
Iron
(mg/L)
Limit Level
Iron
1.00
0.90
0.80
0.70
0.60
0.50
0.40
0.30
0.20
0.10
0.00
Month
|
|
|
|
Concentration, mg/L
Concentration, mg/L
Concentration, mg/L
Remark: Due to the limitation of the laboratory,
the lowest result for Sodium Metabisulphite will only
be shown as < 2 mg/L.
|
flI081 |
33.0 |
|
28.1 |
26.5 |
|
S7 |
Trace |
vs |
|
S.7 |
|||||
02 |
Â0L6 |
342 |
30.6 |
28.4 |
26.2 |
78 |
50 |
Trace |
8.4 |
160 |
43 |
|||||
03 |
JtI061 |
33.S |
|
25.5 |
258 |
78 |
85 |
3vs |
8.3 |
180 |
#.5 |
|||||
04 |
10023 |
32.5 |
29.7 |
26.5 |
24.7 |
75 |
|
0.6 |
7.1 |
070 |
|
|||||
05 |
999.5 |
33.4 |
304 |
26.2 |
24.5 |
|
|
21.5 |
4.3 |
050 |
53.8 |
|||||
06 |
1001.6 |
268 |
276 |
259 |
25.7 |
|
95 |
84.1 |
0.0 |
070 |
56.8 |
|||||
07 |
JtI071 |
09 |
|
2L9 |
26.9 |
|
|
5.8 |
25 |
|
|
|||||
08 |
Â08.6 |
30.1 |
28.2 |
27.3 |
26.5 |
91 |
|
37.8 |
2.3 |
080 |
16.3 |
|||||
09 |
1007.7 |
30.0 |
27.8 |
26.3 |
25.g |
|
83 |
13.0 |
3.0 |
080 |
11.7 |
|||||
10 |
Â073 |
33.3 |
294 |
26.8 |
24.8 |
|
60 |
0.0 |
1¥.0 |
080 |
9.9 |
|||||
|
flI081 |
34.3 |
304 |
28.2 |
25.4 |
|
SI |
0.0 |
|
040 |
6.7 |
|||||
12 |
10070 |
322 |
296 |
27.7 |
25.1 |
|
55 |
0.0 |
9.8 |
230 |
4.s |
|||||
13 |
1005.1 |
34.5 |
304 |
28.2 |
24.9 |
|
|
0.1 |
\ 0.8 |
070 |
7.3 |
|||||
14 |
Â028 |
33.5 |
29.2 |
26.7 |
24.4 |
76 |
|
5L2 |
5.8 |
|
5.4 |
|||||
15 |
10023 |
31.7 |
29.3 |
2L4 |
24.6 |
|
|
24 |
6.9 |
Zb0 |
6.4 |
|||||
16 |
10040 |
06 |
28.5 |
258 |
24.8 |
81 |
85 |
27.4 |
4.1 |
050 |
25.1 |
|||||
17 |
1004.1 |
35.7 |
30.8 |
26.3 |
25.5 |
|
76 |
UO |
9.9 |
040 |
20.6 |
|||||
18 |
JtI039 |
32.8 |
29.7 |
26.8 |
24.3 |
|
|
Trace |
8.4 |
070 |
|
|||||
19 |
Â032 |
33.6 |
|
28.7 |
252 |
7S |
|
0.0 |
9.4 |
070 |
264 |
|||||
20 |
Â032 |
32.6 |
296 |
27.p |
25.7 |
|
|
4.6 |
5.7 |
050 |
12.4 |
|||||
|
10035 |
28.8 |
2T.7 |
25.7 |
258 |
|
|
72.9 |
0.1 |
080 |
¥09 |
|||||
22 |
1005.8 |
30.1 |
27.¥ |
244 |
24.8 |
|
91 |
32d |
0.0 |
Z60 |
22.6 |
|||||
23 |
JtI090 |
28.0 |
25.7 |
23.4 |
23.9 |
|
90 |
24.9 |
os |
|
23.3 |
|||||
2Æ |
Â¥0.6 |
28.2 |
26.7 |
25.2 |
252 |
91 |
89 |
75.0 |
1.0 |
190 |
11.7 |
|||||
25 |
1011.2 |
31.4 |
28.5 |
26.9 |
252 |
|
73 |
5.'Æ |
|
240 |
11.0 |
|||||
26 |
1011.2 |
31.6 |
294 |
27.p |
25.1 |
78 |
39 |
0.0 |
10.3 |
250 |
16.4 |
|||||
27 |
10¥0.1 |
Z2.4 |
29.9 |
28.1 |
25.g |
|
41 |
0.0 |
\ 0.6 |
250 |
20.6 |
|||||
2B |
Â092 |
32.1 |
29d |
27.5 |
25.4 |
|
|
1.3 |
5.7 |
080 |
16.8 |
|||||
29 |
flI08.6 |
31.8 |
|
26.6 |
24.4 |
|
|
3.3 |
9.2 |
|
8.0 |
|||||
30 |
1005.5 |
33.3 |
305 |
27.9 |
24.4 |
71 |
61 |
0.0 |
ss |
280 |
¥3.2 |
|||||
JtI061 |
Z2.0 |
|
2&8 |
252 |
|
|
520.9 |
190.5 |
080 |
17.2 |
|
|
Normal’
30.5
279
26Ù
23.6 78
321.4
174.4
080
21.4
|
” Information of wind direction and wind
speed for Waglan Island are based on autarriafic weather sfaôan dafa since August 1989
Traœ means rainfall less than mm
? 1991-2020 Climatotogical Nonnat. unless otherwise specified
|
||||||||||||||||||||||||
|
1005.2 |
34.2 |
à0.9 |
27.8 |
2t6 |
|
|
0.0 |
8.4 |
350 |
|
|||||||||||||
02 |
10099 |
308 |
274 |
25.5 |
|
75 |
0.0 |
9.S |
J50 |
40.2 |
||||||||||||||
03 |
1013.2 |
29.# |
26¥ |
23.J |
14.6 |
|
|
0.0 |
10.5 |
|
33.4 |
|||||||||||||
04 |
1014. 4 |
30.9 |
270 |
246 |
50 |
69 |
0.0 |
6.6 |
J60 |
18.8 |
||||||||||||||
OS |
|
31.5 |
279 |
25.5 |
20.0 |
|
80 |
0.0 |
6.9 |
|
20.0 |
|||||||||||||
06 |
1013.7 |
33.3 |
29.2 |
26?' |
70 |
42 |
0.0 |
10.5 |
080 |
14.0 |
||||||||||||||
07 |
1014.4 |
32.9 |
293 |
27.J |
222 |
|
60 |
0.0 |
zs |
080 |
10. 4 |
|||||||||||||
08 |
1014.2 |
31.7 |
262 |
262 |
|
J5 |
0.0 |
9.2 |
J60 |
2#.B |
||||||||||||||
09 |
1013.5 |
27.# |
26. 4 |
25.2 |
20.1 |
|
8J |
Trace |
05 |
010 |
22.B |
|||||||||||||
|
1013.0 |
30.6 |
270 |
2%5 |
|
58 |
Trace |
6.0 |
080 |
19.2 |
||||||||||||||
11 |
|
27/5 |
25.3 |
23.2 |
21.0 |
|
|
|
080 |
216 |
||||||||||||||
¥2 |
1015.1 |
29.7 |
270 |
25.6 |
202 |
67 |
31 |
0.0 |
10.7 |
080 |
31.3 |
|||||||||||||
13 |
1014.5 |
302 |
275 |
25.9 |
222 |
|
65 |
0.0 |
9.4 |
070 |
29.5 |
|||||||||||||
¥4 |
1013.5 |
31.0 |
260 |
26.3 |
34 |
0.0 |
9.9 |
080 |
24.0 |
|||||||||||||||
as |
|
09 |
28¥ |
26.6 |
230 |
75 |
|
0.0 |
|
080 |
22.7 |
|||||||||||||
|
1014.5 |
31.1 |
262 |
27.4 |
74 |
88 |
Trace |
5.3 |
080 |
339 |
||||||||||||||
17 |
|
297 |
278 |
27.1 |
230 |
|
85 |
Trace |
19 |
080 |
320 |
|||||||||||||
|
1013.2 |
30.7 |
263 |
27? |
78 |
85 |
Trace |
6.6 |
080 |
19.3 |
||||||||||||||
19 |
1014.1 |
33.7 |
292 |
26.4 |
23.9 |
74 |
43 |
0.0 |
9.6 |
080 |
0.1 |
|||||||||||||
20 |
1016.5 |
29.7 |
279 |
26.9 |
75 |
|
1.9 |
3.4 |
080 |
39.8 |
||||||||||||||
2¥ |
1015.0 |
31.5 |
278 |
26.4 |
229 |
75 |
69 |
Trace |
4.0 |
080 |
25.0 |
|||||||||||||
22 |
1013.7 |
32.J |
263 |
26.0 |
|
52 |
0.0 |
10.0 |
J60 |
2'$2 |
||||||||||||||
23 |
1012.4 |
26# |
25.7 |
23.4 |
16.4 |
57 |
81 |
0.0 |
83 |
|
40.5 |
|||||||||||||
2Æ |
10092 |
28.5 |
24.8 |
22.0 |
06 |
42 |
84 |
0.0 |
10.0 |
J60 |
39.2 |
|||||||||||||
2S |
1006.7 |
29.# |
260 |
22.9 |
13.2 |
|
|
0.0 |
8.4 |
|
38.4 |
|||||||||||||
26 |
10066 |
28.5 |
26.6 |
25.3 |
19g |
67 |
88 |
0.7 |
0.7 |
050 |
41.9 |
|||||||||||||
27 |
1009.3 |
29.2 |
27.3 |
25.9 |
220 |
|
|
Trace |
J.3 |
050 |
2?0 |
|||||||||||||
28 |
1010.1 |
27.2 |
258 |
246 |
192 |
67 |
83 |
Trace |
0.3 |
J60 |
26.3 |
|||||||||||||
29 |
011.1 |
267 |
25.3 |
23.7 |
19.1 |
|
|
Trace |
1.7 |
040 |
19.0 |
|||||||||||||
|
1010.3 |
29.J |
26.2 |
243 |
|
70 |
0.0 |
7.8 |
J60 |
15.3 |
||||||||||||||
|
1006.0 |
306 |
27.1 |
24.1 |
16.4 |
52 |
41 |
0.0 |
10.4 |
|
23.1 |
|||||||||||||
|
1012.2 |
30.J |
27.3 |
25.4 |
65 |
69 |
11.3 |
209.1 |
080 |
26.6 |
||||||||||||||
CIima1oIogicaI Normal' |
1014.0 |
28.1 |
25.7 |
23.9 |
20.2 |
|
|
120.3 |
197.8 |
080 |
26.3 |
^ 1.rilo.'melon of s'iind directionmind mind speed io.• WoQlo.ri !zland ale based o.ri oulom at.'c iveatùe.• stolioin date a.'rice Auquel 1989 Traœ means rainfall less than 0.OS mm
* 1991-2020 Glimd °!°9'*6l No.'mol. einlezs oihenv.'se Apec.'ted
01 |
1009.7 |
e.6 |
26.8 |
240 |
17.2 |
|
|
0.0 |
\0.3 |
"** |
°** |
||||
OZ |
1016.3 |
216 |
251 |
22.9 |
17.8 |
|
76 |
0.0 |
4.3 |
”’ |
’*’ |
||||
03 |
1017.1 |
2R2 |
26.0 |
246 |
207 |
|
|
0.0 |
43 |
’ |
’ |
||||
04 |
1016.9 |
29.0 |
26.Z |
248 |
21.4 |
75 |
|
|
7.0 |
”’ |
’*’ |
||||
05 |
Â178 |
2R2 |
26.0 |
24.1 |
19.2 |
67 |
|
Trace |
6.8 |
’ |
’ |
||||
06 |
flI18.9 |
28.0 |
250 |
213 |
17.6 |
|
|
|
6.4 |
’ |
’ |
||||
07 |
flI19.4 |
27.0 |
23.9 |
22.3 |
13.8 |
|
31 |
Trace |
9.8 |
’ |
’ |
||||
08 |
1016.6 |
2K3 |
24.1 |
2R9 |
12.4 |
|
B2 |
0.0 |
|||||||
09 |
1014.5 |
27.9 |
25J |
234 |
18.2 |
|
|
1.9 |
2.7 |
’ |
’ |
||||
10 |
10148 |
264 |
249 |
2B.4 |
21.1 |
|
|
|
R0 |
’ |
’ |
||||
11 |
1044 |
26.3 |
24.9 |
240 |
206 |
|
|
0.0 |
|||||||
IZ |
1012.3 |
294 |
259 |
213 |
21.1 |
75 |
|
0.0 |
9.9 |
°”” |
“”* |
||||
13 |
1010.1 |
26.2 |
250 |
23.2 |
21.7 |
|
|
14.8 |
0.3 |
"** |
°** |
||||
14 |
1009.6 |
256 |
248 |
2B2 |
22.7 |
|
|
6.3 |
R0 |
’ |
’ |
||||
15 |
|
25¥ |
24J |
23.5 |
23.2 |
|
|
36.6 |
|||||||
16 |
1011.7 |
219 |
255 |
23.G |
23.2 |
|
|
33.3 |
1.5 |
°”” |
“”* |
||||
17 |
1044 |
26.2 |
24.3 |
22.9 |
D.2 |
|
|
6.1 |
3.2 |
"*” |
°”* |
||||
18 |
tg16.8 |
25.5 |
24Z |
212 |
19.1 |
|
|
|
3.2 |
’ |
’ |
||||
19 |
1018.6 |
23.2 |
201 |
184 |
17.0 |
|
97 |
7.3 |
0.0 |
’ |
’ |
||||
20 |
|
18.6 |
18.1 |
|
J7.2 |
|
|
73.8 |
R0 |
’ |
’ |
||||
21 |
1018.2 |
21.¥ |
|
17.9 |
16.7 |
|
|
5.6 |
0.4 |
"*” |
°”* |
||||
|
flI18.9 |
22.6 |
2RZ |
18.8 |
15.4 |
74 |
70 |
|
3.7 |
°”” |
“”* |
||||
23 |
4tf20.0 |
22.5 |
204 |
184 |
is.o |
|
|
Trace |
1.8 |
”’ |
”’ |
||||
2Æ |
1019.5 |
210 |
21.4 |
19.8 |
16.5 |
74 |
|
1.0 |
o.s |
- |
- |
||||
25 |
flI18.4 |
23.5 |
|
21.1 |
18.2 |
|
|
Trace |
0.6 |
"** |
°** |
||||
26 |
11119.0 |
2B.4 |
2R8 |
18.7 |
13.1 |
|
|
|
9.8 |
°”” |
“”* |
||||
27 |
10208 |
21.5 |
|
17.0 |
6.7 |
|
|
0.0 |
9.8 |
’ |
’ |
||||
28 |
1022.0 |
21.5 |
IRZ |
HQ |
|
|
|
0.0 |
9.8 |
°”” |
“”* |
||||
29 |
1020.9 |
21.2 |
18.8 |
16.6 |
2J |
|
32 |
0.0 |
9.8 |
’ |
’ |
||||
30 |
1017.7 |
22.0 |
19.0 |
is.s |
9.8 |
|
21 |
0.0 |
9.8 |
||||||
Mean/TtXaI |
flI16.4 |
253 |
23.0 |
21.3 |
16.8 |
|
71 |
|
|
||||||
24.5 |
22.Z |
2R3 |
16.7 |
|
|
39.3 |
|
070 |
Z6.6 |
”unavai/aô/e
” lnfonnation of wind direction and wind
speed for Waglan lsland are baœd on au/ornafic weafùer sfaôan dafa since August 1989
Traœ rrieans rairifall
less than mm
? 1991-2020 C//mafo/opica/ Norma/. on/ess ofherusse specifiecî
September 2024
All
Area ·
Security Fence footing
construction work ·
Footpath Construction ·
Landscape Construction ·
Irrigation System
Construction ·
Water Pressure Test for FS
and PL system ·
Landscape planting work ·
Traffic signage work · E&M Works and Mechanical Installation |
PWST ·
Water Test in Tank A ·
Waterproofing work at Roof
Slab on Tank A ·
Installation of building
services, electrical switchboards and cables · Installation of mechanical equipment, steel pipe, Pressure Test |
Administration
Building ·
External wall aluminum
features installation ·
Finishing works for dog house · Minor Installation of building services, electrical switchboards & cables, Pressure Test, T&C |
Chemical
building ·
Defect rectification · Repairing the defects inside the dangerous store |
Combined
Shaft & Pump House ·
Internal finishing, defect
rectification ·
Construction of hose reel
cabinet · T&C |
ActiDAFF ·
Installation of access
opening covers for filtered water tank ·
Carrying out finishing works
for staircase no. 3. ·
Minor Installation of
mechanical equipment, piping system · Minor Installation of building services, electrical switchboards and cables, Installation of FRP Enclosure System |
Product
Water Storage Tank Building · Minor Installation of building services, cable laying and termination, PV Panel Installation, Testing & Commissioning |
OSCG
Building ·
Protective Coating for DG
Rooms ·
Installation of Railing on
Brine Maker Tank ·
Minor Installation of
building services, cables and pipe works, T&C · Tank surface cleaning, T&C |
Reverse
Osmosis Building ·
Installation of Signage, AP
doors, sanitary fitting, sanitary ware in toilet, tiling work and water meter
cabinets · Minor Installation of building services, minor cable laying and termination, Testing & Commissioning, PV Panel Installation |
Post
Treatment Building ·
Installation of Cat Ladders
in Water Tanks ·
Placing Soil Mix at Roof ·
Curb Construction for Rescue
Opening at Water Tanks · Installation of building services, piping system, mechanical equipment and piping system, Pressure Test |
Inspection
gallery ·
Construction of roof tiling
works ·
Installation of steel
balustrade at roof ·
Installation of movement
joints ·
Construction of block works · Minor Installation of building service, T&C |
RO and
Electrical Building ·
Installation of Glass House ·
Minor Installation of
building services, electrical switchboards and cables ·
Minor Installation of
mechanical pipework and raised Floor, · PV Panel Installation, T&C Chiller plant
& Main Electrical Building · Minor Installation of building services, electrical switchboards and cables, Pressure Test, T&C Others ·
Slope works · Construction works of extended access road |
October 2024
All
Area ·
Security Fence footing
construction work ·
Footpath Construction ·
Landscape Construction ·
Irrigation System
Construction ·
Water Pressure Test for FS
and PL system ·
Landscape planting work ·
Traffic signage work · E&M Works and Mechanical Installation |
PWST ·
Water Test in Tank A ·
Waterproofing work at Roof
Slab on Tank A ·
Installation of building
services, electrical switchboards and cables · Installation of mechanical equipment, steel pipe, Pressure Test |
Administration
Building ·
External wall aluminum
features installation ·
Finishing works for dog house · Minor Installation of building services, electrical switchboards & cables, Pressure Test, T&C |
Chemical
building ·
Defect rectification · Repairing the defects inside the dangerous store |
Combined
Shaft & Pump House ·
Internal finishing, defect
rectification ·
Construction of hose reel
cabinet · T&C |
ActiDAFF ·
Installation of access
opening covers for filtered water tank ·
Carrying out finishing works
for staircase no. 3. ·
Minor Installation of
mechanical equipment, piping system · Minor Installation of building services, electrical switchboards and cables, Installation of FRP Enclosure System |
Product
Water Storage Tank Building · Minor Installation of building services, cable laying and termination, PV Panel Installation, Testing & Commissioning |
OSCG
Building ·
Protective Coating for DG
Rooms ·
Installation of Railing on
Brine Maker Tank ·
Minor Installation of
building services, cables and pipe works, T&C · Tank surface cleaning, T&C |
Reverse
Osmosis Building ·
Installation of Signage, AP
doors, sanitary fitting, sanitary ware in toilet, tiling work and water meter
cabinets · Minor Installation of building services, minor cable laying and termination, Testing & Commissioning, PV Panel Installation |
Post
Treatment Building ·
Installation of Cat Ladders
in Water Tanks ·
Placing Soil Mix at Roof ·
Curb Construction for Rescue
Opening at Water Tanks · Installation of building services, piping system, mechanical equipment and piping system, Pressure Test |
Inspection
gallery ·
Construction of roof tiling
works ·
Installation of steel
balustrade at roof ·
Installation of movement
joints ·
Construction of block works · Minor Installation of building service, T&C |
RO and
Electrical Building ·
Installation of Glass House ·
Minor Installation of
building services, electrical switchboards and cables ·
Minor Installation of
mechanical pipework and raised Floor, · PV Panel Installation, T&C Chiller plant
& Main Electrical Building · Minor Installation of building services, electrical switchboards and cables, Pressure Test, T&C Others ·
Slope works · Construction works of extended access road |
November 2024
All
Area ·
Security Fence footing
construction work ·
Footpath Construction ·
Landscape Construction ·
Irrigation System
Construction ·
Water Pressure Test for FS
and PL system ·
Landscape planting work ·
Traffic signage work · E&M Works and Mechanical Installation |
PWST ·
Water Test in Tank A ·
Waterproofing work at Roof
Slab on Tank A ·
Installation of building
services, electrical switchboards and cables · Installation of mechanical equipment, steel pipe, Pressure Test |
Administration
Building ·
External wall aluminum
features installation ·
Finishing works for dog house · Minor Installation of building services, electrical switchboards & cables, Pressure Test, T&C |
Chemical
building ·
Defect rectification · Repairing the defects inside the dangerous store |
Combined
Shaft & Pump House ·
Internal finishing, defect
rectification ·
Construction of hose reel
cabinet · T&C |
ActiDAFF ·
Installation of access
opening covers for filtered water tank ·
Carrying out finishing works
for staircase no. 3. ·
Minor Installation of
mechanical equipment, piping system · Minor Installation of building services, electrical switchboards and cables, Installation of FRP Enclosure System |
Product
Water Storage Tank Building · Minor Installation of building services, cable laying and termination, PV Panel Installation, Testing & Commissioning |
OSCG
Building ·
Protective Coating for DG
Rooms ·
Installation of Railing on
Brine Maker Tank ·
Minor Installation of
building services, cables and pipe works, T&C · Tank surface cleaning, T&C |
Reverse
Osmosis Building ·
Installation of Signage, AP
doors, sanitary fitting, sanitary ware in toilet, tiling work and water meter
cabinets · Minor Installation of building services, minor cable laying and termination, Testing & Commissioning, PV Panel Installation |
Post
Treatment Building ·
Installation of Cat Ladders
in Water Tanks ·
Placing Soil Mix at Roof ·
Curb Construction for Rescue
Opening at Water Tanks · Installation of building services, piping system, mechanical equipment and piping system, Pressure Test |
Inspection
gallery ·
Construction of roof tiling
works ·
Installation of steel
balustrade at roof ·
Installation of movement
joints ·
Construction of block works · Minor Installation of building service, T&C |
RO and
Electrical Building ·
Installation of Glass House ·
Minor Installation of
building services, electrical switchboards and cables ·
Minor Installation of
mechanical pipework and raised Floor, · PV Panel Installation, T&C Chiller plant
& Main Electrical Building · Minor Installation of building services, electrical switchboards and cables, Pressure Test, T&C Others · Construction works of extended access road |
Other Factors might affect the monitoring results |
|||
Reporting Period |
|||
Aug 2024 |
Sep 2024 |
Oct 2024 |
Nov 2024 |
N/A |
N/A |
N/A |
N/A |
Appendix E
Summary of Exceedances
Table E1 Summary of Exceedance in Sep 2024
Date of exceedance |
Monitoring Station |
Tide |
SS Level (mg/L) |
Action Level |
Limit Level |
07/09/2024 |
WSR33 |
Flood |
5.33 |
Y |
N |
WSR36 |
5.33 |
Y |
N |
||
NF1 |
5.33 |
Y |
N |
||
12/09/2024 |
WSR4 |
Ebb |
5.08 |
Y |
N |
NF1 |
5.17 |
Y |
N |
||
14/09/2024 |
WSR3 |
Ebb |
3.67 |
Y |
N |
NF2 |
4.17 |
Y |
Y |
||
17/09/2024 |
WSR3 |
Ebb |
4.83 |
Y |
N |
WSR4 |
6.17 |
Y |
Y |
||
WSR16 |
5.83 |
Y |
Y |
||
WSR36 |
4.67 |
Y |
N |
||
WSR37 |
4.67 |
Y |
N |
||
19/09/2024 |
WSR4 |
Ebb |
4.50 |
Y |
Y |
WSR33 |
5.67 |
Y |
Y |
||
WSR36 |
5.50 |
Y |
Y |
||
WSR37 |
5.17 |
Y |
Y |
||
NF1 |
6.17 |
Y |
Y |
||
NF2 |
5.67 |
Y |
Y |
||
NF3 |
5.17 |
Y |
Y |
||
21/09/2024 |
WSR3 |
Flood |
4.25 |
Y |
Y |
24/09/2024 |
WSR37 |
Flood |
4.75 |
Y |
Y |
26/09/2024 |
WSR37 |
Ebb |
4.42 |
Y |
Y |
NF3 |
4.42 |
Y |
Y |
||
28/09/2024 |
WSR2 |
Ebb |
3.42 |
Y |
N |
WSR3 |
3.83 |
Y |
Y |
||
WSR4 |
3.33 |
Y |
N |
||
WSR36 |
4.50 |
Y |
Y |
||
WSR37 |
5.50 |
Y |
Y |
||
NF1 |
4.67 |
Y |
Y |
||
NF2 |
4.50 |
Y |
Y |
||
NF3 |
5.83 |
Y |
Y |
Table E2 Summary of Exceedance in Oct 2024
Date |
Station |
Tide |
SS Level (mg/L) |
Action Level |
Limit Level |
03/10/2024 |
NF1 |
Ebb |
4.67 |
Y |
Y |
NF2 |
3.75 |
Y |
Y |
||
05/10/2024 |
WSR1 |
Flood |
6.67 |
Y |
Y |
WSR2 |
5.17 |
Y |
N |
||
WSR3 |
5.58 |
Y |
Y |
||
WSR4 |
7.83 |
Y |
Y |
||
WSR16 |
6.50 |
Y |
Y |
||
WSR33 |
7.00 |
Y |
Y |
||
WSR36 |
5.5 |
Y |
Y |
||
NF1 |
5.33 |
Y |
N |
||
10/10/2024 |
NF1 |
Ebb |
3.50 |
Y |
N |
12/10/2024 |
WSR16 |
Ebb |
4.83 |
Y |
N |
15/10/2024 |
WSR1 |
Ebb |
4.75 |
Y |
N |
WSR33 |
5.67 |
Y |
Y |
||
NF2 |
4.58 |
Y |
N |
||
17/10/2024 |
NF3 |
Ebb |
5.17 |
Y |
N |
19/10/2024 |
WSR1 |
Flood |
52.67 |
Y |
N |
WSR2 |
18.67 |
Y |
N |
||
22/10/2024 |
WSR4 |
Flood |
3.25 |
Y |
N |
WSR16 |
4.08 |
Y |
Y |
||
WSR33 |
3.50 |
Y |
Y |
||
WSR37 |
3.33 |
Y |
Y |
||
NF2 |
3.25 |
Y |
Y |
||
24/10/2024 |
WSR1 |
Ebb |
10.00 |
Y |
Y |
WSR2 |
8.67 |
Y |
N |
||
WSR3 |
10.67 |
Y |
Y |
||
WSR4 |
11.00 |
Y |
Y |
||
WSR16 |
7.75 |
Y |
N |
||
WSR33 |
6.83 |
Y |
N |
||
WSR36 |
6.08 |
Y |
N |
||
WSR37 |
8.00 |
Y |
N |
||
NF1 |
10.67 |
Y |
Y |
||
NF2 |
8.83 |
Y |
N |
||
NF3 |
7.00 |
Y |
N |
||
26/10/2024 |
WSR1 |
Ebb |
4.92 |
Y |
Y |
WSR2 |
5.17 |
Y |
Y |
||
WSR4 |
4.58 |
Y |
Y |
||
WSR16 |
5.42 |
Y |
Y |
||
WSR37 |
4.42 |
Y |
Y |
||
NF2 |
4.08 |
Y |
Y |
||
29/10/2024 |
WSR1 |
Ebb |
4.83 |
Y |
Y |
WSR2 |
4.83 |
Y |
Y |
||
WSR4 |
6.83 |
Y |
Y |
||
WSR16 |
6.00 |
Y |
Y |
||
31/10/2024 |
WSR16 |
Ebb |
4.00 |
Y |
Y |
WSR33 |
4.50 |
Y |
Y |
||
WSR36 |
3.92 |
Y |
Y |
||
NF1 |
4.17 |
Y |
Y |
Table E3 Summary of Exceedance in Nov 2024
Date of exceedance |
Monitoring Station |
Tide |
SS Level (mg/L) |
Action Level |
Limit Level |
02/11/2024 |
WSR2 |
Ebb |
4.67 |
Y |
N |
WSR4 |
5.17 |
Y |
Y |
||
WSR16 |
6.17 |
Y |
Y |
||
WSR33 |
6.17 |
Y |
Y |
||
WSR36 |
7.00 |
Y |
Y |
||
WSR37 |
7.33 |
Y |
Y |
||
NF1 |
4.83 |
Y |
Y |
||
NF2 |
4.75 |
Y |
Y |
||
05/11/2024 |
WSR2 |
Flood |
4.83 |
Y |
Y |
WSR3 |
3.58 |
Y |
Y |
||
WSR4 |
3.83 |
Y |
Y |
||
WSR16 |
4.58 |
Y |
Y |
||
WSR37 |
4.33 |
Y |
Y |
||
NF1 |
3.50 |
Y |
Y |
||
NF2 |
4.42 |
Y |
Y |
||
7/11/2024 |
WSR4 |
Ebb |
3.75 |
Y |
Y |
WSR16 |
4.08 |
Y |
Y |
||
WSR33 |
4.42 |
Y |
Y |
||
WSR36 |
4.75 |
Y |
Y |
||
WSR37 |
3.75 |
Y |
Y |
||
9/11/2024 |
WSR37 |
Ebb |
3.42 |
Y |
Y |
16/11/2024 |
WSR1 |
Ebb |
6.00 |
Y |
N |
WSR3 |
6.83 |
Y |
Y |
||
WSR16 |
6.83 |
Y |
Y |
||
WSR37 |
7.00 |
Y |
Y |
||
NF2 |
6.33 |
Y |
Y |
||
NF3 |
6.83 |
Y |
Y |
||
23/11/2024 |
NF3 |
Ebb |
5.42 |
Y |
Y |
26/11/2024 |
WSR16 |
Ebb |
3.92 |
Y |
N |
WSR36 |
3.83 |
Y |
N |
||
WSR37 |
4.58 |
Y |
Y |
||
NF2 |
3.75 |
Y |
N |
||
NF3 |
3.83 |
Y |
N |
||
28/11/2024 |
WSR37 |
Ebb |
4.08 |
Y |
N |
30/11/2024 |
WSR1 |
Ebb |
3.50 |
Y |
Y |
WSR3 |
3.42 |
Y |
Y |
||
WSR16 |
4.33 |
Y |
Y |
||
WSR33 |
3.25 |
Y |
Y |
||
WSR36 |
3.92 |
Y |
Y |
||
WSR37 |
7.17 |
Y |
Y |
||
NF1 |
4.33 |
Y |
Y |
||
NF2 |
9.00 |
Y |
Y |
||
NF3 |
4.08 |
Y |
Y |
|
|
Contract
No. 13/WSD/17
Design, Build and Operate First
Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report
Appendix F Waste Flow Table
Contract No. 13/WSD/17
Environmental Management Plan for Design, Build
and Operate First Stage of Tseung Kwan O Desalination Plant
Appendix F - Monthly Summary Waste Flow Table
Name of Department: WSD Contract No.: 13/WSD/17
Month |
Actual Quantities of Inert C&D Materials Generated Monthly |
Actual Quantities of C&D Wastes Generated Monthly |
|||||||||
Total Quantity Generated |
Hard Rock and Large Broken Concrete |
Reused in the Contract |
Reused in other Projects |
Disposed as Public Fill |
Imported Fill |
Metals |
Paper/ cardboard packaging |
Plastics (see Note 3) |
Chemical Waste |
Others, e.g. general refuse |
|
(in '000kg) |
(in '000kg) |
(in '000kg) |
(in '000kg) |
(in '000kg) |
(in '000kg) |
(in '000 kg) |
(in '000kg) |
(in '000kg) |
(in '000kg) |
(in '000kg) |
|
Jan |
4978.345 |
0.000 |
0.000 |
4667.745 |
310.600 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
77.800 |
Feb |
22561.796 |
0.000 |
0.000 |
21883.006 |
678.790 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
53.480 |
Mar |
81.140 |
0.000 |
0.000 |
0.000 |
81.140 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
52.260 |
Apr |
57.130 |
0.000 |
0.000 |
0.000 |
57.130 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
47.390 |
May |
91.370 |
0.000 |
0.000 |
0.000 |
91.370 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
77.260 |
Jun |
49.190 |
0.000 |
0.000 |
0.000 |
49.190 |
0.000 |
0.000 |
0.000 |
0.002 |
0.000 |
60.780 |
Sub-total |
27818.971 |
0.000 |
0.000 |
26550.751 |
1268.220 |
0.000 |
0.000 |
0.000 |
0.002 |
0.000 |
368.970 |
Jul |
60378.440 |
0.000 |
0.000 |
0.000 |
60378.440 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
42.820 |
Aug |
57.390 |
0.000 |
0.000 |
0.000 |
57.390 |
0.000 |
0.000 |
0.000 |
0.000 |
2.460 |
33.980 |
Sep |
834.890 |
0.000 |
0.000 |
0.000 |
834.890 |
0.000 |
0.000 |
0.000 |
0.000 |
0.805 |
27.020 |
Oct |
78.140 |
0.000 |
0.000 |
0.000 |
78.140 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
71.810 |
Nov |
237.790 |
0.000 |
0.000 |
0.000 |
237.790 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
62.300 |
Dec |
|||||||||||
Total |
89405.621 |
0.000 |
0.000 |
26550.751 |
62854.870 |
0.000 |
0.000 |
0.000 |
0.002 |
3.265 |
606.900 |
w
Notes: (1) The performance targets are given in
Section 1.69 of Specification B
1. The waste flow table shall also include
C&D materials that are specified in the Contract to be imported for use at
the Site.
2. Plastics refer to plastic
bottles/containers, plastic sheets/ foam from packaging material
第 1 頁,共 1 頁
Appendix G Complaint Log
Table G1 Statistical Summary of Environmental
Complaints
Reporting Period |
Environmental Complaint Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
|
1 September 2024 - 30 November 2024 |
0 |
2 |
N/A |
Table G2 Statistical Summary of Environmental
Summons
Reporting Period |
Environmental Summons Statistics |
||
Frequency |
Cumulative |
Details |
|
1 September 2024 - 30 November 2024 |
0 |
0 |
N/A |
Table G3 Statistical Summary of Environmental
Prosecution
Reporting Period |
Environmental Prosecution Statistics |
||
Frequency |
Cumulative |
Details |
|
1 September 2024 - 30 November 2024 |
0 |
0 |
N/A |
|
|
Contract
No. 13/WSD/17
Design, Build and Operate First
Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report
Appendix H
Event/ Action Plan for Water Quality
Exceedance
|
|
Contract
No. 13/WSD/17
Design, Build and Operate First
Stage of Tseung Kwan O Desalination Plant Quartertly
EM&A Report
Table H1 Event and Action Plan
for Water Quality Monitoring
|
|
|
|
|
|
|
|
|
Contract
No. 13/WSD/17
Design, Build and Operate First
Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report
Appendix I
Event/ Action Plan for Construction Noise
Exceedance
|
Contract
No. 13/WSD/17
Design, Build and Operate First
Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report
Table I1 Event and Action Plan
for Construction Noise Monitoring
|
|
|
|
|
|
Contract
No. 13/WSD/17
Design, Build and Operate First
Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report
Appendix J
Event/ Action Plan for Coral Monitoring
Exceedance
|
|
Contract
No. 13/WSD/17
Design, Build and Operate First
Stage of Tseung Kwan O Desalination Plant
Table J1 Event and Action Plan
for Coral Monitoring
|
|
|
|
|
|
The copyright of this document is owned by Acuity
Sustainability Consulting Limited. It may not be reproduced except with prior
written approval from the Company.
Acuity Sustainability
Consulting Limited