Revision History

Rev.

Description of Modification

Date

1.

1st Issue

19/12/2024

2.

2nd Issue

16/01/2025

3.

3rd Issue

20/01/2025

 

CONTENTS

Executive Summary 1

Basic Project Information 7

Noise 14

Water Quality 18

Waste 27

Landfill Gas Monitoring 28

Summary of Exceedance, Complaint, Notification of Summons and Prosecutions 32

EM&A Site Inspection 35

Conclusions and Recommendations 36

 

Appendix A

Master Programme

Appendix B

Overview of Desalination Plant in Tseung Kwan O

Appendix C

Summary of Implementation Status of Environmental Mitigation

Appendix D

Water Quality Monitoring Graphical Presentation

Appendix E

Summary of Exceedances

Appendix F

Waste Flow Table

Appendix G

Complaint Log

Appendix H

Event/Action Plan for Water Quality Monitoring

Appendix I

Event/Action Plan for Construction Noise Exceedance

Appendix J

Event/Action Plan for Coral Monitoring Exceedance

 

Acuity Sustainability Consulting Limited

Executive Summary

 

Introduction

 

A1. The Project, Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant (TKODP), is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) and is currently governed by a Further Environmental Permit (EP No. FEP – 01/503/2015/B) for the construction and operation of the Contract.

A2. In accordance with the Environmental Monitoring and Audit (EM&A) Manual for the Contract, EM&A works for marine water quality, noise, waste management and ecology should be carried out by Environmental Team (ET), Acuity Sustainability Consulting Limited (ASCL), during the construction phase of the Contract.

A3. According to the contractor’s information, the works of TKODP were substantially completed on 30 June 2024 and the plant commenced the operation phase on 1 July 2024. The outstanding construction works were being carried out during this reporting period.

A4. This is the 19th Quarterly EM&A Report, prepared by ASCL, for the Contract summarizing the monitoring results and audit findings of the EM&A programme at and around Tseung Kwan O Area 137 (TKO 137) during the reporting period from 1 September 2024 to 30 November

2024.

 

A5. The EM&A programme for this contract has covered environmental monitoring on construction noise level at selected NSRs and Contractor’s environmental performance auditing in the aspects of construction dust, construction noise, water quality, waste management, Landscape and Visual and Ecology.

Summary of Main Works Undertaken & Key Mitigation Measures Implemented

 

A6. Key activities carried out in this reporting period for the Project included the followings:

All Area

·           Security Fence footing construction work

·           Footpath Construction

·           Landscape Construction

·           Irrigation System Construction

·           Water Pressure Test for FS and PL system

·           Landscape planting work

·           Traffic signage work

·           E&M Works and Mechanical Installation

 

 

PWST

·           Water Test in Tank A

·           Waterproofing work at Roof Slab on Tank A

·     Installation of building services, electrical switchboards and cables Installation of mechanical equipment, steel pipe, Pressure Test

Administration Building

·           External wall aluminum features installation

·           Finishing works for dog house

·           Minor Installation of building services, electrical switchboards & cables, Pressure Test, T&C

·           Fitting out works

·           Painting Works

Chemical building

·           Defect rectification

·           Repairing the defects inside the dangerous store

ActiDAFF

·           Installation of access opening covers for filtered water tank

·           Carrying out finishing works for staircase no. 3.

·           Minor Installation of mechanical equipment, piping system

·           Minor Installation of building services, electrical switchboards and cables, Installation of FRP Enclosure System

Product Water Storage Tank Building

·           Minor Installation of building services, cable laying and termination, PV Panel Installation, Testing & Commissioning

OSCG Building

·           Protective Coating for DG Rooms

·           Installation of Railing on Brine Maker Tank

·           Minor Installation of building services, cables and pipe works, T&C

·           Tank surface cleaning, T&C

Reverse Osmosis Building

·           Installation of Signage, AP doors, sanitary fitting, sanitary ware in toilet, tiling work and water meter cabinets

·                    Minor Installation of building services, minor cable laying and termination, Testing & Commissioning, PV Panel Installation

Post Treatment Building

·           Installation of Cat Ladders in Water Tanks

·           Placing Soil Mix at Roof

·           Curb Construction for Rescue Opening at Water Tanks

 

 

·           Installation of building services, piping system, mechanical equipment and piping system, Pressure Test

Inspection gallery

·           Construction of roof tiling works

·           Installation of steel balustrade at roof

·           Installation of movement joints

·           Construction of block works

·           Minor Installation of building service, T&C

RO and Electrical Building

·           Installation of Glass House

·           Minor Installation of building services, electrical switchboards and cables

·           Minor Installation of mechanical pipework and raised Floor,

·           PV Panel Installation, T&C

Chiller plant & Main Electrical Building

·           Minor Installation of building services, electrical switchboards and cables, Pressure Test, T&C

Others

·            Slope works*

·            Construction works of extended access road

Remark: *The slope works were completed in October 2024, and there was no site activities related to the slope works conducted in November 2024.

 

A7. The major environmental impacts brought by the above construction works and slope works include:

·     Construction dust and noise generation from excavation works, construction works;

·     Waste generation from the construction activities

 

A8. The key environmental mitigation measures implemented for the Project in this reporting period associated with the above construction works include:

·     Dust suppression by regular wetting and water spraying for construction works and slope works;

·     Reduction of noise from equipment and machinery on-site and regularly inspection to machinery and plants/vehicles on-site to ensure proper functioning;

·     Sorting and storage of general refuse and construction waste;

·     Deployment of silt curtain at the inshore water outflow; and

·     Deployment protective fencing for trees.

 

Summary of Exceedance & Investigation & Follow-up

 

A9. No noise monitoring was conducted during the reporting period since there are no project- related construction activities undertaken within a radius of 300m from the monitoring locations. No exceedance of the Action Level was recorded during the reporting period.

 

A10. Referring to EM&A Manual, the general water quality monitoring should be carried out when there are marine-related construction activities undertaken. General water quality monitoring at the ten monitoring stations (CE, CF, WSR1, WSR2, WSR3, WSR4, WSR16, WSR33, WSR36 and WSR37) was ceased from 1 September 2023 due to the completion of marine-related construction works.

 

A11. The operation phase water quality was conducted from 1 September 2024 to 30 November 2024. Thirty-six (36) of the operation phase water quality monitoring results of SS obtained had exceeded the Action Level. Eighty-five (85) of the operation phase water quality monitoring results of SS obtained during the reporting period had exceeded the Limit Level. After investigation, all exceedances were concluded unrelated to the Project.

A12. The continuous monitoring of effluent quality was conducted from 1 September 2024 to 30 November 2024 in accordance with the EM&A Manual. No exceedance of the sampling was obtained during the reporting period had exceeded the Limit Level. The plant was shut down from 7 a.m. to 7 p.m. on 3 November 2024. No effluent discharge from TKODP occurred during this period. Due to the plant has suspended production, there was no effluent discharge from the TKODP during the period between 24 November 2024 and 30 November 2024.

A13. In this reporting period, 132 times of Construction Phase landfill gas monitoring were recorded at Wan Po Road (Ch0+390 – Ch0+780) and (Ch0+400 - Ch1+200). No action and limit level exceedance for methane, oxygen and carbon dioxide was recorded. The Construction Phase landfill gas monitoring was ceased from 31 October 2024.

A14. In this reporting period, Operation Phase landfill gas monitoring was conducted on 25, 26 and 27 September 2024, 9 and 10 October 2024, 14 and 15 November 2024. No exceedances of action level and limit level was observed.

A15. Operation phase monthly coral monitoring was conducted during the reporting period on 18 September 2024, 21 October 2024, 11 November 2024. There is no AL/LL exceedance during the monitoring period.

A16. Operation phase fishery monitoring for wet season 2024 was carried out on 24 and 31 August 2024. The detail of the monitoring was presented in the 4th Operation Phase Monthly EM&A Report.

 

A17. Total thirteen (13) times of Weekly site inspections of the construction works were also carried out by ET to audit the mitigation measures implementation status. Three (3) times of monthly Joint site inspections were carried out by ET and IEC.

A18. A summary of the EM&A activities in this reporting period is listed in Table I and summary of the environmental exceedance of the reporting period is tabulated in Table II.

Table I Summary Table for EM&A Activities in the Reporting Period

EM&A Activities

Sep 2024

Oct 2024

Nov 2024

Noise Monitoring

N/A

N/A

N/A

Water Quality Monitoring

3, 7, 10, 12, 14, 17, 19,

21, 24, 26 and 28

September 2024

1, 3, 5, 8, 10, 12, 15, 17,

19, 22, 24, 26, 29 and

31 October 2024

2, 5, 7, 9, 12, 16, 19, 21,

23, 26, 28 and 30

November 2024

TRC Monitoring for

Main Disinfection

 

N/A

 

N/A

 

N/A

Coral Monitoring

18 September 2024

21 October 2024

11 November 2024

Fishery Monitoring

N/A

N/A

N/A

Landfill Gas Monitoring (Construction Phase)

2, 3, 4, 5, 6, 7, 9, 10, 11,

12, 13, 14, 16, 17, 19,

20, 21, 23, 24, 25, 26,

27, 28 and 30

September 2024

1, 2, 3, 4, 5, 7, 8, 9, 10,

12, 14, 15, 16, 17, 18,

19, 21, 22, 23, 24 and

25 October 2024

 

N/A

Landfill Gas Monitoring (Operation

Phase)

 

25, 26 and 27

September 2024

 

9 and 10 October 2024

 

14 and 15 November

2024

Environmental Site Inspection

3, 10, 17 and 24

September 2024

3, 8, 15, 22 and 28

October 2024

5, 14, 18 and 26

November 2024

Continuous Monitoring of Effluent Quality

From 1 to 30

September 2024

From 1 to 31 October

2024

From 1 to 30 November

2024

Table II Summary Table for Exceedance in the Reporting Period

 

Environmental Monitoring

 

Parameter

No. of non- Project

related exceedance

Total No. of non-Project related exceedance

No. of Project

related exceedance

Total No. of Project related exceedance

AL

LL

AL

LL

Noise

Leq (30min)

N/A

N/A

N/A

N/A

N/A

N/A

Water

DO

0

0

0

0

0

0

Turbidity

0

0

0

0

0

0

 

 

Environmental Monitoring

 

Parameter

No. of non- Project related

exceedance

Total No. of non-Project related exceedance

No. of Project related

exceedance

Total No. of Project related exceedance

AL

LL

AL

LL

SS

36

85

121

0

0

0

pH

0

0

0

0

0

0

Salinity

0

0

0

0

0

0

TRC

0

0

0

0

0

0

 

Landfill Gas

O2

0

0

0

0

0

0

CH4

0

0

0

0

0

0

CO2

0

0

0

0

0

0

 

Continuous Monitoring of Effluent Quality

Temperature

0

0

0

0

0

0

pH

0

0

0

0

0

0

Salinity

0

0

0

0

0

0

Total Residual Chlorine

0

0

0

0

0

0

Suspended Solids

0

0

0

0

0

0

Iron-Soluble

0

0

0

0

0

0

Total Inorganic Nitrogen

 

0

 

0

 

0

 

0

 

0

 

0

Total Phosphorus

0

0

0

0

0

0

Sodium

Metabisulphite

0

0

0

0

0

0

Anti-scalant as Reactive Phosphorus*

 

0

 

0

 

0

 

0

 

0

 

0

Coral Monitoring

/

0

0

0

0

0

0

Fisheries Monitoring

/

N/A

N/A

N/A

N/A

N/A

N/A

*Remark: Anti-scalant water quality testing will only be conducted whenever anti-scalant dosage is adopted.

 

Complaint Handling and Prosecution

 

A19. No environmental complaint was received during the reporting period. No notifications of summons or prosecution was received during the reporting period.

Reporting Change

 

A20. There was no change to be reported that may affect the on-going EM&A programme.

 

A21. According to the contractor’s information, the TKODP commenced operation phase on 1 July 2024. The outstanding construction works were being carried out during this reporting period.

Basic Project Information

 

1.           Background

The Acciona Agua, S.A. Trading, Jardine Engineering Corporation Limited and China State Construction Engineering (Hong Kong) Limited and as AJC Joint Venture (AJCJV) is contracted to carry out the Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant (TKODP) under Contract No. 13/WSD/17 (the Contract).

Acuity Sustainability Consulting Limited (ASCL) is commissioned by AJCJV to undertake the Environmental Team (ET) services as required and/or implied, both explicitly and implicitly, in the Environmental Permit (EP), Environmental Impact Assessment Report (EIA Report) (Register No. AEIAR-192/2015) and Environmental Monitoring and Audit Manual (EM&A Manual) for the Contract; and to carry out the Environmental Monitoring and Audit (EM&A) programme in fulfillment of the EIA Report’s EM&A requirements and Contract No. 13/WSD/17 Specification requirements.

Pursuant to the Environmental Impact Assessment Ordinance (EIAO), the Director of Environmental Protection granted the Environmental Permit (No. EP-01/503/2015) and Variation of Environmental Permit (No. EP-01/503/2015/B) to Water Supplies Department (WSD); and granted the Further Environmental Permit (No. FEP-01/503/2015/B) to AJCJV for the Contract.

2.           The Reporting Scope

This is the 19th Quarterly EM&A Report for the Project which summarizes the key findings of the EM&A programme during the reporting period from 1 September 2024 to 30 November 2024.

 

3.           Project Organization

The Project Organization structure for Construction Phase is presented in Figure 1.1.

 

Figure 1.1 Project Organization Chart

 

Contact details of the key personnel are presented in Table 1.1 below:

Table 1.1 Contact Details of Key Personnel

 

Party

Position

Name

Telephone no.

Remark

Project Proponent

SE/CM2

Milton Law

2634-3573

/

Supervising Officer

(Binnies Hong Kong Limited)

Project Manager

Augustine Li

2608-7671

/

Chief Resident Engineer

David Wong

5229-8638

/

 

The Jardine Engineering Corporation, Limited, China State Construction Engineering (Hong Kong) Limited and Acciona Agua, S.A. Trading

Project Manager

Stephen Yeung

2807-4665

/

Environmental Monitoring Manager

 

Brian Kam

 

9456-9541

 

/

Operation Manager

Arnes Parra, Victor

6468-6710

/

Environmental Monitoring Manager

 

Tommy Law

 

6468-1782

 

/

Aurecon Hong Kong Limited

Environmental Team Leader

Toby Wan

9719-5422

/

Lam Environmental Services Limited

Independent Environmental Checker (IEC)

 

Serena Shek

 

6149-6683

 

/

 

4.           Summary of Construction Works

Details of the major construction activities undertaken in this reporting period are shown as below. The construction programme is presented in Appendix A.

 

Administration Building

§   External wall aluminum features installation

§   Finishing works for dog house

§   Minor Installation of building services, electrical switchboards & cables, Pressure Test, T&C

§   Installation of AP Door, Wall finishing, Ceiling, Tile, Internal partition wall, cat ladder,

wood decking;

§   Painting works and external finishing works;

§   Minor Installation of minor cables laying and termination, T&C, and electrical switchboards & cables

 

·           External wall aluminum features installation

PWST

·           Water Test in Tank A

·           Waterproofing work at Roof Slab on Tank A

·           Installation of building services, electrical switchboards and cables

·           Installation of mechanical equipment, steel pipe, Pressure Test

Chemical building

·           Defect rectification

·           Repairing the defects inside the dangerous store

Combined Shaft & Pump House

·           Internal finishing, defect rectification

·           Construction of hose reel cabinet

·           T&C

ActiDAFF

·           Installation of access opening covers for filtered water tank

·           Carrying out finishing works for staircase no. 3.

·           Minor Installation of mechanical equipment, piping system

·           Minor Installation of building services, electrical switchboards and cables, Installation of FRP Enclosure System

Product Water Storage Tank Building

·           Minor Installation of building services, cable laying and termination, PV Panel Installation, Testing & Commissioning

OSCG Building

·           Protective Coating for DG Rooms

·           Installation of Railing on Brine Maker Tank

·           Minor Installation of building services, cables and pipe works, T&C

·           Tank surface cleaning, T&C

Reverse Osmosis Building

·           Installation of Signage, AP doors, sanitary fitting, sanitary ware in toilet, tiling work and water meter cabinets

·           Minor Installation of building services, minor cable laying and termination, Testing &

Commissioning, PV Panel Installation

Post Treatment Building

·           Installation of Cat Ladders in Water Tanks

·           Placing Soil Mix at Roof

·           Curb Construction for Rescue Opening at Water Tanks

·           Installation of building services, piping system, mechanical equipment and piping system, Pressure Test

 

 

Inspection gallery

·           Interior fitting out works and painting works

·           Minor Installation of building services, Lift Installation, T&C

·           Construction of roof tiling works

·           Installation of steel balustrade at roof

·           Installation of movement joints

·           Construction of block works

·           Construction of roof tiling works

RO and Electrical Building

·         Installation of Glass House

·         Minor Installation of building services, electrical switchboards and cables

·         Minor Installation of mechanical pipework and raised Floor,

·         PV Panel Installation, T&C

Chiller plant & Main Electrical Building

·         Minor Installation of building services, electrical switchboards and cables, Pressure Test, T&C

Others

·         Slope works*

·         Construction works of extended access road

Remark: *The slope works were completed in October 2024, and there were no site activities related to the slope works conducted in November 2024.

 

1.           Summary of Environmental Status

A summary of the valid permits, licences, and /or notifications on environmental protection for this Project is presented in Table 1.2.

 

Table 1.2 Summary of the Status of Valid Environmental Licence, Notification, Permit and Documentations

 

 

Permit/ Licences

Valid Period

 

Status

 

Remark

From

To

Environmental Permit

EP – 503/2015/B

Throughout the Contract

Valid

-Issued on 3 April 2024

FEP –

01/503/2015/B

Throughout the Contract

Valid

-Issued on 3 April 2024

Notification of Construction Works under the Air Pollution Control (Construction Dust) Regulation (Form NA)

451539

Throughout the Contract

Valid

-

Billing Account for Disposal of Construction Waste

7036276

Throughout the Contract

Valid

-

Sludge (Special Waste) Disposal (Admission Ticket)

17674

12/06/2024

31/12/2024

Valid

-

17913

01/07/2024

24/12/2024

Valid

-

Chemical Waste Producer Registration

5213-839-A2987-01

Throughout the Contract

Valid

-

Wastewater Discharge Licence (Land and Marine works)

WT00035775-2020

23/08/2021

31/07/2025

Valid

-

 

WT00044188-2023

 

16/06/2023

 

30/06/2028

 

Valid

·  For Plant T&C and operation.

·  Variation of sampling point

S.P.1 is approved by the EPD

on 25 June 2024. (EPD ref.: EP640/W3/D1358/462874).

Construction Noise Permit

GW-RE0667-24

22/06/2024

20/12/2024

Valid

-

The status for all environmental aspects is presented in Table 1.3

 

Table 1.3 Summary of Status for Key Environmental Aspects under the EM&A Manual

 

 

Parameters

 

Status

Water Quality

Baseline Monitoring under EM&A Manual

The baseline water quality monitoring was conducted between 12 May 2020 and 6 June 2020

Construction Phase Impact Monitoring

Ceased from 1 September 2023

TRC Monitoring for Main

Disinfection

Completed

Operation Phase Impact Monitoring

On-going

 

Continuous Monitoring of Effluent Quality

On-going, the plant was shut down from 7 a.m. to 7

p.m. on 3 November 2024. No effluent discharge from TKODP occurred during this period.

Due to the plant has suspended production, there was no effluent discharge from the TKODP during the period between 24 November 2024 and 30

November 2024.

Noise

 

Baseline Monitoring

The baseline noise monitoring result has been

reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4

Impact Monitoring

Completed

Waste Management

Mitigation Measures in Waste Management Plan

On-going

Landfill Gas

(Construction Phase) Regular Monitoring when Construction Works are within the 250m Consultation Zone

In this reporting period, 132 times of Construction Phase landfill gas monitoring were recorded at Wan Po Road (Ch0+390 – Ch0+780) and (Ch0+400 -

Ch1+200). No exceedance of action or limit level for methane, oxygen and carbon dioxide was observed. Construction Phase landfill gas monitoring were ceased from 31 October 2024.

(Operation Phase)

Monthly Monitoring for buildings, manholes and utility pits within the Project Site and along the fresh water mains

In this reporting period, Operation Phase landfill gas monitoring was conducted on 25, 26, 27 September

2024, 9, 10 October 2024 and 14, 15 November 2024. No exceedances of action level and limit level was observed.

Ecology (Coral)

Operation phase Regular Coral Monitoring (Monthly)

Operation phase coral monitoring works was conducted on 18 September 2024, 21 October 2024

and 11 November 2024.

 

 

 

Parameters

 

Status

There is no AL/LL exceedance during the monitoring period.

Ecology (Fishery)

Operation phase Regular Fishery Monitoring (Seasonally)

Operation phase fishery monitoring for wet season 2024 was carried out on 24 and 31 August

2024.

Ecology (Landscape)

Operation phase Landscape and Visual Site Inspection

On-going

Environmental Audit

Site Inspection covering Measures of Air Quality, Noise Impact, Water Quality, Waste, Ecological Quality, Fisheries, Landscape and Visual

 

On-going

Other than the EM&A work by ET, environmental briefings, trainings and regular environmental management meetings were conducted, in order to enhance environmental awareness and closely monitor the environmental performance of the contractors.

The EM&A programme has been implemented in accordance with the recommendations presented in the approved EIA Report and the EM&A Manual. A summary of implementation status of the environmental mitigation measures for the construction phase and operation phase of the Project during the reporting period is provided in Appendix C.

 

Noise

 

1.           Monitoring Requirements

To ensure no adverse noise impact, construction noise monitoring is recommended to be carried out within 300m radius from the nearby noise sensitive receivers (NSRs), during construction phase. The NSRs selected as monitoring station are (i) NSR4 – Creative Secondary School, (ii) NSR24 – PLK Laws Foundation College, and (iii) NSR31 – School of Continuing and Professional Studies – CUHK respectively.

No impact construction noise monitoring was conducted in the reporting period due to the overly distant monitoring station from the works location, where they were farther than 1 km from the closet monitoring station NSR4 to the works location.

2.           Monitoring Parameters, Frequency and Duration

Construction noise level would be measured in terms of the A-weighted equivalent continuous sound pressure level (LAeq). Leq 30min was used as the monitoring parameter for the time period between 0700 and 1900 on normal weekdays. Table 2.1 summarizes the monitoring parameters, frequency and duration of the impact noise monitoring.

Table 2.1 Noise Monitoring Parameters, Time, Frequency and Duration

 

Time

Duration

Interval

Parameters

 

Daytime: 0700-1900

Day time: 0700-1900

(during normal weekdays)

Continuously in

Leq 5min/Leq 30min (average of 6 consecutive Leq 5min)

 

Leq 30min

L10 30min & L90 30min

 

3.           Monitoring Locations

The monitoring locations should normally be made at a point 1m from the exterior of the NSRs building façade and be at a position 1.2m above the ground. A correction of +3dB(A) should be made to the free-field measurements.

According to the environmental findings detailed in the EIA report and Baseline Monitoring Report, the designated locations for the construction noise monitoring are listed in Table 2.2 below.

Table 2.2 Noise Sensitive Receivers

 

NSR ID

Noise Sensitive Receivers

Monitoring Location

Position

NSR 4

Creative Secondary School

Roof Floor

1 m from facade

NSR 24

PLK Laws Foundation College

Pedestrian Road on Ground Floor

Free-field

NSR 31

School of Continuing and Professional Studies - CUHK

Roof Floor

1 m from facade

 

The monitoring locations should normally be made at a point 1m from the exterior of the NSRs building façade and be at a position 1.2m above the ground. A correction of +3dB(A) should be made to the free-field measurements. Three noise monitoring locations for impact monitoring at the nearby sensitive receivers are shown in Figure 2.1-2.3.

 

 

Figure 2.1 NSR4 Creative Secondary School

 

Figure 2.2 NSR24 PLK Laws Foundation College

 

 

Figure 2.3 NSR31 School of Continuing and Professional Studies - CUHK

 

4.           Action and Limit Levels

The Action/Limit Levels are in line with the criteria of Practice Note for Professional Persons (ProPECC PN 2/93) “Noise from Construction Activities – Non-statutory Controls” and Technical Memorandum on Environmental Impact Assessment Process issued by HKSAR Environmental Protection Department [“EPD”] under the Environmental Impact Assessment Ordinance, Cap 499,

S.16 are presented in Table 2.3.

Table 2.3 Action and Limit Levels for Construction Noise Monitoring per EM&A Manual

 

Time Period

Action Level

Limit Level (dB(A))

0700-1900 on

normal weekdays

When one documented complaint is received from any one of the noise sensitive receivers

§  70 dB(A) for school and

§  65 dB(A) during examination period

Notes: Limits specified in the GW-TM and IND-TM for construction and operation noise, respectively.

 

If exceedances were found during noise monitoring, the actions in accordance with the Event and Action Plan shall be carried out according to Appendix E.

 

5.           Monitoring Results and Observations

 

Referring to EM&A manual Section 4.1.2, the impact noise monitoring should be carried out when there are project-related construction activities undertaken within a radius of 300m from the monitoring stations. As no Contract-related construction activities were undertaken in the reporting period within a radius of 300m from the monitoring stations of the Project site as shown in Figure 2.4, no impact noise monitoring was conducted in the reporting period.

 

Figure 2.4 Site Layout Plan with Noise Sensitive Receivers and Desalination Plant

 

WATER QUALITY

 

In accordance with the recommendations of the EIA, water quality monitoring is required during dredging for the submarine pipelines and, during operation phase. In addition, baseline water quality monitoring was conducted prior to the commencement of marine construction activities.

The following Section provides details of the water quality monitoring to be undertaken by the Environmental Team (ET) to verify the distance of sediment and brine plume dispersion and to identify whether the potential exists for any indirect impacts to occur to ecological sensitive receivers. The water quality monitoring programme was carried out to allow any deteriorating water quality to be readily detected and timely action taken to rectify the situation.

Water quality monitoring for the Project can be divided into the following stages:

·                     Dredging activities during construction phase;

·                     Discharge of effluent from main disinfection during construction phase;

·                     Operation phase – first year upon operation; and,

·                     Continuous monitoring of effluent quality.

 

1.           Water Quality Parameters

Parameters to be measured in the marine water quality monitoring and the Continuous Monitoring of Effluent Quality are listed in Table 3.1 and Table 3.2 respectively.

1.    Operation phase Marine Water Quality Monitoring

The parameters that have been selected for measurement in situ and in the laboratory are those that were either determined in the EIA to be those with the most potential to be affected by the operation works or are a standard check on water quality conditions. Parameters measured in the monitoring are listed in Table 3.1

Table 3.1 Parameters measured in the marine water quality monitoring

Parameters

Unit

Abbreviation

In-situ measurements

Dissolved oxygen

mg/L

DO

Temperature

oC

-

pH

pH

-

Turbidity

NTU

-

Salinity

0/00

-

Total Residual Chlorine

mg/L

TRC

Total Residual Chlorine (Disinfection)

mg/L

TRC

Laboratory measurements

Suspended Solids

mg/L

SS

Iron

mg/L

Anti-scalant

mg/L

-

 

 

NOTE 1: Monitoring of Total Residual Chlorine (Disinfection) will be conducted when cleaning and sterilization of the new freshwater main is carried out.

 

2.   Continuous Monitoring of Effluent Quality

The monitoring requirement for the continuous effluent quality monitoring shall be conducted in accordance with the effluent parameters and standards stipulated by the Water Pollution Control Ordinance Discharge License (No.: WT00044188-2023) conditions.

Table 3.2 Parameters measured in the Continuous Monitoring of Effluent Quality

 

Parameters

Unit

Abbreviation

In-situ measurements

Temperature

oC

-

pH

pH

-

Salinity

0/00

-

Total Residual Chlorine

mg/L

TRC

Laboratory measurements

Suspended Solids

mg/L

SS

Iron-Soluble

mg/L

Fe

Total Inorganic Nitrogen

mg/L

-

Total Phosphorus

mg/L

-

Sodium Metabisulphite

mg/L

SMBS

Anti-scalant as Reactive Phosphorus *

mg/L

PO4 as P-

*Remark: Anti-scalant water quality testing will only be conducted whenever anti-scalant dosage is adopted.

 

In addition to the water quality parameters, other relevant data were measured and recorded in Water Quality Monitoring Logs, including the location of the sampling stations, water depth, time, weather conditions, sea conditions, tidal stage, current direction and velocity, special phenomena and work activities undertaken around the monitoring and works area that may influence the monitoring results.

2.           Monitoring Locations

 

1.  Operation phase Marine Water Quality Monitoring

The water quality monitoring locations are detailed in Table 3.2 and shown in Figure 3.1 below.

Table 3.3 Location of Water Quality Monitoring Station

 

Station

Easting

Northing

Description

CE

843550

815243

Upstream control station at ebb tide

CF

846843

810193

Upstream control station at flood tide

WSR1

846864

812014

Ecological sensitive receiver at Tung Lung Chau

WSR2

847645

812993

Fisheries sensitive receiver at Tung Lung Chau

WSR3

848023

813262

Ecological sensitive receiver at Tung Lung Chau

WSR4

847886

814154

Ecological sensitive receiver at Tai Miu Wan

 

 

WSR16

845039

815287

Ecological sensitive receiver at Fat Tong Chau

WSR33

847159

814488

Ecological sensitive receiver at Tai Miu Wan

WSR36

846878

814081

Ecological sensitive receiver at Kwun Tsai

WSR37

846655

813810

Ecological sensitive receiver at Tit Cham Chau

NF1

846542

813614

Edge of mixing zone, ~ 200m west of outfall diffuser

NF2

846942

813614

Edge of mixing zone, ~ 200m east of outfall diffuser

NF3

846742

813414

Edge of mixing zone, ~ 200m south of outfall diffuser

 

Figure 3.1 Water Quality Monitoring Locations under EM&A Manual

 

2.   Continuous Monitoring of Effluent Quality

In accordance with the discharge license, the Continuous Monitoring shall be sampling at Brine Outfall Shaft.

 

 

Figure 3.2 Continuous Monitoring locations

 

3.           Monitoring Equipment, Methodology and QA/QC Procedures

The monitoring methodology, equipment used, and QA/QC procedures could be referred to Section 3.1.2 -3.1.4, 3.1.6-3.1.7 and 3.2 of the Monthly EM&A Report.

4.           Action and Limit levels

The Action and Limit Levels have been set based on the derivation criteria specified in the EM&A Manual. The Action/Limit Levels have been derived and are presented in Table 3.4 and Table 3.5.

1.  Operation phase Marine Water Quality Monitoring

Table 3.4 Derived Action and Limit Levels for Water Quality

 

Parameters

Action

Limit

Operation Phase Monitoring

DO in mg/L

Surface and Middle

Surface and Middle

7.30 mg L-1

4 mg L-1

Bottom

Bottom

7.31 mg L-1

2 mg L-1

Tung Lung Chau Fish Culture Zone

Tung Lung Chau Fish Culture Zone

5.1 mgL-1 or level at control station

5.0 mgL-1 or level at control station

(Whichever the lower)

(Whichever the lower)

 

Parameters

Action

Limit

Operation Phase Monitoring

SS in mg/L (Depth-

averaged)

5.00 mg L-1 or 20% exceedance of value at any impact station compared with

corresponding data from control station

6.00 mg L-1 or 30% exceedance of value at any impact station compared with

corresponding data from control station

Turbidity in NTU (Depth-

averaged)

2.41 NTU or 20% exceedance of value at any impact station compared with

corresponding data from control station

2.84 NTU or 30% exceedance of value at any impact station compared with

corresponding data from control station

Salinity in PSU

(Depth- averaged)

34.28 PSU or 9% exceedance of value at

any impact station compared with corresponding data from control station

34.60 PSU or 10% exceedance of value

at any impact station compared with corresponding data from control station

Iron in mg/L

(Depth- averaged)

0.3 mg/L

0.3 mg/L

Total residual

chlorine in mg/L

0.01 mg/L

0.01 mg/L

Total residual

chlorine in mg/L (Disinfection)

0.1 mg/L

0.1 mg/L

Notes:

1.          "Depth-averaged" is calculated by taking the arithmetic means of reading of all three depths.

2.            For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

3.              For Turbidity, SS, iron and Salinity, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

 

2.   Continuous Monitoring of Effluent Quality

Table 3.5 Derived Limit Levels for Water Quality

Parameters

Limit

Continuous Monitoring of Effluent Quality

Flow Rate in m3/day

216841

Temperature in °C

Maximum 40

Salinity

71347

SS in mg/L

13

pH

6-9

Iron in mg/L

0.6

Total residual chlorine in mg/L

0.1

Total Inorganic Nitrogen in mg/L

2

Total Phosphorous in mg/L

1

 

Parameters

Limit

Continuous Monitoring of Effluent Quality

Sodium Metabisulphite in mg/L

0.5

Anti scalant in mg/L*

2.2

*Remark:

1. Anti-scalant water quality testing will only be conducted whenever anti-scalant dosage is adopted.

 

5.           Monitoring Results and Observations

Construction Phase

Referring to EM&A Manual, the general water quality monitoring should be carried out when there are marine-related construction activities undertaken. General water quality monitoring at the ten monitoring stations (CE, CF, WSR1, WSR2, WSR3, WSR4, WSR16, WSR33, WSR36 and WSR37) was ceased from 1 September 2023 due to the completion of marine-related construction works.

Operation Phase

The first-year operation phase marine water quality monitoring was carried out during the reporting period, the monitoring was conducted at the thirteen monitoring stations (CE, CF, WSR1, WSR2, WSR3, WSR4, WSR16, WSR33, WSR36, WSR37, NF1, NF2 and NF3). The Action and

Limit Level would be referred to the approved EM&A Manual Table 5.4 First-year Operation Phase Marine Water Monitoring.

The operation phase marine water quality monitoring was conducted on 3, 7, 10, 12, 14, 17, 19,

21, 24, 26 and 28 September 2024 , 1, 3, 5, 8, 10, 12, 15, 17, 19, 22, 24, 26, 29 and 31 October 2024

and 2, 5, 7, 9, 12, 16, 19, 21, 23, 26, 28 and 30 November 2024. The result of the reporting quarterly is presented in Table 3.6.

Thirty-six (36) of the operation phase marine water quality monitoring results of SS obtained had exceeded the Action Level. Eighty-five (85) of the operation phase water quality monitoring results of SS obtained during the reporting period had exceeded the Limit Level.

Investigation on the reason of exceedance has been carried out, where the exceedances of SS were concluded to be unrelated to the Contract as detailed in the Incident Reports on Action Level or Limit Level. Summary of the exceedance is presented in Appendix E.

Continuous Monitoring of Effluent Quality

Continuous Monitoring of Effluent Quality was conducted sampling point in the reporting period. No exceedance of the sampling was obtained during the reporting period had exceeded the Limit Level. The detailed results are summarized in Table 3.7.

The plant was shut down from 7 a.m. to 7 p.m. on 3 November 2024. No effluent discharge from TKODP occurred during this period.

Due to the plant has suspended production, there was no effluent discharge from the TKODP during the period between 24 November 2024 and 30 November 2024.

 

Table 3.6 Summary of Operation Phase Water Quality Monitoring Results

 

 

Location

Parameter

 

Salinity (ppt)

Dissolved Oxygen (mg/L)

 

pH

 

Turbidity (NTU)

 

Suspended Solids (mg/L)

 

Temp. (oC)

 

TRC (mg/L)

 

Iron (mg/L)

Surface & Middle

Bottom

Sep-

2024

Oct-

2024

Nov-

2024

Sep-

2024

Oct-

2024

Nov-

2024

Sep-

2024

Oct-

2024

Nov-

2024

Sep-

2024

Oct-

2024

Nov-

2024

Sep-

2024

Oct-

2024

Nov-

2024

Sep-

2024

Oct-

2024

Nov-

2024

Sep-

2024

Oct-

2024

Nov-

2024

Sep-

2024

Oct-

2024

Nov-

2024

Sep-

2024

Oct-

2024

Nov-

2024

 

CE

Avg.

32.49

32.40

32.06

8.71

8.90

8.48

8.73

8.89

8.51

8.14

8.19

8.18

2.52

2.44

2.41

3.41

4.60

3.29

28.84

28.64

26.55

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Min.

31.63

30.94

31.27

8.12

7.90

8.05

8.04

7.89

8.05

8.03

8.08

8.00

1.98

2.01

2.05

2.50

2.50

2.50

27.94

27.78

25.10

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Max..

33.66

33.12

33.14

9.54

9.64

8.98

9.58

9.67

8.96

8.27

8.31

8.36

2.85

2.79

2.69

7.00

37.00

6.00

29.85

29.38

27.57

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

 

CF

Avg.

32.19

32.55

32.14

8.62

8.83

8.69

8.60

8.82

8.69

8.27

8.24

8.14

2.40

2.28

2.32

3.55

7.68

3.76

28.94

28.65

26.41

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Min.

31.20

31.71

31.52

7.91

7.98

8.12

7.92

7.80

8.04

8.12

8.09

7.94

2.13

1.86

2.06

2.00

2.50

2.50

28.02

27.81

25.06

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Max..

33.55

33.56

33.23

9.57

9.84

9.21

9.51

9.74

9.26

8.40

8.40

8.41

2.96

2.68

2.66

9.00

86.00

8.00

29.98

29.38

27.59

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

 

WSR1

Avg.

31.97

32.21

32.07

8.59

8.67

8.48

8.60

8.67

8.50

8.19

8.24

8.17

1.71

1.83

1.77

3.30

7.90

3.44

28.91

28.60

26.55

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Min.

31.33

31.41

31.40

7.81

7.70

7.96

7.80

7.72

7.95

8.08

8.05

7.98

1.32

1.30

1.34

2.50

2.50

2.50

28.14

27.73

25.25

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Max..

33.09

33.04

32.42

9.08

9.36

9.22

9.13

9.40

9.33

8.31

8.40

8.32

2.10

2.22

2.18

6.00

65.00

9.00

29.69

29.26

27.81

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

 

WSR2

Avg.

32.34

32.52

32.07

8.66

8.87

8.71

8.66

8.85

8.73

8.20

8.21

8.14

1.84

1.65

1.73

3.28

5.01

3.38

28.92

28.59

26.49

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Min.

31.54

31.59

31.05

7.52

7.99

7.91

7.53

7.95

7.91

8.05

8.04

8.00

1.52

1.34

1.40

2.50

2.50

2.50

28.12

27.69

25.00

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Max..

33.17

33.59

33.30

9.66

9.64

9.15

9.72

9.65

9.25

8.32

8.33

8.30

2.17

2.22

2.20

6.00

63.00

10.00

29.74

29.30

27.60

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

 

WSR3

Avg.

32.34

32.52

32.13

8.75

8.91

8.68

8.74

8.90

8.69

8.23

8.22

8.16

1.77

1.68

1.76

3.44

4.10

3.62

28.82

28.59

26.47

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Min.

30.93

31.52

31.29

7.54

8.16

8.21

7.58

8.13

8.28

7.98

8.03

7.98

1.45

1.22

1.42

2.50

2.50

2.50

27.85

27.91

24.94

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Max..

33.59

33.05

32.90

9.46

9.86

9.24

9.57

9.86

9.25

8.39

8.39

8.36

2.21

2.08

2.09

8.00

12.00

12.00

29.80

29.22

27.80

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

 

WSR4

Avg.

32.24

32.52

32.07

8.61

8.96

8.52

8.61

8.99

8.52

8.20

8.21

8.15

1.68

1.81

1.86

3.63

4.40

3.53

28.91

28.64

26.56

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Min.

31.27

31.56

31.00

8.08

7.75

8.02

8.15

7.78

8.00

8.10

8.00

7.91

1.34

1.31

1.47

2.50

2.00

2.50

27.88

27.93

25.15

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Max..

33.62

33.33

32.84

9.27

9.60

9.27

9.36

9.61

9.19

8.28

8.41

8.33

1.96

2.16

2.21

10.00

13.00

7.00

29.74

29.33

27.71

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

 

WSR16

Avg.

32.24

32.35

32.24

8.56

8.76

8.62

8.55

8.75

8.63

8.21

8.20

8.18

1.76

1.76

1.67

3.48

4.29

4.07

28.93

28.58

26.51

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Min.

31.21

31.24

31.20

7.68

8.14

8.09

7.73

8.12

8.05

8.06

8.06

7.94

1.34

1.44

1.37

2.50

2.50

2.50

27.88

27.72

25.19

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Max..

32.97

33.13

33.07

9.52

9.49

9.05

9.39

9.55

9.11

8.40

8.34

8.33

2.10

2.14

2.10

7.00

11.00

9.00

29.83

29.19

27.44

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

 

WSR33

Avg.

32.29

32.42

32.10

8.66

8.59

8.47

8.66

8.59

8.49

8.26

8.21

8.20

1.72

1.74

1.77

3.52

4.03

3.53

28.93

28.66

26.55

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Min.

31.64

30.89

31.27

7.77

7.82

7.83

7.80

7.89

7.97

8.12

8.03

7.92

1.33

1.32

1.23

2.50

2.50

2.50

27.83

28.01

25.14

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Max..

32.90

33.56

33.09

9.47

9.16

9.28

9.49

9.15

9.38

8.37

8.34

8.36

2.13

2.19

2.20

8.00

14.00

8.00

30.05

29.32

27.88

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

 

WSR36

Avg.

32.27

32.34

31.80

8.44

8.93

8.66

8.45

8.94

8.68

8.22

8.21

8.16

1.82

1.77

1.78

3.64

3.83

3.69

28.97

28.59

26.46

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Min.

30.94

31.31

31.17

7.73

7.73

8.14

7.73

7.75

8.21

8.05

8.09

7.97

1.54

1.34

1.46

2.50

2.50

2.50

28.05

27.82

24.84

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Max..

33.51

33.14

32.54

9.29

9.68

9.14

9.32

9.66

9.13

8.35

8.35

8.32

2.19

2.15

2.13

7.00

9.00

11.00

29.87

29.20

27.36

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

 

WSR37

Avg.

31.88

32.43

32.00

8.56

8.83

8.52

8.59

8.84

8.52

8.22

8.23

8.20

1.77

1.78

1.76

4.25

3.85

4.46

28.93

28.62

26.55

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Min.

30.72

31.23

31.04

8.08

7.90

7.75

8.10

7.93

7.72

8.07

8.12

8.04

1.29

1.37

1.48

2.50

2.00

2.50

27.77

28.05

25.13

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Max..

33.21

33.49

32.79

9.42

9.41

9.10

9.47

9.49

9.18

8.34

8.40

8.32

2.12

2.14

2.21

8.00

11.00

13.00

30.12

29.30

27.88

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

 

 

Location

Parameter

 

Salinity (ppt)

Dissolved Oxygen (mg/L)

 

pH

 

Turbidity (NTU)

 

Suspended Solids (mg/L)

 

Temp. (oC)

 

TRC (mg/L)

 

Iron (mg/L)

Surface & Middle

Bottom

Sep-

2024

Oct-

2024

Nov-

2024

Sep-

2024

Oct-

2024

Nov-

2024

Sep-

2024

Oct-

2024

Nov-

2024

Sep-

2024

Oct-

2024

Nov-

2024

Sep-

2024

Oct-

2024

Nov-

2024

Sep-

2024

Oct-

2024

Nov-

2024

Sep-

2024

Oct-

2024

Nov-

2024

Sep-

2024

Oct-

2024

Nov-

2024

Sep-

2024

Oct-

2024

Nov-

2024

 

NF1

Avg.

32.37

32.35

32.27

8.70

8.76

8.67

8.69

8.75

8.68

8.21

8.21

8.16

1.81

1.77

1.74

3.79

4.19

3.47

28.88

28.64

26.51

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Min.

31.55

31.55

31.59

7.87

8.27

8.11

7.81

8.22

8.11

8.02

8.11

7.96

1.58

1.33

1.39

2.50

2.50

2.50

27.99

27.76

25.04

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Max..

33.04

33.36

33.24

9.54

9.28

9.21

9.42

9.22

9.14

8.32

8.39

8.30

2.08

2.18

2.04

8.00

13.00

9.00

29.70

29.38

27.87

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

 

NF2

Avg.

32.26

32.31

32.05

8.53

8.76

8.49

8.54

8.75

8.48

8.19

8.21

8.13

1.73

1.71

1.71

3.77

4.00

4.14

28.96

28.61

26.49

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Min.

31.51

31.34

31.38

7.89

8.19

7.99

7.84

8.19

8.02

8.01

8.05

7.99

1.39

1.25

1.43

2.50

2.00

2.50

27.94

27.75

25.14

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Max..

32.90

33.27

32.84

9.14

9.35

9.24

9.19

9.33

9.11

8.33

8.39

8.28

2.09

2.20

2.14

7.00

11.00

15.00

29.98

29.20

27.57

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

 

NF3

Avg.

32.18

32.25

32.11

8.79

8.75

8.72

8.82

8.73

8.70

8.21

8.24

8.15

1.66

1.83

1.67

3.83

3.64

3.78

28.93

28.60

26.50

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Min.

31.14

31.45

31.25

7.97

7.81

8.05

7.98

7.78

8.08

8.04

8.07

7.98

1.41

1.47

1.42

2.50

2.00

2.50

28.04

27.81

24.99

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

Max..

32.92

33.08

32.83

9.21

9.61

9.33

9.31

9.55

9.33

8.34

8.36

8.25

1.96

2.22

2.22

8.00

11.00

10.00

29.77

29.30

27.74

<0.01

<0.01

<0.01

<0.1

<0.1

<0.1

 

Table 3.7 Summary of Continuous Effluent Monitoring Results

 

 

Salinity (ppt)

 

pH

 

Temp (°C)

Total Residual Chlorine (mg/L)

 

Suspended Solids (mg/L)

Total Inorganic Nitrogen (mg/L)

Total Phosphorus (mg/L)

*Sodium Metabisulphite (mg/L)

 

Iron (mg/L)

 

Sep-2024

Avg.

54.88

7.68

29.67

0.03

3.00

0.54

0.01

<2

<0.1

Min.

51.05

7.27

24.50

0.00

<2

0.08

<0.01

<2

<0.1

Max.

58.25

7.85

31.06

0.20

2

0.49

0.02

<2

<0.1

 

Oct-2024

Avg.

55.19

7.55

27.77

0.04

3.00

0.54

0.01

<2

<0.1

Min.

51.05

7.14

24.50

0.01

<2

0.08

<0.01

<2

<0.1

Max.

58.26

7.86

31.15

0.07

2

0.49

0.02

<2

<0.1

 

Nov-2024

Avg.

53.82

7.32

26.01

0.04

2.00

0.21

0.01

<2

<0.1

Min.

49.80

6.68

24.01

0.01

<2

0.02

<0.01

<2

<0.1

Max.

58.57

8.00

28.60

0.09

2

0.42

0.02

<2

<0.1

* Remark: As confirmed by various laboratories in Hong Kong, the lowest detection limit for Sodium Metabisulphite is <2 mg/L. Due to the limitation of the laboratory, the lowest result for Sodium Metabisulphite will only be shown as < 2 mg/L.

 

 

Waste

 

The waste generated from this Project includes inert construction and demolition (C&D) materials, and non-inert C&D materials. Non-inert C&D materials are made up of general refuse, vegetative wastes, and recyclable wastes such as plastics and paper/cardboard packaging waste. Steel materials generated from the project are also grouped into non-inert C&D materials as the materials were not disposed of with other inert C&D materials. With reference to relevant handling records and trip tickets of this Project, the quantities of different types of waste generated in the reporting period are summarized in Table 4.1. Details of cumulative waste management data are presented as a waste flow table in Appendix F.

Table 4.1 Quantities of Waste Generated from the Project during reporting period

 

 

Reporting Months

Actual Quantities of Inert C&D Materials Generated Monthly

Actual Quantities of C&D Wastes Generated Monthly

 

Total Quantity Generated

 

Hard Rock and Large Broken Concrete

 

Reused in the Contract

 

Reused in other Projects

 

Disposed as Public Fill

 

Imported Fill

 

Metals

 

Paper / cardboard packaging

 

Plastics (1)

 

Chemical Waste

 

Others, e.g. general refuse

(in ,000kg)

(in ,000kg)

(in ,000kg)

(in ,000kg)

(in ,000kg)

(in ,000kg)

(in ,000kg)

(in ,000kg)

(in ,000kg)

(in ,000kg)

(in ,000kg)

Sep 2024

834.890

0.000

0.000

0.000

834.890

0.000

0.000

0.000

0.000

0.805

27.020

Oct 2024

78.140

0.000

0.000

0.000

78.140

0.000

0.000

0.000

0.000

0.000

71.810

Nov 2024

237.790

0.000

0.000

0.000

237.790

0.000

0.000

0.000

0.000

0.000

62.300

Notes: (1) Plastics refer to plastic bottles / containers, plastic sheets / foam from packaging material

LANDFILL GAS MONITORING

 

1.           Monitoring Requirement

In accordance with Section 11 of the EM&A Manual, monitoring of landfill gas is required for construction works within the 250m Consultation Zone. Part of the desalination plant and the indicative area of natural slope mitigation works fall within the SENT Landfill Extension Consultation Zone; and part of the 1,200 mm diameter fresh water mains along Wan Po Road falls within the SENT Landfill and SENT Landfill Extension Consultation Zones, TKO Stage II/III Restored Landfill and TKO Stage I Restored Landfill Consultation Zones.

Routine monitoring is required at buildings within the Project Site and consultation zones. The monitoring frequency will be monthly for the first year of operation.

For the manholes and utility pits within the Project Site and along the fresh water mains, each manhole/ utility pit should be monitored with two measurements (at mid depth and base). Each measurement should be monitored for a minimum of 10 minutes. A steady reading and peak reading should be recorded at each manhole/ utility pit and for each measurement.

Monitoring of oxygen, methane, carbon dioxide and barometric pressure would be performed monthly during the operation phase.

 

2.           Monitoring Location

Monitoring of oxygen, methane, carbon dioxide and barometric pressure was performed for excavations at 1m depth or more within the consultation Zone.

During construction of works within the consultation zones, excavations of 1m depth or more was monitored:

§   At the ground surface before excavation commences;

§   Immediately before any worker enters the excavation;

§   At the beginning of each working day for the entire period the excavation remains open; and

§   Periodically through the working day whilst workers are in the excavation.

 

For excavations between 300mm and 1m deep, measurements should be carried out:

 

§   Directly after the excavation has been completed; and

§   Periodically whilst the excavation remains open.

 

3.           Monitoring Parameters

LFG monitoring was carried out to identify any migration between the landfill and the Project and to ensure the safety of the construction, operation and maintenance personnel working on- site, visitors and any other person within the Project area.

 

The following parameters were monitored:

§     Methane.

§     Oxygen.

§     Carbon Dioxide.

§     Barometric Pressure.

 

4.           Monitoring Location

The area required to be monitored for landfill gas in the reporting period is shown in Figure 5.1,

5.2 and 5.3.

Figure 5.1 Overview of the SENT Extension Consultation Zone and the Project Site Area

 

29

The copyright of this document is owned by Acuity Sustainability Consulting Limited. It may not be reproduced except with prior written approval from the Company.

 

 

Figure 5.2 Landfill Gas Monitoring Location for Building

 

 

Figure 5.3 Landfill Gas Monitoring Location for Manholes/Pits

 

5.              Action and Limit Level

Action and Limit Level are provided in Table 5.1.

Table 5.1 Action and Limit Level for Landfill Gas Monitoring

Parameters

Action Level

Limit Level

Oxygen (O2)

<19% O2

<19% O2

Methane (CH4)

>10% LEL

>20% LEL

Carbon Dioxide (CO2)

>0.5% CO2

>1.5% CO2

 

6.                Monitoring Equipment

The monitoring equipment used during the construction phase in this reporting period is detailed in Section 5.8 of the Construction Phase Monthly EM&A Report and the monitoring equipment used during the operation phase in the reporting period is detailed in Section 4.7 – 4.8 of the Operation Phase Monthly EM&A Report.

 

7.              Monitoring Results and Observations

In this reporting period, 132 times of Construction Phase landfill gas monitoring were recorded at Wan Po Road (Ch0+390 – Ch0+780) and (Ch0+400 - Ch1+200). No exceedance of action and limit levels for methane, oxygen and carbon dioxide was observed. Monitoring was conducted during excavations at 1m depth or more within the consultation zone and whenever workers entered the excavation on the day. The landfill gas monitoring was ceased from 31 October 2024.

In this reporting period, Operation Phase landfill gas monitoring was conducted on 25, 26 and 27 September 2024, 9 and 10 October 2024 and 14 and 15 November 2024. No exceedances of action level and limit level was observed.

 

SUMMARY OF EXCEEDANCE, COMPLAINT, NOTIFICATION OF SUMMONS AND

Prosecutions

 

The Environmental Complaint Handling Procedure is shown in below Figure 6.1:

 

 

Figure 6.1 Environmental Complaint Handling Procedures

 

No noise monitoring was conducted during the reporting period since there are no Contract- related construction activities undertaken within a radius of 300m from the monitoring locations. No Action Level exceedance was recorded during the reporting period.

Referring to EM&A Manual, the general water quality monitoring should be carried out when there are marine-related construction activities undertaken. General water quality monitoring at the ten monitoring stations (CE, CF, WSR1, WSR2, WSR3, WSR4, WSR16, WSR33, WSR36 and WSR37) was ceased from 1 September 2023 due to the completion of marine-related construction works.

Thirty-six (36) of the operation phase water quality monitoring results of SS obtained had exceeded the Action Level. Eighty-five (85) of the operation phase water quality monitoring results of SS obtained during the reporting period had exceeded the Limit Level. After investigation, all exceedances were considered non-project related.

In this reporting period, 132 times of Construction Phase landfill gas monitoring were recorded at Wan Po Road (Ch0+390 – Ch0+780) and (Ch0+400 - Ch1+200). No exceedance of action and limit levels for methane, oxygen and carbon dioxide was observed. Monitoring was conducted during excavations at 1m depth or more within the consultation zone and whenever workers entered the excavation on the day. The landfill gas monitoring was ceased from 31 October 2024.

In this reporting period, Operation Phase landfill gas monitoring was conducted on 25, 26 and 27 September 2024, 9 and 10 October 2024 and 14, 15 November 2024. No exceedances of action level and limit level was observed.

Operation phase monthly coral monitoring was conducted during the reporting period on 18 September 2024, 21 October 2024 and 11 November 2024. No sediment, bleaching or increased mortality in the general condition of all other tagged coral colonies were observed during the monthly operation phase monitoring period. No deterioration of the coral community was observed in the ecological monitoring results when compared with the baseline ecological monitoring results. There is no AL/LL exceedance during the monitoring period.

Operation phase fishery monitoring for wet season 2024 was carried out on 24 and 31 August 2024. The detail of the monitoring was presented in the 4th Operation Phase Monthly EM&A Report.

Continuous Monitoring of Effluent Quality was conducted sampling point from 1 September 2024 to 30 November 2024. No exceedance of the sampling was obtained during the reporting period had exceeded the Limit Level.

The plant was shut down from 7 a.m. to 7 p.m. on 3 November 2024. No effluent discharge from TKODP occurred during this period.

Due to the plant has suspended production, there was no effluent discharge from the TKODP during the period between 24 November 2024 and 30 November 2024.

ET will keep closely monitoring the performance of Contractor, implementation of water quality mitigation measure and other contamination issue around the Project site, to ensure the EM&A requirement is properly implemented.

No environmental complaint was received in the reporting period. No notification of summons and prosecution was received in the reporting period.

Statistics on complaints and regulatory compliance are summarized in Appendix G.

 

 

EM&A SITE INSPECTION

 

Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract.

No trespass by the Contractor outside the works area of the Project and Clear Water Bay Country Park, and no damage to the vegetation and rocky shore outside the Project area was observed in the reporting period. All plants were observed to be in satisfactory condition in the reporting period.

ET weekly site inspections were carried out by ET on 3, 10, 17 and 24 September 2024, 3, 8, 15,

22 and 28 October 2024 and 5, 14, 18 and 26 November 2024.

Joint site inspections were also carried out by ET and IEC on 24 September 2024, 28 October 2024 and 26 November 2024.

According to the EIA Study Report, Environmental Permit, contract documents and EM&A Manual, the mitigation measures detailed in the documents should be implemented as much as practical during the reporting period. An updated Implementation Status of Environmental Mitigation Measures (EMIS) is provided in Appendix C.

 

 

CONCLUSIONS AND RECOMMENDATIONS

 

This is the 19th Quarterly EM&A Report for the Project which summarizes the key findings of the EM&A programme during the reporting period from 1 September 2024 to 30 November 2024, in accordance with the EM&A Manual and the requirement under FEP-01/503/2015/B.

According to the contractor’s information, the works of TKODP were substantially completed on 30 June 2024 and the plant commenced the operation phase on 1 July 2024. The outstanding construction works were being carried out during this reporting period.

No noise monitoring was conducted in the reporting period due to the over distant monitoring station from the works location.

Referring to EM&A Manual, the general water quality monitoring should be carried out when there are marine-related construction activities undertaken. General water quality monitoring at the ten monitoring stations (CE, CF, WSR1, WSR2, WSR3, WSR4, WSR16, WSR33, WSR36 and WSR37) was ceased from 1 September 2023 due to the completion of marine-related construction works.

Thirty-six (36) of the operation phase water quality monitoring results of SS obtained had exceeded the Action Level. Eighty-five (85) of the operation phase water quality monitoring results of SS obtained during the reporting period had exceeded the Limit Level. After investigation, all exceedances were considered non-project related.

Continuous Monitoring of Effluent Quality was conducted sampling point 1 September 2024 to 30 November 2024. No exceedance of the sampling was obtained during the reporting period had exceeded the Limit Level.

The plant was shut down from 7 a.m. to 7 p.m. on 3 November 2024. No effluent discharge from TKODP occurred during this period.

Due to the plant has suspended production, there was no effluent discharge from the TKODP during the period between 24 November 2024 and 30 November 2024.

In this reporting period, 132 times of Construction Phase landfill gas monitoring were recorded at Wan Po Road (Ch0+390 – Ch0+780) and (Ch0+400 - Ch1+200). No exceedance of action and limit levels for methane, oxygen and carbon dioxide was observed. Monitoring was conducted during excavations at 1m depth or more within the consultation zone and whenever workers entered the excavation on the day. The landfill gas monitoring was ceased from 31 October 2024.

In this reporting period, Operation Phase landfill gas monitoring was conducted on 25, 26, 27 September 2024, 9, 10 October 2024 and 14, 15 November 2024. No exceedances of action level and limit level was observed.

Operation phase monthly coral monitoring was conducted during the reporting period on 18 September 2024, 21 October 2024 and 11 November 2024. No sediment, bleaching or increased mortality in the general condition of all other tagged coral colonies were observed during the monthly operation phase monitoring period. No deterioration of the coral community was 36

The copyright of this document is owned by Acuity Sustainability Consulting Limited. It may not be reproduced except with prior written approval from the Company.

observed in the ecological monitoring results when compared with the baseline ecological monitoring results. There is no AL/LL exceedance during the monitoring period.

Operation phase fishery monitoring for wet season 2024 was carried out on 24 and 31 August 2024. The detail of the monitoring was presented in the 4th Operation Phase Monthly EM&A Report.

Weekly environmental site inspection was conducted during the reporting period. Minor deficiency was observed during site inspection and was rectified. The environmental performance of the project was therefore considered satisfactory.

According to the environmental site inspections performed in the reporting period, the Contractor is reminded to pay attention on maintaining proper materials storage.

Two (2) environmental complaints were received of Contract since commencement of the Contract. No notification of summons or prosecution was received of the Contract since commencement of the Contract quarter.

The ET will keep track on the construction and operation works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.

 

 

 

Contract No. 13/WSD/17

Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report

 

Appendix A

 

Master Programme

13/WSD/17 Design, Build and Operate Stage 1 of Tesung Kwan O Desalination Plant 31 Jul 24

Activity ID Activity Name Baseline

Baseline Start Baseline Finish Remaining

Actual / Planned

Actual / Planned

Actual %

Variance

Total

2020 2021 2022 2023 2024

 

Project Programme Updated as at 31 Jul 2024

Project Programme Updated as at 31 Jul 2024

Key Dates

Key Dates

Commencement and Completion Date

Commencement and Completion Date

Duration

Duration

Start

Finish

Complete

Finish Date

Float N D J F M A M J J A S O N D J F M A M J J A S O N D J

F M A M J

J A S O N D J

F M A M J J A S O N D J F M A M J J A S O N D

KD0000100

Letter of Acceptance

0 15-Nov-19

0 15-Nov-19 A

100% 0

Letter of Acceptance

 

KD0000110

Commencement of the Works

0 30-Dec-19

0 30-Dec-19 A

100% 0

Commencement of the Works

 

KD0000120

Original Completion of the Works (1170 Days)

0 13-Mar-23 0

1.   Mar-23 A

100% 0

Original Completion of the Works (1170 Days)

 

KD0000130

Revised Completion of the Works (324 Days EOT Granted) 0

0 14-Mar-23 A

31-Jan-24 A

100%

Revised Completion of the Work

 

KD0000510

Planned Completion of the Works

0 0 30-Jun-24 A

100%

Planned Comple

 

Possession of Site

Possession of Site

KD0000200

Possession of First Stage Portion A

0 30-Dec-19

0 30-Dec-19 A

100% 0

Possession of First Stage Portion A

 

KD0000210

Possession of First Stage Portion B

0 30-Dec-19

0 30-Dec-19 A

100% 0

Possession of First Stage Portion B

 

KD0000220

Possession of Area for Access Road

0 30-Dec-19

0 30-Dec-19 A

100% 0

Possession of Area for Access Road

 

KD0000230

Possession of Temporary Works Area 1

0 30-Dec-19

0 30-Dec-19 A

100% 0

Possession of Temporary Works Area 1

 

KD0000240

Possession of Temporary Works Area 2

0 30-Dec-19

0 30-Dec-19 A

100% 0

Possession of Temporary Works Area 2

 

KD0000250

Possession of Temporary Works Area 3

0 30-Dec-19

0 30-Dec-19 A

100% 0

Possession of Temporary Works Area 3

 

KD0000260

Possession of Temporary Works in Clear Water Bay Country Park

0 30-Dec-19

0 30-Dec-19 A

100% 0

Possession of Temporary Works in Clear Water Bay Country Park

 

Executive Summaries

Preliminary Setup

Civil Design AIP and DDA

M&E Design AIP and DDA

Executive Summaries Preliminary Setup

ES0001000

Mobilization and Preliminary Set Up

191

30-Dec-19

07-Jul-20

0

30-Dec-19 A

20-Jul-20 A

100%

-13

 

Civil Design AIP and DDA

ES0001010

AIP Civil Design Submission and Approval

330

30-Dec-19

23-Nov-20

0

30-Dec-19 A

31-Aug-20 A

100%

84

ES0001020

DDA Civil Design Submission and Approval

414

28-Feb-20

16-Apr-21

0

22-Jan-20 A

01-Sep-21 A

100%

-138

 

M&E Design AIP and DDA

ES0002000

M&E AIP Process Mechanical Submission and Approval

477

30-Dec-19

19-Apr-21

0

30-Dec-19 A

22-Dec-20 A

100%

118

ES0002010

M&E DDA Process Mechanical Submission and Approval

679

08-Feb-20

17-Dec-21

0

21-Jul-20 A

02-Sep-21 A

100%

106

ES0002020

M&E AIP Instrumentation & Control Submission and Approval

607

31-Jan-20

28-Sep-21

0

04-Feb-20 A

25-Feb-20 A

100%

581

ES0002030

M&E DDA Instrumentation & Control Submission and Approval

514

22-Jul-20

17-Dec-21

0

13-Feb-21 A

14-Apr-23 A

100%

-482

ES0002050

M&E DDA Renewable Energy Submission and Approval

382

16-Aug-20

01-Sep-21

0

17-Aug-20 A

31-Dec-20 A

100%

244

ES0002060

M&E AIP Building Services Submission and Approval

226

30-Dec-19

11-Aug-20

0

30-Dec-19 A

30-Oct-20 A

100%

-80

ES0002065

M&E Design Basis & Civil Guidance Dwg

112

30-Dec-19

19-Apr-20

0

30-Dec-19 A

24-Jul-20 A

100%

-96

ES0002070

M&E DDA Building Services Submission and Approval

306

28-Feb-20

29-Dec-20

0

01-Mar-20 A

30-Jun-21 A

100%

-183

ES0002085

M&E AIP Site Wide Electrical Submission and Approval

155

09-Jun-20

10-Nov-20

0

21-Mar-20 A

22-Jul-20 A

100%

111

ES0002090

M&E CMS Lift Submission and Approval

140

27-Aug-20

13-Jan-21

0

01-Oct-20 A

20-Jul-21 A

100%

-188

ES0002095

M&E DDA Site Wide Electrical Submission and Approval

140

11-Nov-20

30-Mar-21

0

23-Jul-20 A

04-Jun-21 A

100%

-66

ES0002100

M&E DDA T&C Design Submission and Approval

155

29-Mar-22

30-Aug-22

0

01-Aug-21 A

05-Oct-23 A

100%

-401

 

Procurement of Major Plant & Equipment Schedule

ES0002320

M&E Procurement of Major Plant, Equipment, Material and Delivery

901

14-Mar-20

31-Aug-22

0

04-Feb-20 A

16-Jan-23 A

100%

-137

ES2420

M&E Procurement of Mechanical Equipment - Intake Pumps

595

18-May-20

02-Jan-22

0

04-Feb-20 A

11-May-22 A

100%

-128

ES2430

M&E Procurement of Mechanical Equipment - ActiDAFF Underdrain

333

30-Oct-20

27-Sep-21

0

02-Aug-20 A

14-Mar-22 A

100%

-168

ES2440

M&E Procurement of Mechanical Equipment - ActiDAFF Media

298

15-Mar-21

06-Jan-22

0

23-Jul-20 A

14-Oct-22 A

100%

-281

ES2450

M&E Procurement of Mechanical Equipment - RO and ERD Rack

274

22-Feb-21

22-Nov-21

0

22-Jul-20 A

28-Dec-21 A

100%

-36

ES2460

M&E Procurement of Mechanical Equipment - RO Membrane

755

29-Mar-20

22-Apr-22

0

12-Feb-20 A

28-Dec-22 A

100%

-249

ES2470

M&E Procurement of Electrical Equipment - CLP Substation for LV Switchboard / Genset / Building Services

300

14-Mar-20

07-Jan-21

0

14-Mar-20 A

28-Feb-21 A

100%

-52

 

Procurement of Major Plant & Equipment Schedule

Summary Bar

Actual Level of Effort Target Bar

Actual Work Early Bar Critical Bar

Target Milestone Milestone

Page 1 of 5

 

Appendix D - Critical Path

 

file: MPR202407_c

13/WSD/17 Design, Build and Operate Stage 1 of Tesung Kwan O Desalination Plant 31 Jul 24

Activity ID Activity Name Baseline

Baseline Start Baseline Finish Remaining

Actual / Planned

Actual / Planned

Actual %

Variance

Total

2020 2021 2022 2023 2024

 

132kV Substation

132kV Substation

Duration

Duration

Start

Finish

Complete

Finish Date

Float N D J

F M A M J

J A S O N D J

F M A M J

J A S O N D J

F M A M J

J A S O N D J

F M A M J

J A S O N D J

F M A M J

J A S

O N D

ES0001460

Excavation and Formation Works for 132kV Substation

15 16-Mar-20

30-Mar-20

0 19-Feb-20 A

23-Apr-20 A

100%

-24

 

ES0001470

Construction of 132kV Substation

233

31-Mar-20

18-Nov-20

0 27-Apr-20 A

30-Dec-20 A

100%

-42

 

ES0001480

Architectural Finishes for 132kV Substation

126

11-Sep-20

2.   Jan-21

0 23-Nov-20 A

22-Mar-21 A

100%

-67

 

Combine Shaft

Intake

OutFall

ActiDAFF

Reverse Osmosis Building

ES0002240

M&E Installation of 132kV Substation

93 20-Nov-20

20-Feb-21

0 01-Dec-20 A

22-Mar-21 A

100%

-30

 

Combine Shaft

ES0001060

Construction of Combine Shaft

257

27-Mar-20

08-Dec-20

0

02-May-20 A

30-Jun-21 A

100%

-204

ES0002120

M&E Installation at Combine Shaft

160

03-Jan-22

11-Jun-22

0

11-Oct-22 A

06-May-23 A

100%

-328

Intake

ES0001070

DN2500 Pipe Jacking for Intake Pipeline

163

09-Dec-20

20-May-21

0

02-Jul-21 A

28-Mar-22 A

100%

-312

ES0001080

Receiving Pit and Marine Intake Structure

416

11-Nov-20

31-Dec-21

0

22-Mar-21 A

30-Dec-22 A

100%

-364

ES0001110

Construction of Intake Land Structure (Combined Shaft)

193

21-May-21

29-Nov-21

0

17-Feb-22 A

10-Oct-22 A

100%

-315

ES0001120

Architectural Finishes for Intake Land Structure

32

30-Nov-21

31-Dec-21

0

24-Oct-22 A

08-Dec-22 A

100%

-342

OutFall

ES0001090

DN1650 Pipe Jacking for Outfall Pipeline

140

29-Dec-20

17-May-21

0

01-Sep-21 A

24-Mar-22 A

100%

-311

ES0001100

Receiving Pit, Outfall and Diffuser Pipeline

343

18-Dec-20

25-Nov-21

0

08-Apr-21 A

25-Apr-23 A

100%

-516

ActiDAFF

ES0001140

Excavation for ActiDAFF

97

02-May-20

06-Aug-20

0

22-Apr-20 A

15-Aug-20 A

100%

-9

ES0001150

Construction of ActiDAFF Structure

393

11-Sep-20

08-Oct-21

0

10-Aug-20 A

03-Aug-22 A

100%

-299

ES0001160

Architectural Finishes for ActiDAFF

183

07-Jul-21

05-Jan-22

0

28-Apr-22 A

10-Oct-22 A

100%

-278

ES0002130

M&E Installation at ActiDAFF

257

28-Sep-21

11-Jun-22

0

22-Jan-22 A

20-May-24 A

100%

-708

ES0002140

M&E Installation of Filter Water Tank and Pumping Station

137

29-Nov-21

14-Apr-22

0

01-Jul-22 A

24-Aug-23 A

100%

-496

 

Reverse Osmosis Building

ES0001170

Excavation at RO Building

270

24-Jun-20

20-Mar-21

0

18-Jun-20 A

10-Oct-20 A

100%

161

ES0001180

Construction of RO Building

321

16-Nov-20

02-Oct-21

0

25-Aug-20 A

11-Dec-21 A

100%

-70

ES0001190

Architectural Finishes for RO Building

106

09-Aug-21

22-Nov-21

0

20-Sep-21 A

21-Oct-22 A

100%

-333

ES0002150

M&E Installation of RO Building

315

23-Nov-21

03-Oct-22

0

24-Nov-21 A

05-Dec-23 A

100%

-428

 

Product Water Storage Tank

ES0001240

Excavation and Soil Nail System for Product Water Storage Tank

106

10-Aug-20

23-Nov-20

0

24-Jun-20 A

01-Dec-20 A

100%

-8

ES0001250

Construction of Product Water Storage Tank

276

24-Nov-20

26-Aug-21

0

21-Oct-20 A

18-Dec-21 A

100%

-114

ES0001260

Architectural Finishes for Product Water Storage Tank

70

27-Aug-21

04-Nov-21

0

16-May-22 A

07-Jun-22 A

100%

-215

ES0002210

M&E Installation of Product Water Tank

78

12-Jan-22

30-Mar-22

0

31-Jul-21 A

04-Apr-24 A

100%

-736

 

Product Water Pumping Station

ES0001270

Excavation for Product Water Pump Station

47

22-Oct-20

07-Dec-20

0

08-Mar-21 A

07-Apr-21 A

100%

-121

ES0001280

Construction of Product Water Pump Station

270

22-Jan-21

18-Oct-21

0

17-Apr-21 A

18-Dec-21 A

100%

-61

ES0001290

Architectural Finishes for Product Water Pumping Station

106

25-Sep-21

08-Jan-22

0

10-Feb-22 A

16-Jul-22 A

100%

-189

ES0002215

M&E Installation of Product Water Pump Station

78

12-Jan-22

30-Mar-22

0

20-Jun-22 A

14-Dec-23 A

100%

-624

 

Chemical Building

ES0001300

Excavation for Chemical Building

42

12-Aug-20

22-Sep-20

0

17-Jun-21 A

17-Jul-21 A

100%

-298

ES0001310

Construction of Chemical Building

255

23-Sep-20

04-Jun-21

0

17-Jul-21 A

09-Jun-22 A

100%

-370

ES0001320

Architectural Finishes for Chemical Building

73

05-Jun-21

16-Aug-21

0

09-Jun-22 A

30-Nov-22 A

100%

-470

ES0002220

M&E Installation of Chemical Building

264

02-Sep-21

23-May-22

0

15-Aug-22 A

10-Aug-23 A

100%

-443

 

Product Water Storage Tank

Product Water Pumping Station

Chemical Building

Administration Building

Administration Building

 

Summary Bar

Actual Level of Effort Target Bar

Actual Work Early Bar Critical Bar

Target Milestone Milestone

Page 2 of 5

 

Appendix D - Critical Path

 

file: MPR202407_c

13/WSD/17 Design, Build and Operate Stage 1 of Tesung Kwan O Desalination Plant 31 Jul 24

Activity ID

Activity Name

Baseline

Baseline Start

Baseline Finish

Remaining

Actual / Planned

Actual / Planned

Actual %

Variance

Total

2020 2021 2022 2023 2024

 

ES0001330

 

Piling Works for Administration Building

Duration

110

 

19-Oct-20

 

05-Feb-21

Duration

0

Start

03-Oct-20 A

Finish

16-Jan-21 A

Complete

100%

Finish Date

20

Float N D J

F M A M J

J A S O N D J

F M A M J

J A S

O N D J

F M A M J

J A S O N D J

F M A M J

J A S O N D J

F M A M J

J A S O N D

 

ES0001340

Excavation for Administration Building

31 06-Feb-21

08-Mar-21

0 28-Dec-20 A

3.   Mar-21 A

100% -7

 

ES0001350

Construction of Administration Building

339

09-Mar-21

1.   Feb-22

0 28-Jan-21 A

1.   Aug-22 A

100%

-200

 

ES0001360

Architectural Finishes for Administration Building

204

1.   Aug-21

17-Mar-22

0 19-Apr-22 A

22-May-23 A

100%

-431

 

ES0002230

M&E Installation of Admin Building

184

4.   Nov-21

18-May-22

0 15-Jul-22 A

18-Feb-23 A

100%

-276

 

Building Services & Lift Installation

Building Services & Lift Installation

ES0002270

Lift Installation

147

1.   Mar-22

1.  Aug-22

0 02-Feb-23 A

28-Jun-24 A

100%

-686

 

ES0002280

Building Services Installation

676

1.   Nov-20

1.   Oct-22

12 01-Dec-20 A

2.   Aug-24

85%

-679

-194

Building Ser

 

OSCG Building

OSCG Building

ES0001400

Excavation for On-site Chlorine Generation Building

25 11-Dec-20

3.   Jan-21

0 01-Apr-21 A

09-Apr-22 A

100%

-460

 

ES0001410

Construction of On-site Chlorine Generation Building

291

4.   Jan-21

22-Oct-21

0 05-Jul-21 A

15-Jun-22 A

100%

-236

 

ES0001420

Architectural Finishes for On-site Chlorine Generation Building

59 23-Oct-21

5.   Dec-21

0 16-Jun-22 A

1.   Sep-22 A

100%

-282

 

Post Treatment Building

Sludge Thickener

Workshop

Inspection Corridor

ES0002200

BS Installation of On-site Chlorine Generation Building (DG inspection)

162

6.   Dec-21

31-May-22

12 11-Oct-22 A

12-Aug-24

90%

-804

-194

BS Installatio

 

Post Treatment Building

ES0001210

Excavation and ELS for Post Treatment Building

126

19-Dec-20

23-Apr-21

0

03-Dec-20 A

01-Sep-21 A

100%

-131

ES0001220

Construction of Post Treatment Building

209

14-Apr-21

08-Nov-21

0

17-Dec-20 A

19-May-22 A

100%

-192

ES0001230

Architectural Finishes for Post Treatment Building

59

11-Oct-21

08-Dec-21

0

22-Jul-22 A

16-Sep-22 A

100%

-282

ES0002180

M&E Installation of Post Treatment Building

199

09-Dec-21

25-Jun-22

0

14-Jul-22 A

04-Apr-24 A

100%

-649

 

Sludge Thickener

ES0001680

Excavation for Sludge Thickener

73

19-Apr-21

30-Jun-21

0

02-Oct-21 A

16-Oct-21 A

100%

-108

ES0001690

Construction of Sludge Thickener

121

02-Jul-21

30-Oct-21

0

08-Oct-21 A

26-Jul-22 A

100%

-269

ES0001700

Architectural Finishes for Sludge Thickener

44

01-Nov-21

14-Dec-21

0

29-Jul-22 A

31-Jan-24 A

100%

-778

ES0002190

M&E Installation of Sludge Thickener

141

15-Dec-21

04-May-22

0

06-Feb-23 A

28-Mar-24 A

100%

-693

Workshop

ES0001560

Excavation for Workshop

7

21-May-21

27-May-21

0

06-Nov-23 A

07-Nov-23 A

100%

-894

ES0001570

Construction of Workshop

179

28-May-21

22-Nov-21

0

08-Nov-23 A

15-Mar-24 A

100%

-844

ES0001580

Architectural Finishes for Workshop

81

17-Nov-21

05-Feb-22

0

16-Mar-24 A

26-Jun-24 A

100%

-872

 

Inspection Corridor

ES0001590

Piling for Inspection Corridor (Elevated Walkway)

60

09-Jan-21

09-Mar-21

0

15-Dec-20 A

19-Jan-21 A

100%

49

ES0001600

Excavation for Inspection Corridor

121

14-Apr-21

12-Aug-21

0

26-Mar-21 A

28-May-22 A

100%

-289

ES0001610

Construction of Inspection Corridor

299

06-May-21

28-Feb-22

0

12-Apr-21 A

16-Nov-23 A

100%

-626

ES0001620

Architectural Finishes for Inspection Corridor

99

08-Feb-22

17-May-22

0

03-Oct-23 A

29-Jun-24 A

100%

-774

ES0001625

Building Services for Inspection Corridor

0

0

03-Jan-23 A

01-Feb-24 A

100%

 

Main Electrical and Central Chiller Plant Building

ES0001430

Excavation for Main Electrical and Central Chiller Plant Building

20

11-Jan-21

30-Jan-21

0

18-Jan-21 A

06-Feb-21 A

100%

-7

ES0001440

Construction of Main Electrical and Central Chiller Plant Building

227

01-Feb-21

15-Sep-21

0

01-Feb-21 A

20-Oct-21 A

100%

-35

ES0001450

Architectural Finishes for Main Electrical and Central Chiller Plant Building

99

20-Jul-21

26-Oct-21

0

06-Nov-21 A

25-Jun-22 A

100%

-242

ES0002260 M&E Installation for Main Electrical and Central Chiller Plant Building

 

Guard House

152

25-Jan-22

25-Jun-22

0

27-Jul-22 A

14-Apr-23 A

100%

-293

ES0001490

Excavation for Guard House at Main Gate

7

15-Sep-21

21-Sep-21

0

16-May-23 A

17-May-23 A

100%

-603

ES0001500

Construction of Guard House at Main Gate

149

23-Sep-21

18-Feb-22

0

18-May-23 A

26-Aug-23 A

100%

-554

ES0001510

Architectural Finishes for Guard House at Main Gate

76

19-Feb-22

05-May-22

0

18-Aug-23 A

15-Sep-23 A

100%

-498

ES0001520

Excavation for Guard House near Pier

8

21-May-21

28-May-21

0

07-Jun-23 A

09-Jun-23 A

100%

-742

 

Main Electrical and Central Chiller Plant Building

Guard House

Summary Bar

Actual Level of Effort Target Bar

Actual Work Early Bar Critical Bar

Target Milestone Milestone

Page 3 of 5

 

Appendix D - Critical Path

 

file: MPR202407_c

13/WSD/17 Design, Build and Operate Stage 1 of Tesung Kwan O Desalination Plant 31 Jul 24

Activity ID

Activity Name

Baseline

Baseline Start

Baseline Finish

Remaining

Actual / Planned

Actual / Planned

Actual %

Variance

Total

2020 2021 2022 2023 2024

 

ES0001530

 

Construction of Guard House near Pier

Duration

147

 

1.   May-21

 

7.   Oct-21

Duration

0

Start

10-Jun-23 A

Finish

1.   Oct-23 A

Complete

100%

Finish Date

-718

Float N D J

F M A M J

J A S O N D J

F M A

M J J A S O N D J F M A M J

J A S O N D J

F M A M J J A S

O N D J

F M A M J

J A S O N D

 

CO2 Tanks Areas

Diesel Emergency Generator

ES0001540

Architectural Finishes for Guard House near Pier

74 23-Oct-21

1.   Jan-22

0 05-Oct-23 A

8.   Mar-24 A

100%

-809

 

Switch Room and Transformer Installation

Miscellaneous

CO2 Tanks Areas

ES0001370

Filling to Formation for CO2 Tanks Area

29

22-Jun-21

20-Jul-21

0

14-Dec-21 A

17-Dec-21 A

100%

-150

ES0001380

Construction of CO2 Tanks Area

116

21-Jul-21

13-Nov-21

0

21-Dec-21 A

10-Mar-22 A

100%

-117

ES0002170

M&E Installation of CO2 Tanks Area

84

27-Jan-22

20-Apr-22

0

11-Mar-22 A

03-Oct-23 A

100%

-531

 

Diesel Emergency Generator

ES0002250

M&E Diesel Emergency Generator

57

25-Feb-22

22-Apr-22

0

18-Jan-23 A

28-Jul-23 A

100%

-462

 

Switch Room and Transformer Installation

ES0002300

M&E Installation of HV/LV Switchroom and Transformer (Admin)

242

16-Nov-21

15-Jul-22

0

27-Jul-22 A

20-Apr-23 A

100%

-279

 

Miscellaneous

ES0001630

Remaining Architectural Finishes for All Buildings

322

11-Jan-22

28-Nov-22

0

09-Dec-22 A

29-Jun-24 A

100%

-579

ES0001640

External Process and Non Process Pipe

655

18-Dec-20

03-Oct-22

0

27-May-21 A

23-Nov-23 A

100%

-416

ES0001650

Drainage and Cable Duct

518

04-Jun-21

03-Nov-22

0

25-Apr-22 A

18-Jul-23 A

100%

-257

ES0001660

Slope Mitigation Works

684

23-Nov-20

07-Oct-22

76

28-Sep-21 A

15-Oct-24

50%

-739

-258

ES0001670

Landscaping Works

469

28-Oct-21

08-Feb-23

0

01-Mar-23 A

18-May-24 A

100%

-465

ES0002290

M&E PV Panels

215

23-Nov-21

25-Jun-22

0

05-Jan-23 A

29-Jul-24 A

100%

-764

ES0002310

M&E Chiller & Irrigation System Installation

298

27-Oct-21

20-Aug-22

0

25-Aug-23 A

30-May-24 A

100%

-648

ES0002350

M&E Installation of Surge Vessel

70

24-Feb-22

04-May-22

0

15-Sep-23 A

30-Oct-23 A

100%

-544

ES0002390

M&E Installation of Thickened Sludge Holding Tank

42

09-Dec-21

19-Jan-22

0

27-Mar-23 A

31-Jan-24 A

100%

-742

Slope

 

Statutory Submission & Inspection

Statutory Submission & Inspection

ES0002330 Statutory Submission & Inspection 1148 11-Jan-20 03-Mar-23 2 03-Dec-19 A 02-Aug-24 100% -518 -184

 

Statutory Sub

 

Testing and Commissioning

Testing and Commissioning

ES0002400

M&E Precomissioning

229

12-Jun-22

26-Jan-23

0

22-Apr-23 A

29-Mar-24 A

100%

-428

ES0002410

M&E Commissioning

213

04-Jul-22

01-Feb-23

0

02-Jun-23 A

30-Jul-24 A

100%

-544

ES0002420

M&E Performance Test

40

02-Feb-23

13-Mar-23

0

28-Nov-23 A

26-Apr-24 A

100%

-409

 

Procurement of Major Plant & Equipment Schedule

Pipes, Fittings and Valves

Procurement of Major Plant & Equipment Schedule Pipes, Fittings and Valves

Pressure Relief Valves

Pressure Relief Valves

P-PV-A51IK-0 NR Receipt - Pressure relief valves

 

0 08-Sep-21 0

 

02-Oct-20 A

 

100%

 

341

 

NR Receipt - Pressure relief valves

 

P-PV-A51IK-0 Receipt of offers - Pressure relief valves

30 09-Sep-21

08-Oct-21

0 03-Oct-20 A

27-Oct-20 A

100%

346

Receipt of offers - Pressure relief valves

 

P-PV-A51IK-0 Technical Validation - Pressure relief valves

30 09-Oct-21

07-Nov-21

0 28-Oct-20 A

9.   Mar-21 A

100%

248

Technical Validation - Pressure relief valves

 

P-PV-A51IK-0 Negotiation and Award / Client Approval - Pressure relief valves

60 08-Nov-21

10.Jan-22

0 06-Mar-21 A

2.   Nov-21 A

100% 49

Negotiation and Award / Client Approval - Pressure relief valves

 

P-PV-A51IK-0 Manufacture and FAT - Pressure relief valves

187

1.   Jan-22

12-Jul-22

0 20-Nov-21 A

22-Jul-22 A

100% -9

Manufacture and FAT - Pressure relief valves

 

P-PV-A51IK-0 Transport & Customs - Pressure relief valves

50 13-Jul-22

31-Aug-22

0 23-Jul-22 A

31-Jul-22 A

100% 32

Transport & Customs - Pressure relief valves

 

P-PV-A51IK-0 1st delivery date to site - Pressure relief valves

0 31-Aug-22 0

31-Jul-22 A

100% 32

1st delivery date to site - Pressure relief valves

 

Instrumentation, Control & Automation

Instrumentation, Control & Automation

Bypass Level Indicators

Bypass Level Indicators

P-IC-A08FK2- NR Receipt - Bypass Level Indicators

 

0 12-Apr-21 0

 

16-Sep-20 A

 

100%

 

208

 

NR Receipt - Bypass Level Indicators

 

P-IC-A08FK2- Receipt of offers - Bypass Level Indicators

30 13-Apr-21

12-May-21

0 17-Sep-20 A

3.   Oct-20 A

100%

205

Receipt of offers - Bypass Level Indicators

 

P-IC-A08FK2- Technical Validation - Bypass Level Indicators

30 13-May-21

1.  Jun-21

0 21-Oct-20 A

25-Nov-20 A

100%

199

Technical Validation - Bypass Level Indicators

 

P-IC-A08FK2- Negotiation and Award / Client Approval - Bypass Level Indicators

60 12-Jun-21

10-Aug-21

0 26-Nov-20 A

1.   Jun-21 A

100% 42

Negotiation and Award / Client Approval - Bypass Level Indicators

 

P-IC-A08FK2- Manufacture and FAT - Bypass Level Indicators

90 11-Aug-21

1.   Nov-21

0 01-Jul-21 A

22-Jul-22 A

100%

-255

Manufacture and FAT - Bypass Level Indicators

 

P-IC-A08FK2- Transport & Customs - Bypass Level Indicators

50 09-Nov-21

28-Dec-21

0 18-Sep-22 A

26-Oct-22 A

100%

-301

Transport & Customs - Bypass Level Indicators

 

Summary Bar

Actual Level of Effort Target Bar

Actual Work Early Bar Critical Bar

Target Milestone Milestone

Page 4 of 5

 

Appendix D - Critical Path

 

file: MPR202407_c

13/WSD/17 Design, Build and Operate Stage 1 of Tesung Kwan O Desalination Plant 31 Jul 24

Activity ID

Activity Name

Baseline

Baseline Start

Baseline Finish

Remaining

Actual / Planned

Actual / Planned

Actual %

Variance

Total

2020 2021 2022 2023 2024

 

P-IC-A08FK2- 1st delivery date to site - Bypass Level Indicators

Duration

0

 

28-Dec-21

Duration

0

Start

Finish

26-Oct-22 A

Complete

100%

Finish Date

-301

Float N D J

F M A M J

J A S O N D J

F M A

M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S

1st delivery date to site - Bypass Level Indicators

O N D

 

Level Transmitters

Level Transmitters

P-IC-A08FK1- NR Receipt - Level Transmitters

 

0 12-Apr-21 0

 

16-Sep-20 A

 

100%

 

208

 

NR Receipt - Level Transmitters

 

P-IC-A08FK1- Receipt of offers - Level Transmitters

30 13-Apr-21

2.   May-21

0 17-Sep-20 A

20-Oct-20 A

100%

204

Receipt of offers - Level Transmitters

 

P-IC-A08FK1- Technical Validation - Level Transmitters

30 13-May-21

11-Jun-21

0 21-Oct-20 A

26-Nov-20 A

100%

198

Technical Validation - Level Transmitters

 

P-IC-A08FK1- Negotiation and Award / Client Approval - Level Transmitters

60 12-Jun-21

10-Aug-21

0 26-Nov-20 A

02-Dec-21 A

100%

-113

Negotiation and Award / Client Approval - Level Transmitters

 

P-IC-A08FK1- Manufacture and FAT - Level Transmitters

90 11-Aug-21

08-Nov-21

0 03-Dec-21 A

1.   Mar-22 A

100%

-142

Manufacture and FAT - Level Transmitters

 

P-IC-A08FK1- Transport & Customs - Level Transmitters

50 09-Nov-21

28-Dec-21

0 02-Apr-22 A

01-Jun-22 A

100%

-154

Transport & Customs - Level Transmitters

 

P-IC-A08FK1- 1st delivery date to site - Level Transmitters

0 28-Dec-21 0

01-Jun-22 A

100%

-154

1st delivery date to site - Level Transmitters

 

Construction

Construction

Civil & Structure Construction

Civil & Structure Construction

ActiDAFF Structure (DAF)

ActiDAFF Structure (DAF)

CC0200906k DAF: Remedial Work at Cell No. 1 and 3 after Water Test 0 0 30-Nov-21 A 27-Jun-22 A 100%

 

DAF: Remedial Work at Cell No. 1 and 3 after Water Test

 

Yard Piping - Process & Non Process

Yard Piping - Combined Shaft Zone

Yard Piping - Process & Non Process Yard Piping - Combined Shaft Zone

CC2401356k GRP Combined Shaft S - DN500 Tee at +3.214mPD 0 0 01-Apr-23 A 06-Apr-23 A 100%

 

GRP Combined Shaft S - DN500 Tee at +3.214mPD

 

Yard Piping - ActiDAFF Zone

Yard Piping - ActiDAFF Zone

CC2401311k GRP West ActiDAFF: (Covid-19) Limited Resources Effect to GRP Works 0

 

0 08-Feb-22 A

 

19-Apr-22 A

 

100%

 

GRP West ActiDAFF: (Covid-19) Limited Resources Effect to GRP Works

 

CC2401349k GRP South ActiDAFF: DN400 at 5.490mPD at C10/CD~CF 0

0 14-May-22 A

18-Jun-22 A

100%

GRP South ActiDAFF: DN400 at 5.490mPD at C10/CD~CF

 

Summary Bar

Actual Level of Effort Target Bar

Actual Work Early Bar Critical Bar

Target Milestone Milestone

Page 5 of 5

 

Appendix D - Critical Path

 

file: MPR202407_c

 

 

Contract No. 13/WSD/17

Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report

 

Appendix B

 

Overview of Desalination Plant in Tseung Kwan O

 

TEMPORARY

 

GLA—TSK 692

TGLA

SKE PHASING

ALLOCATED LAI4D BOUNDARIES

 

NOTE: TEMPORARY WORKS AREA 1 \YILL BE

 

TOLERAMCC OC *500mm.

 

 

A 07/I 8 UPDATE COORDINATES

YLc YLC

 

YLC

CKH

SZ

TLS

°°t'

o2/ 8

o2/18

o2/18

o2/18

 

FOR

 

 

PORTION 8

CE 8/ 2015 (W s)

 

ROINT

EASTING

NORTHINC

A

8465B I.93

8l4S0â.03

 

B

 

8‹6610.11

 

813979.23

C

8466 I ‹.73

813975.I 2

D

%662909

8139978

E

8466+1.75

813986.74

F

8‹66 6.80

8i 3985.28

G

846677.2A

8\4034.67

13/¥/S D/ 17

 

DESIGN, BUILD AND OPERATE FIRST STA6E OF TSEUN6 KWAN 0 DESALINATION PLANT

 

)

 

SITE HANDOVER WORKS AREAS

 

 

LA/TRD

NHCATVE L SMñATER I

 

INDICATIVE LOCATION OF PROPOSED OUTFALL

OPOSED

8*6766.21

 

J 8+6+59.65

81*53ll

 

81 \\+8.83

 

190495 K TEND 10 0005

 

l4

84661 4.60

814117.96

H

846676.B4

81T207.77

0

846756.68

81416T.57

Water Supplies Department

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

M.L.

 

100

C.L. A.U.T.

 

MV/AL F.E.

H.R. A D

P.D.

 

MAIN ELECTRICAL AND CENTRAL CHILLER PLANT BUILDING

 

TOTAL G.F.A.

TOTAL SITE COVERAGE

=

=

PLOT RATIO

=

=

25092.141 / 56108

0.447 < PERMITTED

SITE COVERAGE

=

=

21414.841 / 56108 x 100

38.167%

FIRST STAGE

 

82

 

20

JOSS HOUSE BAY ( TAI MIU WAN )

 

 

Contract No. 13/WSD/17

Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report

 

Appendix C

 

Summary of Implementation Status of Environmental Mitigation

 

EIA

Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

Air Quality

S4.8.1

Impervious dust screen or sheeting will be provided to enclose scaffolding from the ground floor level of building for construction of superstructure of the new buildings.

Land site/ During Construction

Contractor(s)

ü

Implemented

Air Pollution Control (Construction Dust)

S4.8.1

Impervious sheet will be provided for skip hoist for material transport.

Land site/ During Construction

Contractor(s)

ü

NA

-

S4.8.1

The area where dusty work takes place should be sprayed with water or a dust suppression chemical immediately prior to, during and immediately after dusty activities as far as practicable.

Land site/ During Construction

Contractor(s)

ü

Implemented

-

S4.8.1

All dusty materials should be sprayed with water or a dust suppression chemical immediately prior to any loading, unloading or transfer operation.

Land site/ During Construction

Contractor(s)

ü

Implemented

-

S4.8.1

Dropping heights for excavated materials should be controlled to a practical height to minimize the fugitive dust arising from unloading.

Land site/ During Construction

Contractor(s)

ü

Implemented

-

S4.8.1

During transportation by truck, materials should not be loaded to a level higher than the side and tail boards and should be dampened or covered before transport.

Land site/ During Construction

Contractor(s)

ü

Implemented

-

S4.8.1

Wheel washing device should be provided at the exits of the work sites. Immediately before leaving a construction site, every vehicle shall be washed to remove any dusty material from its body and wheels as far as practicable.

Land site/ During Construction

Contractor(s)

ü

Implemented

-

S4.8.1

Road sections between vehicle-wash areas and vehicular entrance will be paved.

Land site/ During Construction

Contractor(s)

ü

Implemented

-

S4.8.1

Hoarding of not less than 2.4m high from ground level will be provided along the length of the Project Site boundary.

Land site/ During construction

Contractor(s)

ü

ü

N/A

-

S4.8.1

Haul roads will be kept clear of dusty materials and will be sprayed with water so as to maintain the entire road surface wet at all times.

Land site/ During construction

Contractor(s)

ü

Implemented after reminder

-

S4.8.1

Temporary stockpiles of dusty materials will be either covered entirely by impervious sheets or sprayed with water to maintain the entire surface wet all the time.

Land site/ During construction

Contractor(s)

ü

Implemented after reminder

 

-

 

EIA

Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S4.8.1

Stockpiles of more than 20 bags of cement, dry pulverized fuel ash and dusty construction materials will be covered entirely by impervious sheeting sheltered on top and 3-sides.

Land site/ During construction

Contractor(s)

ü

N/A

 

-

S4.8.1

All exposed areas will be kept wet always to minimize dust emission.

Land site/ During construction

Contractor(s)

ü

Implemented after reminder

-

S4.8.1

Ultra-low-Sulphur diesel (ULSD) will be used for all construction plant on-site, as defined as diesel fuel containing not more than 0.005% Sulphur by weight) as stipulated in Environment, Transport and Works Bureau Technical Circular (ETWB-TC(W)) No 19/2005 on Environmental Management on Construction Sites.

Land site/ During construction/ During Operation

Contractor(s)

ü

ü

Implemented

Environment, Transport and Works Bureau Technical Circular (ETWB- TC(W)) No 19/2005 on

Environmental Management on Construction Sites

S4.8.1

The engine of the construction equipment during idling will be switched off.

Land site/ During construction

Contractor(s)

ü

Implemented

-

S4.8.1

Concrete batching plant will be required on site. control measures recommended in the Guidance Note on a Best Practicable Means for Cement Works (Concrete Batching Plant) (BPM 3/2 (93)) will be implemented. The control measures recommended in the Guidance Note on a Best Practicable Means for Cement Works (Concrete Batching Plant) (BPM 3/2 (93)) will be implemented.

Land site/ During construction

Contractor(s)

ü

N/A

 

-

S4.8.1

Regular maintenance of construction equipment deployed on- site will be conducted to prevent black smoke emission.

Land site/ During construction

Contractor(s)

ü

Implemented

-

S4.10

To ensure proper implementation of the recommended dust mitigation measures and good construction site practices during the construction phase, environmental site audits on weekly basis is recommended throughout the construction period.

Land site/ During construction

Contractor(s)/ Environmental Team (ET) & Independent Environmental Checker (IEC)

ü

Implemented

 

-

Noise

S5.7

Only well-maintained plant will be operated on-site, and plant will be serviced regularly during the construction phase.

All area/ During construction

Contractor(s)

ü

Implemented

A Practical Guide for the Reduction of Noise from Construction Works

A Practical Guide for the Reduction of Noise from Construction Works

 

EIA

Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S5.7

Silencers or mufflers on construction equipment will be utilized and will be properly maintained during the construction phase.

Noise control/ During construction

Contractor(s)

ü

N/A

 

-

S5.7

Mobile plant, if any, will be sited as far away from NSRs as possible.

Noise control/ During construction

Contractor(s)

ü

N/A

-

S5.7

Machines and plant (such as trucks) that may be in intermittent use will be shut down between work periods or will be throttled down to a minimum.

Noise control/ During construction

Contractor(s)

ü

Implemented

 

-

S5.7

Plants known to emit noise strongly in one direction will, wherever possible, be orientated so that the noise is directed away from the nearby NSRs.

Noise control/ During construction

Contractor(s)

ü

N/A

 

-

S5.7

Material stockpiles and other structures will be effectively utilized, wherever practicable, in screening noise from on-site construction activities.

Noise control/ During construction

Contractor(s)

ü

N/A

 

-

S5.7

Use of Quite Powered Mechanical Equipment (QPME).

Noise control/ During construction

Contractor(s)

ü

Implemented

-

S5.7

Movable noise barriers of 3m in height with skid footing should be used and located within a few meters of stationary plant and mobile plant such that the line of sight to the NSR is blocked by the barriers. The length of the barrier should be at least five times greater than its height. The noise barrier material should have a superficial surface density of at least 7 kg m-2 and have no o or gappeningss.

Noise control/ During construction

Contractor(s)

ü

N/A

 

-

S5.7

The noise insulating sheet should be deployed such that there would be no opening or gaps on the joints.

Noise control/ During construction

Contractor(s)

ü

N/A

-

S5.7

Construction activities (e.g., excavation/shoring, reinstatement (asphalt), and pipe jacking) will be planned and carried out in sequence, such that items of PME proposed for these activities will not be operated simultaneously.

Noise control/ During construction

Contractor(s)

ü

ü

Implemented

 

-

S5.7

PMEs will not be used at the works areas near educational institutions with residual impact (i.e., the “influence area” within a radius of 40m) during school hours in order to reduce impact to the educational institutions.

Noise control / During construction

Contractor(s)

ü

N/A

 

-

 

EIA

Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S5.7

Noise enclosures or acoustic sheds would be used to cover stationary PME such as generators. Portable/Movable noise enclosure made of material with superficial surface density of at least 7 kg m-2 may be used for screening the noise from operation of the saw/groover, concrete.

Noise control/ Pre- construction/ During construction

Contractor(s)

ü

ü

N/A

 

-

5.9

Sawcutting pavement, breaking up of pavement, excavation

/shoring, pipe laying, backfilling, reinstatement (concrete) and pipe jacking shall be scheduled outside the examination period.

Noise control/ Pre- construction/ During construction

Contractor(s)

ü

ü

N/A

 

-

S5.9

In view the duration of noise exceedance at Creative Secondary School, PLK Laws Foundation College, TKO Kei Tak Primary School and School of Continuing and Professional Studies-CUHK is limited to 8 weeks, the construction work in the influence areas near the four schools shall be scheduled during long school holidays (eg summer holiday, Easter holiday or Christmas holiday, etc) as far as practicable.

Scheduling the construction work for the four schools.

Noise control/ Pre- construction/ During construction

Contractor(s)

ü

ü

N/A

 

-

S5.10

A noise monitoring programme shall be implemented for the construction phase.

Designated monitoring stations as defined in EM&A Manual/During construction phase

Environmental Team

ü

N/A

 

-

S5.10

The effectiveness of on-site control measures could also be evaluated through the regular site audits.

All facilities/ During construction

Contractor(s)/ ET & IEC

ü

Implemented

-

Water Quality

S6.9

Dredged marine sediment will be disposed of in a gazette marine disposal area in accordance with marine dumping permit conditions of the Dumping at Sea Ordinance (DASO).

Marine Dredging/ During construction

Contractor(s)

ü

Implemented

Dumping at Sea Ordinance (DASO)

S6.9

Disposal vessels will be fitted with tight bottom seals in order to prevent leakage of material during transport.

Marine Dredging/ During construction

Contractor(s)

ü

Implemented

-

S6.9

Barges will be filled to a level, which ensures that material does not spill over during transport to the disposal site and that adequate freeboard is maintained to ensure that the decks are not washed by wave action.

Marine Dredging/ During construction

Contractor(s)

ü

Implemented

 

-

S6.9

After dredging, any excess materials will be cleaned from decks and exposed fittings before the vessel is moved from the dredging area.

Marine Dredging/ During construction

Contractor(s)

ü

Implemented

 

-

 

EIA

Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S6.9

All vessels should be well maintained and inspected before use to limit any potential discharges to the marine environment.

Marine Dredging/ During construction

Contractor(s)

ü

Implemented

-

S6.9

All vessels must have a clean ballast system.

Marine Dredging/ During construction

Contractor(s)

ü

Implemented

-

S6.9

No discharge of sewage/grey wastewater should be allowed. Wastewater from potentially contaminated area on working vessels should be minimized and collected. These kinds of wastewater should be brought back to port and discharged at appropriate collection and treatment system.

Marine Dredging/ During construction

Contractor(s)

ü

Implemented

S6.9

No soil waste is allowed to be disposed overboard.

Marine Dredging/ During construction

Contractor(s)

ü

N/A

S6.9

Silt removal facilities such as silt traps or sedimentation facilities will be provided to remove silt particles from runoff to meet the requirements of the TM standard under the WPCO. The design of silt removal facilities will be based on the guidelines provided in ProPECC PN 1/94. All drainage facilities and erosion and sediment control structures will be inspected on a regular basis and maintained to confirm proper and efficient operation at all times and particularly during rainstorms. Deposited silt and grit will be removed regularly.

Land site & drainage/ During construction

Contractor(s)

ü

Implemented

ProPECC PN 1/94 TM

Standard under the WPCO

S6.9

Earthworks to form the final surfaces will be followed up with surface protection and drainage works to prevent erosion caused by rainstorms.

Land site & drainage/ During construction

Contractor(s)

ü

Implemented

-

S6.9

Appropriate surface drainage will be designed and provided where necessary.

Land site & drainage/ During construction

Contractor(s)

ü

Implemented

-

S6.9

The precautions to be taken at any time of year when rainstorms are likely together with the actions to be taken when a rainstorm is imminent or forecasted and actions to be taken during or after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94.

Land site & drainage/ During construction

Contractor(s)

ü

ü

Implemented

ProPECC PN 1/94

S6.9

Oil interceptors will be provided in the drainage system where necessary and regularly emptied to prevent the release of oil and grease into the storm water drainage system after accidental spillages.

Land site & drainage/ During construction

Contractor(s)

ü

N/A

-

 

EIA

Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S6.9

Temporary and permanent drainage pipes and culverts provided to facilitate runoff discharge, if any, will be adequately designed for the controlled release of storm flows.

Land site & drainage/ During construction

Contractor(s)

ü

Implemented

-

S6.9

The temporary diverted drainage, if any, will be reinstated to the original condition when the construction work has finished or when the temporary diversion is no longer required.

Land site & drainage/ During construction

Contractor(s)

ü

N/A

-

S6.9

Appropriate numbers of portable toilets shall be provided by a licensed contractor to serve the construction workers over the construction site to prevent direct disposal of sewage into the water environment.

Land site & drainage/ During construction

Contractor(s)

ü

Implemented

-

S6.9 and S6.12

The sterilization water should be dechlorinated with total residual chlorine (TRC) level below 1 mg/L before discharge to public sewer. In situ testing of TRC should also be conducted for the discharge of chlorinated water for pipeline disinfection to ensure sufficient dechlorination before discharge to public sewer.

Sterilization of water mains prior to commissioning

Contractor(s)

ü

ü

N/A

Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems Inland and Coastal Waters

S6.9

The cleaning and flushing water should also be treated and desilted to the relevant discharge requirement stipulated in TM-DSS before discharging.

Sterilization of water mains prior to commissioning

Contractor(s)

ü

ü

Implemented

S6.9

Site drainage should be well maintained, and good construction practices should be observed to ensure that oil, fuels, solvents and other chemicals are managed, stored and handled properly and do not enter the nearby water streams.

Land site & drainage/ During construction/ During operation

Contractor(s)

ü

ü

Implemented after reminder

 

-

S6.12

Regular site inspections will be carried out in order to confirm that regulatory requirements are being met and that contractors are implementing the standard site practice and mitigation measures as proposed to reduce potential impacts to water quality.

During construction

Contractor(s)/ ET & IEC

ü

Implemented

 

-

Waste Management

S8.5

Nomination of approved personnel to be responsible for standard site practices, arrangements for collection and effective disposal to an appropriate facility of all wastes generated at the site.

Contract mobilization/ During construction

Contractor(s)

ü

Implemented

 

-

 

EIA

Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S8.5

Training of site personnel in proper waste management and chemical handling procedures. Training will be provided to workers on the concepts of site cleanliness and appropriate waste management procedures, including waste reduction, reuse and recycling at the beginning of the construction works.

Contract mobilization/ During construction

Contractor(s)

ü

Implemented

 

-

S8.5

Provision of sufficient waste disposal points and regular collection for disposal.

All area/ During construction/ During operation

Contractor(s)

ü

ü

Implemented

DEVB TC(W) No. 8/2010,

Enhanced Specification for Site Cleanliness and Tidiness.

S8.5

Appropriate measures to reduce windblown litter and dust transportation of waste by either covering trucks or by transporting wastes in enclosed containers.

All area/ During construction

Contractor(s)

ü

Implemented

S8.5

A waste management plan (WMP) as stated in the “ETWB TC(W) No. 19/2005, Environmental Management on Construction Sites” for the amount of waste generated, recycled and disposed of (including the disposal sites) will be established and implemented during the construction phase as part of the Environmental Management Plan (EMP). The Contractor will be required to prepare the EMP and submits it to the Architect/ Engineer under the Contract for approval prior to implementation.

All area/ During construction

Contractor(s)

ü

Implemented

ETWB TC(W) No. 19/2005,

Environmental Management on Construction Sites

S8.5

Separation of chemical wastes for special handling and appropriate treatment at the Chemical Waste Treatment Centre at Tsing Yi.

All area/ During construction

Contractor(s)

ü

Implemented

Chapters 2 & 3 Code of Practice on the Packaging, Labelling & Storage of Chemical Wastes published under the Waste Disposal Ordinance (Cap 354),

S8.5

Regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors.

Land site/ During construction

Contractor(s)

ü

Implemented

Waste Disposal Ordinance (Cap 354)

S8.5

A recording system for the amount of waste generated/ recycled and disposal sites. The trip- ticket system will be included as one of the contractual requirements and implemented by the contractor(s).

Land site/ During construction

Contractor(s)

ü

Implemented

DEVB TC(W) No.

6/2010,

Trip Ticket System for Disposal of Construction &

S8.5

Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of material and their proper disposal.

Land site/ During construction/ During operation

Contractor(s)

ü

Implemented

WBTC 32/92, The Use of Tropical Hard Wood on Construction Site

 

EIA

Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S8.5

Encourage collection of aluminium cans and wastepaper by individual collectors during construction with separate labelled bins provided to segregate these wastes from other general refuse by the workforce.

Land site/ During construction

Contractor(s)

ü

Implemented

ETWB TCW No.

33/2002,

Management of Construction and

S8.5

Any unused chemicals and those with remaining functional capacity will be recycled as far as possible.

Land site/ During construction

Contractor(s)

ü

N/A

-

S8.5

Use of reusable non-timber formwork to reduce the amount of C&D materials.

All areas/ During construction

Contractor(s)

ü

Implemented

WBTC 32/92, The Use of Tropical Hard Wood on Construction Site

S8.5

Prior to disposal of construction waste, wood, steel and other metals will be separated to the extent practical, for re-use and/or recycling to reduce the quantity of waste to be disposed of to landfill.

All areas/ During construction

Contractor(s)

ü

Implemented

DEVB TC(W) No. 6/2010,

Trip Ticket System for

Disposal of Construction & Demolition Materials

S8.5

Proper storage and site practices to reduce the potential for damage or contamination of construction materials.

All areas/ During construction

Contractor(s)

ü

Implemented

-

S8.5

Plan and stock construction materials carefully to reduce amount of waste generated and avoid unnecessary generation of waste.

All areas/ During construction

Contractor(s)

ü

Implemented

 

-

S8.5

A Sediment Quality Report (SQR) for sampling and chemical testing of the sediment will be prepared and submitted to the EPD for approval. The approved detailed sampling and chemical testing will be carried out prior to the commencement of the dredging activities to confirm the sediment disposal method.

Marine works/ During construction

Contractor(s)

ü

N/A

ETWB TC(W) No. 34/2002

and Dumping at Sea Ordinance (DASO)

S8.5

The management of dredged/ excavated sediment management requirement from ETWB TC(W) No. 34/2002 will be incorporated in the Specification of the Contract Documents.

Marine works/ During construction

WSD/ Contractor(s)

ü

Implemented

ETWB TC(W) No. 34/2002

and Dumping at Sea Ordinance (DASO)

S8.5

The contractor will open a billing account with EPD in accordance with the Waste Disposal (Charges for Disposal of Construction Waste) Regulation for the payment of disposal charges.

Contract mobilization/ During construction

Contractor(s)

ü

Implemented

Cap 354N Waste Disposal (Charges for Disposal of Construction Waste) Regulation

S8.5

A trip-ticket system will be established in accordance with DEVB TC(W) No. 6/2010 to monitor the reuse of surplus excavated materials off-site and disposal of construction waste and general refuse at transfer facilities/ landfills, and to control fly-tipping.

Contract mobilization/ During construction

Contractor(s)

ü

Implemented

DEVB TC(W) No. 6/2010,

Trip Ticket System for Disposal of Construction & Demolition Materials

 

EIA

Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S8.5

The project proponent will also conduct regular inspection of the waste management measures implemented on site as described in the Waste Management Plan.

All area/ During construction

Contractor(s)/ Environmental Team (ET) & Independent Environmental Checker (IEC)

ü

Implemented

ETWB TC(W) No.

19/2005,

Environmental Management on Construction Sites

S8.5

A recording system (similar to summary table as shown in Annex 5 and Annex 6 of Appendix G of ETWB TC(W) No. 19/2005) for the amount of waste generated, recycled and

disposed of (including the disposal sites) will be established during the construction phase.

All area/ During construction

Contractor(s)

ü

Implemented

Annex 5 and Annex 6 of Appendix G of ETWB TC(W) No. 19/2005

S8.5

Inert C&D materials (public fill) will be reused within the Project as far as practicable.

All area/ During construction

Contractor(s)

ü

Implemented

-

S8.5

Public fill and construction waste shall be segregated and stored in different containers or skips to facilitate reuse or recycling of materials and their proper disposal.

All area/ During construction

Contractor(s)

ü

Implemented

 

-

S8.5

Specific areas of the work site will be designated for such segregation and storage if immediate use is not practicable.

All area/ During construction

Contractor(s)

ü

Implemented

-

S8.5

To reduce the potential dust and water quality impacts of site formation works, C&D materials will be wetted as quickly as possible to the extent practice after filling.

All area/ During construction

Contractor(s)

ü

Implemented

Air Pollution Control (Construction Dust) Regulation (Cap 311R); WPCO (Cap 358)

S8.5

Open stockpiles of excavated/ fill materials or construction wastes on-site should be covered with tarpaulin or similar fabric.

Land site/ During Construction, particularly dry season

Contractor(s)

ü

Implemented

Air Pollution Control (Construction Dust) Regulation (Cap 311R)

S8.5

Chemical waste container shall be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed.

All area/ During construction/ During operation

Contractor(s)/ WSD

ü

ü

Implemented

Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes

S8.5

Chemical waste container shall have a capacity of less than 450 L unless the specifications have been approved by the EPD.

All area/ During construction/ During operation

Contractor(s)/ WSD

ü

ü

Implemented

S8.5

A label in English and Chinese shall be displayed on the chemical container in accordance with instructions prescribed in Schedule 2 of the Regulations.

All area/ During construction/ During operation

Contractor(s)/ WSD

ü

ü

Implemented

 

EIA

Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S8.5

Storage areas for chemical waste shall be enclosed on at least 3 sides.

All area/ During construction/ During operation

Contractor(s)/ WSD

ü

ü

Implemented

S8.5

Storage areas for chemical waste shall have an impermeable floor and bunding, of capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in that area, whichever is the greatest.

All area/ During construction/ During operation

Contractor(s)/ WSD

ü

ü

Implemented

S8.5

Storage areas for chemical waste shall have adequate ventilation.

All area/ During construction/ During operation

Contractor(s)/ WSD

ü

ü

Implemented

S8.5

Storage areas for chemical waste shall be covered to prevent rainfall entering (water collected within the bund must be tested and disposed of as chemical waste, if necessary).

All area/ During construction/ During operation

Contractor(s)/ WSD

ü

ü

Implemented

S8.5

Storage areas for chemical waste shall be arranged so that incompatible materials are appropriately separated.

All area/ During construction/ During operation

Contractor(s)/ WSD

ü

ü

Implemented

S8.5

General refuse will be stored in enclosed bins or compaction units separately from construction and chemical wastes.

All area/ During construction/ During operation

Contractor(s)/ WSD

ü

ü

Implemented after reminder

S8.5

Adequate number of waste containers will be provided to avoid over-spillage of waste.

All area/ During construction/ During operation

Contractor(s)/ WSD

ü

ü

Implemented

DEVB TC(W) No. 8/2010

Enhanced Specification for

Site Cleanliness and Tidiness.

S8.5

A reputable waste collector will be employed by the Contractor to remove general refuse from the site, separately from construction and chemical wastes, on a daily basis to minimise odour, pest and litter impacts.

All area/ During construction/ During operation

Contractor(s)/ WSD

ü

ü

Implemented after reminder

 

-

S8.5

Recycling bins will be provided at strategic locations within the Site to facilitate recovery of recyclable materials (including aluminum can, waste paper, glass bottles and plastic bottles) from the Site. Materials recovered will be sold for recycling.

All area/ During construction/ During operation

Contractor(s)/ WSD

ü

ü

Implemented

 

-

S8.5

To avoid any odour and litter impact, accurate number of portable toilets will be provided for workers on-site.

All area/ During construction

Contractor(s)

ü

Implemented

-

S8.5

The burning of refuse on construction sites is prohibited by law.

All area/ During construction

Contractor(s)

ü

Implemented

Air Pollution Control Ordinance (Cap 311)

 

EIA

Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S8.7

To facilitate monitoring and control over the contractors’ performance on waste management, a waste inspection and audit programme will be implemented throughout the construction phase.

All facilities/ During construction

ET/ IEC

ü

Implemented

 

-

Ecology

S9.7

For slope mitigation works within the Clear Water Bay Country Park, to avoid tree felling and damages to trees, the exact locations of the flexible barrier foundation plates, soil nails and rock dowels can be adjusted during detailed design, and a setback distance from existing trees is recommended to be maintained as far as practical. A detailed specification describing the exact locations of the flexible barrier foundation plates, soil nails and rock dowels will be prepared to illustrate how the setback distance from existing trees would be implemented for tree avoidance.

Slope mitigation works area/ During detailed design/ During construction

Contractor(s)

ü

ü

Implemented

 

-

S9.7

Pruning of tree canopies along the alignment of the flexible barriers shall be limited to a minimum.

Slope mitigation works area/ During construction

Contractor(s)

ü

Implemented

S9.7

The alignment of flexible barriers shall be optimized to preserve all species of conservation interest and minimize the impact to the existing vegetation as far as practicable. All individuals of Marsdenia lachnostoma within the slope mitigation areas shall be retained in- situ, by positioning the alignment of flexible barrier at a minimum 1.5m in a radius away from these individuals.

Slope mitigation works area/ During detailed design/ During construction

Contractor(s)

ü

ü

Implemented

 

-

S9.7 and 9.10

At the detailed design stage prior to the commencement of the slope mitigation works, a vegetation survey shall be carried out at the slope mitigation areas within the Clear Water Bay Country Park to assess the condition and identify the location of each individual of Marsdenia lachnostoma and other flora species of conservation interest that may be directly affected by the construction works.

Slope mitigation works area/ During detailed design/ During construction

Contractor(s)

ü

Implemented

 

-

S9.7

Temporary fencing will be installed to fence off the concerned species either in groups of individually within the works area and in the close proximity to prevent from being damaged and disturbed during construction. A sign identifying the site shall be attached to the fence and flagging tape shall be attached to the individuals to visualize their locations.

Slope mitigation works area/ During construction

Contractor(s)

ü

Implemented

 

-

 

EIA

Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S9.7 and S9.10

A specification for fencing and demarcating individuals of Marsdenai lachnostoma (or other flora species of conservation interest, if found) adjacent to the proposed alignment of the flexible barriers will be prepared to protect the species.

Slope mitigation works area/ During construction

Contractor(s)

ü

Implemented

 

-

S9.7

Induction training shall also be provided to all site personnel in order to brief them on this flora of conservation interest including the locations and their importance.

Slope mitigation works area/ During construction

Contractor(s)

ü

Implemented

 

-

S9.7

The resident site supervisory staff will closely monitor the conditions of concerned individuals during construction of flexible barriers in the close proximity.

Slope mitigation works area/ During construction

Contractor(s)

ü

Implemented

 

-

S9.7

Erect fences along the boundary of the works area before the commencement of works to prevent vehicle movements and encroachment of personnel onto adjacent areas.

All area/ During construction

Contractor(s)

ü

Implemented

 

-

S9.7

Regularly check the work site boundaries to ensure that they are not breached and that damage does not occur to surrounding areas.

All area/ During construction

Contractor(s)/ ET

ü

Implemented after reminder

 

-

S9.7

Avoid any damage and disturbance, particularly those caused by filling and illegal dumping, to the surrounding habitats through proper management of waste disposal.

All area/ During construction

Contractor(s)

ü

Implemented

 

-

S9.7

Reinstate temporarily affected areas, particularly the habitats of plantation and shrubland-grassland immediately after completion of construction works, through on-site tree/shrub planting. The tree/shrub species will be chosen with reference to those in the surrounding area.

All area/ During construction

Contractor(s)

ü

To be Implemented

 

-

S9.7

Affected habitats within the Clear Water Bay Country Bay shall be reinstated by hydro-seeding and planting of climbers and native shrub seedlings where practical upon completion of the slope mitigation works.

All area/ During construction

Contractor(s)

ü

To be Implemented

 

-

Landscape & Visual

S11.10 & 11.11

The construction area and area allowed for temporary structures, such as the contractor’s office, will be minimized to a practical minimum. (MM1)

All area/ Detailed design/ During construction/ During operation

WSD/ Contractor(s)

ü

ü

ü

Implemented

-

S11.10 & 11.11

At the detailed design stage, the design team will seek to minimize the landscape footprint of the Project and above ground facilities, while satisfying all other requirements. (MM2)

All area/ Detailed design/ During construction/ During operation

WSD/ Contractor(s)

ü

ü

ü

Implemented

-

 

EIA

Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S11.10 & 11.11

Design principles will be adopted to take into account the surrounding area, particularly Clear Water Bay Country Park behind and the nearby waterfront, with due consideration given to:

·     green roofs where practical (i.e. without equipment on the roof);

· roadside planting;

· aesthetic treatment of all structures;

· vertical greening;

· screen planting along application site; and

·     landscape enhancement with amenity planting where practical including planting along the edge (site boundary) fence with native shrubs where feasible, to reduce their visual impact and blend them into the surrounding landscape. (MM3)

All area/ Detailed design/ During construction/ During operation

WSD/ Contractor(s)

ü

ü

ü

Implemented

--

S11.10 & 11.11

All trees within the Project Site or the potential slope mitigation works area will be carefully protected during construction according to DEVB TCW No. 10/2013 – Tree Preservation (MM4)

All area/ Detailed design/ During construction/ During operation

WSD/ Contractor(s)

ü

ü

ü

Implemented after reminder

 

ETWB TCW No. 3/2006 -

Tree Preservation.

S11.10 & 11.11

No tree within the Country Park will be felled. Trees within the Site unavoidably affected by the works will be transplanted where necessary and practical. For trees that need to be felled, compensatory planting will be provided to the satisfaction of relevant Government departments.

A compensatory tree planting proposal including locations of tree compensation will be submitted to seek relevant government department’s approval, in accordance with DEVB TC(W) No. 10/2013. (MM5)

All area/ Detailed design/ During construction/ During operation

WSD/ Contractor(s)

ü

ü

ü

Implemented

 

DEVB TC(W) No. 10/2013

S11.10 & 11.11

Any slope mitigation works necessary to address natural terrain hazards, will be minimized to minimize any potential environmental impact to the Country Park e.g. soil nailing and rock stabilization will aim to avoid existing trees e.g. should any restoration of vegetation be necessary, the best planting matrix with native species will be established, with the aim of resembling the existing vegetation. (MM6)

All area/ Detailed design/ During construction/ During operation

WSD/ Contractor(s)

ü

ü

ü

N/A

 

-

 

EIA

Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S11.10 & 11.11

Dredging works for the installation of intake structures and outfall diffusers should be minimized to avoid or reduce any potential environmental impacts to as low as reasonably practicable (ALARP). The intake and outfall structures (e.g. intake openings and diffuser heads) will be prefabricated and transferred to site for installation. (MM7)

All area/ Detailed design/ During construction/ During operation

WSD/ Contractor(s)

ü

ü

ü

Implemented

 

-

S11.10 & 11.11

All night-time lighting will be reduced to a practical minimum both in terms of number of level and will be hooded and directional. (MM8) units and lux level and will be hooded and directional. (MM8)

All area/ Detailed design/ During construction/ During operation

WSD/ Contractor(s)

ü

ü

ü

Implemented

 

-

Landfill Gas Hazard

S12.7

During all works, safety procedures should be implemented to minimise the risks of fires and explosions, asphyxiation of workers and toxicity effects resulting from contact with

contaminated soil and groundwater.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

-

S12.7

During trenching and excavation as well as creation of confined spaces at near to or below ground level, precautions should be clearly laid down and rigidly Gas detection equipment and appropriate breathing apparatus should be available and used when entering confined spaces or trenches deeper than 1 meter.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

-

S12.7

The Contractor should make the workers are aware of potential hazards of working in confined spaces (any chamber, manhole or culvert which is large enough to permit access to personnel). Such work in confined spaces is controlled by the Factories and Industrial Undertakings (Confined Spaces) Regulations of the Factories and Industrial Undertakings Ordinance. Following the Safety Guide to Working in Confined Spaces ensures compliance with the above regulations.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

-

S12.7

Safety officers, specifically trained with regard to landfill gas and leachate related hazards and the appropriate actions to take in adverse circumstances, should be present on the site

throughout the works, in particular, when works are undertaken below grade.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

-

S12.7

All personnel who work on site and all visitors to the site should be made aware of the possibility of ignition of gas in the

vicinity of the works, the possible presence of contaminated water and the need to avoid physical contact with it.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

-

 

EIA

Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S12.7

Monitoring for landfill gas should be undertaken in all excavations, manholes, chambers (particularly during pipe jacking) and any confined spaces through the use of an intrinsically safe portable instrument, appropriately calibrated and capable of measuring the concentrations of methane. carbon dioxide and oxygen.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

-

S12.7

Monitoring frequency and areas to be monitored should be specified prior to commencement of groundwork, either by the Safety Officer, or by an appropriately qualified person. All measurements should be recorded and documented.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

-

S12.7

Proceed drilling with adequate care and precautions against the potential hazards which may be encountered.

All area/ Detailed design/ During construction/ During

operation

Contractor(s)

ü

ü

ü

Implemented

-

S12.7

Prior to the commencement of the site works, the drilling contractor should devise a 'method-of- working' statement covering all normal and emergency procedures (including but not limited to number of operatives, experience and special skills of operatives, normal method of operations, emergency procedures, supervisors responsibilities, storage and use of safety equipment, safety procedures and signs, barriers and guarding). The site supervisor and all operatives must be

familiar with this statement.

All area/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

-

S12.7

Where below ground service entries are necessary to the Incoming Switchgear Room, 132 kV Substation and Chlorine Store (I) and (II), the entry point should be sealed to prevent gas entry. In addition, any below grade cable trenches entering the Incoming Switchgear Room and 132 kV Substation can become the pathway for landfill gas and hence grilled metal covers should be used.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

N/A

 

-

S12.7

It is recommended regular landfill gas monitoring should be carried out at the Incoming Switchgear Room, 132 kV Substation and Chlorine Store (I) and (II). The monitoring frequency will be monthly for the first year of operation. If the monitoring results show no sign of landfill gas migration, reduce the monitoring frequency to once every six months.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

N/A

 

-

 

EIA

Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

 

Implementation Agent

Implementation Stage

Implementation status

Relevant Legislation & Guidelines

D

C

O

S12.7

The manholes and utility pits within the Project Site and along the freshwater mains. Each manhole/ utility pit should be monitored with two measurements (at mid depth and base). Each measurement should be monitored for a minimum of 10 minutes. A steady reading and peak reading should be recorded at each manhole/ utility pit and for each measurement. The need for venting the manhole/ utility pit and further monitoring will be reviewed after the initial monitoring.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

-

S12.7

All construction, operation and maintenance personnel working on-site as well as visitors should be made aware of the hazards of landfill gas and its possible presence on-site. This should be achieved through a combination of posting warning signs in prominent places and also by access to detailed information on landfill gas hazards and the designs and procedural means by which these hazards are being minimized on-site.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

-

Note: D – Design stage C – Construction O – Operation

Contract No. 13/WSD/17

Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report

 

Appendix D

 

Water Quality Monitoring Graphical Presentation

 

·             Appendix D.1 Weather Condition

·             Appendix D.2 Key Activities Carried Out During the Reporting Quarter

·             Appendix D.3 Other Factor Might Affect the Monitoring Results

 

 

Dissolved Oxygen

11

10

9

8

7

6

5

4

3

2

1

0

DO

Date

Turbidity

 

4

 

3

 

2

 

1

 

0

 

Date

 

Turb

 

Suspended Solids

 

20

18

16

14

12

10

8

6

4

2

0

 

Date

 

Date SS

 

Salinity

 

35

34

33

32

31

30

29

28

 

Date

 

Series1

 

Concentration, mg/L

Concentration, NTU

Concentration, NTU

Concentration, NTU

 

Iron

 

0.3

 

0.25

 

0.2

 

0.15

 

0.1

 

0.05

 

0

 

Date

 

Iron

 

Total Residual Chlorine

 

0.3

 

0.25

 

0.2

 

0.15

 

0.1

 

0.05

 

0

 

Date

 

TRC

Concentration, mg/L

Concentration, mg/L

Remark: The lowest detection limit of the Iron is 0.1mg/L. All result of iron monitoring are lower than the detection limit.

 

Remark: The lowest detection limit of the Total Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring are lower than the detection limit.

 

Dissolved Oxygen

 

12

 

10

 

8

 

6

 

4

 

2

 

0

 

Date

 

DO

Turbidity

 

3

 

3

 

2

 

2

 

1

 

1

 

0

 

Date

 

Turb

Suspended Solids

 

60

 

50

 

40

 

30

 

20

 

10

 

0

 

Date

 

SS

 

Salinity

 

34

34

33

33

32

32

31

31

30

 

Date

 

Sal.

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

Monitoring Location: CF

 

Iron

 

0.3

 

0.25

 

0.2

 

0.15

 

0.1

 

0.05

 

0

 

Date

 

Iron

Concentration, mg/L

Monitoring Location: CF

 

Total Residual Chlorine

 

0.3

 

0.25

 

0.2

 

0.15

 

0.1

 

0.05

 

0

 

Date

 

TRC

Concentration, mg/L

Remark: The lowest detection limit of the Iron is 0.1mg/L. All result of iron monitoring are lower than the detection limit.

 

Remark: The lowest detection limit of the Total Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring are lower than the detection limit.

DO

Action Level

Limit Level

Dissolved Oxygen

 

10

9

8

7

6

5

4

3

2

1

0

 

Date

Turbidity

 

3

 

3

 

2

 

2

 

1

 

1

 

0

 

Date

Turb

Action Level (Baseline) Limit Level (Baseline)

Suspended Solids

 

60

 

50

 

40

 

30

 

20

 

10

 

0

 

Date

SS

Action Level (Baseline) Limit Level (Baseline)

 

Salinity

 

35

 

34

 

33

 

32

 

31

 

30

 

29

 

Date

Sal.

Action Level (Baseline) Limit Level (Baseline)

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

 

Iron

 

0.35

0.3

0.25

0.2

0.15

0.1

0.05

0

 

Date

Iron

Action Level

Total Residual Chlorine

 

0.012

 

0.01

 

0.008

 

0.006

 

0.004

 

0.002

 

0

 

Date

TRC

Action Level

 

Concentration, mg/L

Concentration, mg/L

Remark: The lowest detection limit of the Iron is 0.1mg/L. All result of iron monitoring are lower than the detection limit.

 

Remark: The lowest detection limit of the Total Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring are lower than the detection limit.

DO

Action Level

Limit Level

Dissolved Oxygen

 

12

 

10

 

8

 

6

 

4

 

2

 

0

 

Date

 

Turbidity

 

3

 

3

 

2

 

2

 

1

 

1

 

0

 

Date

Turb

Action Level (Baseline) Limit Level (Baseline)

Suspended Solids

 

20

18

16

14

12

10

8

6

4

2

0

 

Date

SS

Action Level (Baseline) Limit Level (Baseline)

 

 

Salinity

 

35

 

34

 

33

 

32

 

31

 

30

 

29

 

Date

Sal.

Action Level (Baseline)

Limit Level (Baseline)

 

 

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

 

Iron

 

0.35

0.3

0.25

0.2

0.15

0.1

0.05

0

 

Date

Iron

Action Level

Total Residual Chlorine

 

0.012

 

0.01

 

0.008

 

0.006

 

0.004

 

0.002

 

0

 

Date

TRC

Action Level

 

Concentration, mg/L

Concentration, mg/L

Remark: The lowest detection limit of the Iron is 0.1mg/L. All result of iron monitoring are lower than the detection limit.

 

Remark: The lowest detection limit of the Total Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring are lower than the detection limit.

 

DO

Action Level

Limit Level

Dissolved Oxygen

 

12

 

10

 

8

 

6

 

4

 

2

 

0

 

Date

Suspended Solids

 

18

16

14

12

10

8

6

4

2

0

 

Date

SS

Action Level (Baseline)

Limit Level (Baseline)

 

 

 

Turbidity

 

3

 

3

 

2

 

2

 

1

 

1

 

0

 

Date

Turb

Action Level (Baseline) Limit Level (Baseline)

Salinity

 

35

 

34

 

33

 

32

 

31

 

30

 

29

 

Date

Sal.

Action Level (Baseline) Limit Level (Baseline)

 

 

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

 

Iron

 

0.35

0.3

0.25

0.2

0.15

0.1

0.05

0

 

Date

Iron

Action Level

Total Residual Chlorine

 

0.35

0.3

0.25

0.2

0.15

0.1

0.05

0

 

Date

Iron

Action Level

 

Concentration, mg/L

Concentration, mg/L

Remark: The lowest detection limit of the Iron is 0.1mg/L. All result of iron monitoring are lower than the detection limit.

 

Remark: The lowest detection limit of the Total Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring are lower than the detection limit.

 

 

DO

Action Level

Limit Level

Dissolved Oxygen

 

12

 

10

 

8

 

6

 

4

 

2

 

0

 

Date

Turbidity

 

3

 

3

 

2

 

2

 

1

 

1

 

0

 

Date

Turb

Action Level (Baseline)

Limit Level (Baseline)

Suspended Solids

 

18

16

14

12

10

8

6

4

2

0

 

Date

SS

Action Level (Baseline) Limit Level (Baseline)

 

 

Salinity

 

35

34

33

32

31

30

29

28

 

Date

Sal.

Action Level (Baseline) Limit Level (Baseline)

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

 

Iron

 

0.35

0.3

0.25

0.2

0.15

0.1

0.05

0

 

Date

Iron

Action Level

Total Residual Chlorine

 

0.012

 

0.01

 

0.008

 

0.006

 

0.004

 

0.002

 

0

 

Date

TRC

Action Level

 

Concentration, mg/L

Concentration, mg/L

Remark: The lowest detection limit of the Iron is 0.1mg/L. All result of iron monitoring are lower than the detection limit.

 

Remark: The lowest detection limit of the Total Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring are lower than the detection limit.

 

DO

Action Level

Limit Level

Dissolved Oxygen

 

10

9

8

7

6

5

4

3

2

1

0

 

Date

Turbidity

 

3

 

3

 

2

 

2

 

1

 

1

 

0

 

Date

Turb

Action Level (Baseline)

Limit Level (Baseline)

Suspended Solids

 

18

16

14

12

10

8

6

4

2

0

 

Date

SS

Action Level (Baseline)

Limit Level (Baseline)

 

 

 

Salinity

 

35

34

33

32

31

30

29

28

 

Date

Sal.

Action Level (Baseline) Limit Level (Baseline)

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

 

Iron

 

0.35

0.3

0.25

0.2

0.15

0.1

0.05

0

 

Date

Iron

Action Level

Total Residual Chlorine

 

0.012

 

0.01

 

0.008

 

0.006

 

0.004

 

0.002

 

0

 

Date

TRC

Action Level

 

Concentration, mg/L

Concentration, mg/L

Remark: The lowest detection limit of the Iron is 0.1mg/L. All result of iron monitoring are lower than the detection limit.

 

Remark: The lowest detection limit of the Total Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring are lower than the detection limit.

DO

Action Level

Limit Level

Dissolved Oxygen

 

10

9

8

7

6

5

4

3

2

1

0

 

Date

Turbidity

 

3

 

3

 

2

 

2

 

1

 

1

 

0

 

Date

Turb

Action Level (Baseline)

Limit Level (Baseline)

Suspended Solids

 

16

14

12

10

8

6

4

2

0

 

Date

SS

 

Action Level (Baseline)

 

Limit Level (Baseline)

 

 

Salinity

 

35

 

34

 

33

 

32

 

31

 

30

 

29

 

Date

Sal.

Action Level (Baseline)

Limit Level (Baseline)

 

 

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

 

Iron

 

0.35

0.3

0.25

0.2

0.15

0.1

0.05

0

 

Date

Iron

Action Level

Total Residual Chlorine

 

0.012

 

0.01

 

0.008

 

0.006

 

0.004

 

0.002

 

0

 

Date

TRC

Action Level

 

Concentration, mg/L

Concentration, mg/L

Remark: The lowest detection limit of the Iron is 0.1mg/L. All result of iron monitoring are lower than the detection limit.

 

Remark: The lowest detection limit of the Total Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring are lower than the detection limit.

 

DO

Action Level

Limit Level

Dissolved Oxygen

 

12

 

10

 

8

 

6

 

4

 

2

 

0

 

Date

Turbidity

 

3

 

3

 

2

 

2

 

1

 

1

 

0

 

Date

Turb

Action Level (Baseline)

Limit Level (Baseline)

Suspended Solids

 

20

18

16

14

12

10

8

6

4

2

0

 

Date

SS

Action Level (Baseline) Limit Level (Baseline)

 

 

 

Salinity

 

35

 

34

 

33

 

32

 

31

 

30

 

29

 

Date

Sal.

Action Level (Baseline)

Limit Level (Baseline)

 

 

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

 

Iron

 

0.35

0.3

0.25

0.2

0.15

0.1

0.05

0

 

Date

Iron

Action Level

Total Residual Chlorine

 

0.012

 

0.01

 

0.008

 

0.006

 

0.004

 

0.002

 

0

 

Date

TRC

Action Level

 

Concentration, mg/L

Concentration, mg/L

Remark: The lowest detection limit of the Iron is 0.1mg/L. All result of iron monitoring are lower than the detection limit.

 

Remark: The lowest detection limit of the Total Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring are lower than the detection limit.

 

DO

Action Level

Limit Level

Dissolved Oxygen

 

10

9

8

7

6

5

4

3

2

1

0

 

Date

Turbidity

 

3

 

3

 

2

 

2

 

1

 

1

 

0

 

Date

Turb

Action Level (Baseline)

Limit Level (Baseline)

Suspended Solids

 

20

18

16

14

12

10

8

6

4

2

0

 

Date

SS

Action Level (Baseline)

Limit Level (Baseline)

 

 

 

Salinity

 

35

34

33

32

31

30

29

28

 

Date

Sal.

Action Level (Baseline)

Limit Level (Baseline)

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

Monitoring Location: WSR37

 

Iron

 

0.35

0.3

0.25

0.2

0.15

0.1

0.05

0

 

Date

Iron

Action Level

Total Residual Chlorine

 

0.12

 

0.1

 

0.08

 

0.06

 

0.04

 

0.02

 

0

 

Date

TRC

Action Level

 

Concentration, mg/L

Remark: The lowest detection limit of the Iron is 0.1mg/L. All result of iron monitoring are lower than the detection limit.

 

Remark: The lowest detection limit of the Total Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring are lower than the detection limit.

 

DO

Action Level

Limit Level

Dissolved Oxygen

 

10

9

8

7

6

5

4

3

2

1

0

 

Date

Turbidity

 

3

 

3

 

2

 

2

 

1

 

1

 

0

 

Date

Turb

Action Level (Baseline) Limit Level (Baseline)

Suspended Solids

 

18

16

14

12

10

8

6

4

2

0

 

Date

SS

Action Level (Baseline)

Limit Level (Baseline)

 

 

Salinity

 

35

34

33

32

31

30

29

28

 

Date

Sal.

Action Level (Baseline) Limit Level (Baseline)

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

 

The lowest detection limit of the Iron is 0.1mg/L. All result of iron monitoring are lower than the detection limit.

Iron

 

0.35

0.3

0.25

0.2

0.15

0.1

0.05

0

 

Date

Iron

Action Level

Total Residual Chlorine

 

0.12

 

0.1

 

0.08

 

0.06

 

0.04

 

0.02

 

0

 

Date

TRC

Action Level

 

Concentration, mg/L

Concentration, mg/L

Remark:

 

Remark: The lowest detection limit of the Total Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring are lower than the detection limit.

 

DO

Action Level

Limit Level

Dissolved Oxygen

 

10

9

8

7

6

5

4

3

2

1

0

 

Date

Turbidity

 

3

 

3

 

2

 

2

 

1

 

1

 

0

 

Date

Turb

Action Level (Baseline) Limit Level (Baseline)

Suspended Solids

 

18

16

14

12

10

8

6

4

2

0

 

Date

SS

Action Level (Baseline)

Limit Level (Baseline)

 

 

Salinity

 

35

 

34

 

33

 

32

 

31

 

30

 

29

 

Date

Sal.

Action Level (Baseline) Limit Level (Baseline)

 

 

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

 

Iron

 

0.35

0.3

0.25

0.2

0.15

0.1

0.05

0

 

Date

Iron

Action Level

Total Residual Chlorine

 

0.12

 

0.1

 

0.08

 

0.06

 

0.04

 

0.02

 

0

 

Date

TRC

Action Level

 

Concentration, mg/L

Concentration, mg/L

Remark: The lowest detection limit of the Iron is 0.1mg/L. All result of iron monitoring are lower than the detection limit.

 

Remark: The lowest detection limit of the Total Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring are lower than the detection limit.

DO

Action Level

Limit Level

Dissolved Oxygen

 

12

 

10

 

8

 

6

 

4

 

2

 

0

 

Date

Turbidity

 

3

 

3

 

2

 

2

 

1

 

1

 

0

 

Date

Turb

Action Level (Baseline) Limit Level (Baseline)

Suspended Solids

 

20

18

16

14

12

10

8

6

4

2

0

 

Date

SS

Action Level (Baseline)

Limit Level (Baseline)

 

 

Salinity

 

35

 

34

 

33

 

32

 

31

 

30

 

29

 

Date

Sal.

Action Level (Baseline)

Limit Level (Baseline)

 

 

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

 

The lowest detection limit of the Iron is 0.1mg/L. All result of iron monitoring are lower than the detection limit.

Iron

 

0.35

0.3

0.25

0.2

0.15

0.1

0.05

0

 

Date

Iron

Action Level

Total Residual Chlorine

 

0.12

 

0.1

 

0.08

 

0.06

 

0.04

 

0.02

 

0

 

Date

TRC

Action Level

 

Concentration, mg/L

Concentration, mg/L

Remark:

 

Remark: The lowest detection limit of the Total Residual Chlorine is 0.01mg/L. All result of Total Residual Chlorine monitoring are lower than the detection limit.

Salinity

 

80

70

60

50

40

30

20

10

0

 

Month

 

Sal (ppt) Limit Level

 

 

 

pH

 

14

13

12

11

10

9

8

7

6

5

4

3

2

1

 

Month

pH

Limit Level

 

 

 

Temperature

 

45

40

35

30

25

20

15

10

5

0

 

Month

 

Temp (°C) Limit Level

 

 

 

pH

Concentration, mg/L

Temp (°C)

Total Residual Chlorine

 

0.16

0.14

0.12

0.10

0.08

0.06

0.04

0.02

0.00

 

Month

Total Residual Chlorine (mg/L)

Limit Level

 

 

 

Suspended Solids

 

15

14

13

12

11

10

9

8

7

6

5

4

3

2

1

0

 

Month

Suspended Solids (mg/L)

 

Limit Level

 

 

 

Total Inorganic Nitrogen

 

2.2

2.0

1.8

1.6

1.4

1.2

1.0

0.8

0.6

0.4

0.2

0.0

 

Month

Total Inorganic Nitrogen (mg/L)

Limit Level

 

 

 

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

 

Total Phosphorus

 

1.20

1.10

1.00

0.90

0.80

0.70

0.60

0.50

0.40

0.30

0.20

0.10

0.00

 

Month

Total Phosphorus (mg/L)

 

Limit Level

 

 

 

Sodium Metabisulphite

 

5.00

4.50

4.00

3.50

3.00

2.50

2.00

1.50

1.00

0.50

0.00

 

Month

Sodium Metabisulphite (mg/L)

Limit Level

 

 

 

Iron

(mg/L)

Limit Level

Iron

 

1.00

0.90

0.80

0.70

0.60

0.50

0.40

0.30

0.20

0.10

0.00

 

Month

 

 

 

Concentration, mg/L

Concentration, mg/L

Concentration, mg/L

Remark: Due to the limitation of the laboratory, the lowest result for Sodium Metabisulphite will only be shown as < 2 mg/L.

 

Appendix D.1 Weather Condition

 

 

flI081

33.0

 

28.1

26.5

 

S7

Trace

vs

 

S.7

02

Â0L6

342

30.6

28.4

26.2

78

50

Trace

8.4

160

43

03

JtI061

33.S

 

25.5

258

78

85

3vs

8.3

180

#.5

04

10023

32.5

29.7

26.5

24.7

75

 

0.6

7.1

070

 

05

999.5

33.4

304

26.2

24.5

 

 

21.5

4.3

050

53.8

06

1001.6

268

276

259

25.7

 

95

84.1

0.0

070

56.8

07

JtI071

09

 

2L9

26.9

 

 

5.8

25

 

 

08

Â08.6

30.1

28.2

27.3

26.5

91

 

37.8

2.3

080

16.3

09

1007.7

30.0

27.8

26.3

25.g

 

83

13.0

3.0

080

11.7

10

Â073

33.3

294

26.8

24.8

 

60

0.0

1¥.0

080

9.9

 

flI081

34.3

304

28.2

25.4

 

SI

0.0

 

040

6.7

12

10070

322

296

27.7

25.1

 

55

0.0

9.8

230

4.s

13

1005.1

34.5

304

28.2

24.9

 

 

0.1

\ 0.8

070

7.3

14

Â028

33.5

29.2

26.7

24.4

76

 

5L2

5.8

 

5.4

15

10023

31.7

29.3

2L4

24.6

 

 

24

6.9

Zb0

6.4

16

10040

06

28.5

258

24.8

81

85

27.4

4.1

050

25.1

17

1004.1

35.7

30.8

26.3

25.5

 

76

UO

9.9

040

20.6

18

JtI039

32.8

29.7

26.8

24.3

 

 

Trace

8.4

070

 

19

Â032

33.6

 

28.7

252

7S

 

0.0

9.4

070

264

20

Â032

32.6

296

27.p

25.7

 

 

4.6

5.7

050

12.4

 

10035

28.8

2T.7

25.7

258

 

 

72.9

0.1

080

¥09

22

1005.8

30.1

27.¥

244

24.8

 

91

32d

0.0

Z60

22.6

23

JtI090

28.0

25.7

23.4

23.9

 

90

24.9

os

 

23.3

Â¥0.6

28.2

26.7

25.2

252

91

89

75.0

1.0

190

11.7

25

1011.2

31.4

28.5

26.9

252

 

73

5.'Æ

 

240

11.0

26

1011.2

31.6

294

27.p

25.1

78

39

0.0

10.3

250

16.4

27

10¥0.1

Z2.4

29.9

28.1

25.g

 

41

0.0

\ 0.6

250

20.6

2B

Â092

32.1

29d

27.5

25.4

 

 

1.3

5.7

080

16.8

29

flI08.6

31.8

 

26.6

24.4

 

 

3.3

9.2

 

8.0

30

1005.5

33.3

305

27.9

24.4

71

61

0.0

ss

280

¥3.2

JtI061

Z2.0

 

2&8

252

 

 

520.9

190.5

080

17.2

 

 

 

Normal’

30.5

279

26Ù

23.6 78

321.4

174.4

080

21.4

 

Information of wind direction and wind speed for Waglan Island are based on autarriafic weather sfaôan dafa since August 1989

Traœ means rainfall less than mm

? 1991-2020 Climatotogical Nonnat. unless otherwise specified

 

 

 

 

 

 

 

 

 

 

 

 

 

1005.2

34.2

à0.9

27.8

2t6

 

 

0.0

8.4

350

 

02

10099

308

274

25.5

 

75

0.0

9.S

J50

40.2

03

1013.2

29.#

26¥

23.J

14.6

 

 

0.0

10.5

 

33.4

04

1014. 4

30.9

270

246

50

69

0.0

6.6

J60

18.8

OS

 

31.5

279

25.5

20.0

 

80

0.0

6.9

 

20.0

06

1013.7

33.3

29.2

26?'

70

42

0.0

10.5

080

14.0

07

1014.4

32.9

293

27.J

222

 

60

0.0

zs

080

10. 4

08

1014.2

31.7

262

262

 

J5

0.0

9.2

J60

2#.B

09

1013.5

27.#

26. 4

25.2

20.1

 

8J

Trace

05

010

22.B

 

1013.0

30.6

270

2%5

 

58

Trace

6.0

080

19.2

11

 

27/5

25.3

23.2

21.0

 

 

 

080

216

¥2

1015.1

29.7

270

25.6

202

67

31

0.0

10.7

080

31.3

13

1014.5

302

275

25.9

222

 

65

0.0

9.4

070

29.5

¥4

1013.5

31.0

260

26.3

34

0.0

9.9

080

24.0

as

 

09

28¥

26.6

230

75

 

0.0

 

080

22.7

 

1014.5

31.1

262

27.4

74

88

Trace

5.3

080

339

17

 

297

278

27.1

230

 

85

Trace

19

080

320

 

1013.2

30.7

263

27?

78

85

Trace

6.6

080

19.3

19

1014.1

33.7

292

26.4

23.9

74

43

0.0

9.6

080

0.1

20

1016.5

29.7

279

26.9

75

 

1.9

3.4

080

39.8

1015.0

31.5

278

26.4

229

75

69

Trace

4.0

080

25.0

22

1013.7

32.J

263

26.0

 

52

0.0

10.0

J60

2'$2

23

1012.4

26#

25.7

23.4

16.4

57

81

0.0

83

 

40.5

10092

28.5

24.8

22.0

06

42

84

0.0

10.0

J60

39.2

2S

1006.7

29.#

260

22.9

13.2

 

 

0.0

8.4

 

38.4

26

10066

28.5

26.6

25.3

19g

67

88

0.7

0.7

050

41.9

27

1009.3

29.2

27.3

25.9

220

 

 

Trace

J.3

050

2?0

28

1010.1

27.2

258

246

192

67

83

Trace

0.3

J60

26.3

29

011.1

267

25.3

23.7

19.1

 

 

Trace

1.7

040

19.0

 

1010.3

29.J

26.2

243

 

70

0.0

7.8

J60

15.3

 

1006.0

306

27.1

24.1

16.4

52

41

0.0

10.4

 

23.1

 

1012.2

30.J

27.3

25.4

65

69

11.3

209.1

080

26.6

CIima1oIogicaI Normal'

 

1014.0

28.1

25.7

23.9

20.2

 

 

 

120.3

 

197.8

080

26.3

 

^ 1.rilo.'melon of s'iind directionmind mind speed io.• WoQlo.ri !zland ale based o.ri oulom at.'c iveatùe.• stolioin date a.'rice Auquel 1989 Traœ means rainfall less than 0.OS mm

* 1991-2020 Glimd °!°9'*6l No.'mol. einlezs oihenv.'se Apec.'ted

 

01

1009.7

e.6

26.8

240

17.2

 

 

0.0

\0.3

"**

°**

OZ

1016.3

216

251

22.9

17.8

 

76

0.0

4.3

”’

’*’

03

1017.1

2R2

26.0

246

207

 

 

0.0

43

04

1016.9

29.0

26.Z

248

21.4

75

 

 

7.0

”’

’*’

05

Â178

2R2

26.0

24.1

19.2

67

 

Trace

6.8

06

flI18.9

28.0

250

213

17.6

 

 

 

6.4

07

flI19.4

27.0

23.9

22.3

13.8

 

31

Trace

9.8

08

1016.6

2K3

24.1

2R9

12.4

 

B2

0.0

09

1014.5

27.9

25J

234

18.2

 

 

1.9

2.7

10

10148

264

249

2B.4

21.1

 

 

 

R0

11

1044

26.3

24.9

240

206

 

 

0.0

IZ

1012.3

294

259

213

21.1

75

 

0.0

9.9

°””

“”*

13

1010.1

26.2

250

23.2

21.7

 

 

14.8

0.3

"**

°**

14

1009.6

256

248

2B2

22.7

 

 

6.3

R0

15

 

25¥

24J

23.5

23.2

 

 

36.6

16

1011.7

219

255

23.G

23.2

 

 

33.3

1.5

°””

“”*

17

1044

26.2

24.3

22.9

D.2

 

 

6.1

3.2

"*”

°”*

18

tg16.8

25.5

24Z

212

19.1

 

 

 

3.2

19

1018.6

23.2

201

184

17.0

 

97

7.3

0.0

20

 

18.6

18.1

 

J7.2

 

 

73.8

R0

21

1018.2

21.¥

 

17.9

16.7

 

 

5.6

0.4

"*”

°”*

 

flI18.9

22.6

2RZ

18.8

15.4

74

70

 

3.7

°””

“”*

23

4tf20.0

22.5

204

184

is.o

 

 

Trace

1.8

”’

”’

1019.5

210

 

21.4

19.8

16.5

74

 

1.0

o.s

-

-

25

flI18.4

23.5

 

21.1

18.2

 

 

Trace

0.6

"**

°**

26

11119.0

2B.4

2R8

18.7

13.1

 

 

 

9.8

°””

“”*

27

10208

21.5

 

17.0

6.7

 

 

0.0

9.8

28

1022.0

21.5

IRZ

HQ

 

 

 

0.0

9.8

°””

“”*

29

1020.9

21.2

18.8

16.6

2J

 

32

0.0

9.8

30

1017.7

22.0

19.0

is.s

9.8

 

21

0.0

9.8

Mean/TtXaI

flI16.4

253

23.0

21.3

16.8

 

71

 

 

 

24.5

 

22.Z

 

2R3

 

16.7

 

 

 

39.3

 

070

 

Z6.6

 

unavai//e

lnfonnation of wind direction and wind speed for Waglan lsland are baœd on au/ornafic weafùer sfaôan dafa since August 1989

Traœ rrieans rairifall less than mm

? 1991-2020 C//mafo/opica/ Norma/. on/ess ofherusse specifiecî

 

Appendix D.2

Key Activities Carried Out During the Reporting Quarter

September 2024

 

All Area

·           Security Fence footing construction work

·           Footpath Construction

·           Landscape Construction

·           Irrigation System Construction

·           Water Pressure Test for FS and PL system

·           Landscape planting work

·           Traffic signage work

·           E&M Works and Mechanical Installation

PWST

·           Water Test in Tank A

·           Waterproofing work at Roof Slab on Tank A

·           Installation of building services, electrical switchboards and cables

·           Installation of mechanical equipment, steel pipe, Pressure Test

Administration Building

·           External wall aluminum features installation

·           Finishing works for dog house

·           Minor Installation of building services, electrical switchboards & cables, Pressure Test, T&C

Chemical building

·           Defect rectification

·           Repairing the defects inside the dangerous store

Combined Shaft & Pump House

·           Internal finishing, defect rectification

·           Construction of hose reel cabinet

·           T&C

ActiDAFF

·           Installation of access opening covers for filtered water tank

·           Carrying out finishing works for staircase no. 3.

·           Minor Installation of mechanical equipment, piping system

·           Minor Installation of building services, electrical switchboards and cables, Installation of FRP Enclosure System

Product Water Storage Tank Building

·           Minor Installation of building services, cable laying and termination, PV Panel Installation, Testing & Commissioning

OSCG Building

·           Protective Coating for DG Rooms

·           Installation of Railing on Brine Maker Tank

·           Minor Installation of building services, cables and pipe works, T&C

·           Tank surface cleaning, T&C

 

Reverse Osmosis Building

·           Installation of Signage, AP doors, sanitary fitting, sanitary ware in toilet, tiling work and water meter cabinets

·           Minor Installation of building services, minor cable laying and termination,

Testing & Commissioning, PV Panel Installation

Post Treatment Building

·           Installation of Cat Ladders in Water Tanks

·           Placing Soil Mix at Roof

·           Curb Construction for Rescue Opening at Water Tanks

·           Installation of building services, piping system, mechanical equipment and piping system, Pressure Test

Inspection gallery

·           Construction of roof tiling works

·           Installation of steel balustrade at roof

·           Installation of movement joints

·           Construction of block works

·           Minor Installation of building service, T&C

RO and Electrical Building

·           Installation of Glass House

·           Minor Installation of building services, electrical switchboards and cables

·           Minor Installation of mechanical pipework and raised Floor,

·           PV Panel Installation, T&C

Chiller plant & Main Electrical Building

·           Minor Installation of building services, electrical switchboards and cables, Pressure Test, T&C

Others

·            Slope works

·            Construction works of extended access road

October 2024

All Area

·           Security Fence footing construction work

·           Footpath Construction

·           Landscape Construction

·           Irrigation System Construction

·           Water Pressure Test for FS and PL system

·           Landscape planting work

·           Traffic signage work

·           E&M Works and Mechanical Installation

PWST

·           Water Test in Tank A

·           Waterproofing work at Roof Slab on Tank A

·           Installation of building services, electrical switchboards and cables

·           Installation of mechanical equipment, steel pipe, Pressure Test

Administration Building

·           External wall aluminum features installation

·           Finishing works for dog house

·           Minor Installation of building services, electrical switchboards & cables, Pressure Test, T&C

Chemical building

·           Defect rectification

·           Repairing the defects inside the dangerous store

Combined Shaft & Pump House

·           Internal finishing, defect rectification

·           Construction of hose reel cabinet

·           T&C

ActiDAFF

·           Installation of access opening covers for filtered water tank

·           Carrying out finishing works for staircase no. 3.

·           Minor Installation of mechanical equipment, piping system

·           Minor Installation of building services, electrical switchboards and cables, Installation of FRP Enclosure System

Product Water Storage Tank Building

·           Minor Installation of building services, cable laying and termination, PV Panel Installation, Testing & Commissioning

OSCG Building

·           Protective Coating for DG Rooms

·           Installation of Railing on Brine Maker Tank

·           Minor Installation of building services, cables and pipe works, T&C

·           Tank surface cleaning, T&C

 

Reverse Osmosis Building

·           Installation of Signage, AP doors, sanitary fitting, sanitary ware in toilet, tiling work and water meter cabinets

·           Minor Installation of building services, minor cable laying and termination,

Testing & Commissioning, PV Panel Installation

Post Treatment Building

·           Installation of Cat Ladders in Water Tanks

·           Placing Soil Mix at Roof

·           Curb Construction for Rescue Opening at Water Tanks

·           Installation of building services, piping system, mechanical equipment and piping system, Pressure Test

Inspection gallery

·           Construction of roof tiling works

·           Installation of steel balustrade at roof

·           Installation of movement joints

·           Construction of block works

·           Minor Installation of building service, T&C

RO and Electrical Building

·           Installation of Glass House

·           Minor Installation of building services, electrical switchboards and cables

·           Minor Installation of mechanical pipework and raised Floor,

·           PV Panel Installation, T&C

Chiller plant & Main Electrical Building

·           Minor Installation of building services, electrical switchboards and cables, Pressure Test, T&C

Others

·            Slope works

·            Construction works of extended access road

November 2024

All Area

·           Security Fence footing construction work

·           Footpath Construction

·           Landscape Construction

·           Irrigation System Construction

·           Water Pressure Test for FS and PL system

·           Landscape planting work

·           Traffic signage work

·           E&M Works and Mechanical Installation

PWST

·           Water Test in Tank A

·           Waterproofing work at Roof Slab on Tank A

·           Installation of building services, electrical switchboards and cables

·           Installation of mechanical equipment, steel pipe, Pressure Test

Administration Building

·           External wall aluminum features installation

·           Finishing works for dog house

·           Minor Installation of building services, electrical switchboards & cables, Pressure Test, T&C

Chemical building

·           Defect rectification

·           Repairing the defects inside the dangerous store

Combined Shaft & Pump House

·           Internal finishing, defect rectification

·           Construction of hose reel cabinet

·           T&C

ActiDAFF

·           Installation of access opening covers for filtered water tank

·           Carrying out finishing works for staircase no. 3.

·           Minor Installation of mechanical equipment, piping system

·           Minor Installation of building services, electrical switchboards and cables, Installation of FRP Enclosure System

Product Water Storage Tank Building

·           Minor Installation of building services, cable laying and termination, PV Panel Installation, Testing & Commissioning

OSCG Building

·           Protective Coating for DG Rooms

·           Installation of Railing on Brine Maker Tank

·           Minor Installation of building services, cables and pipe works, T&C

·           Tank surface cleaning, T&C

 

Reverse Osmosis Building

·           Installation of Signage, AP doors, sanitary fitting, sanitary ware in toilet, tiling work and water meter cabinets

·           Minor Installation of building services, minor cable laying and termination,

Testing & Commissioning, PV Panel Installation

Post Treatment Building

·           Installation of Cat Ladders in Water Tanks

·           Placing Soil Mix at Roof

·           Curb Construction for Rescue Opening at Water Tanks

·           Installation of building services, piping system, mechanical equipment and piping system, Pressure Test

Inspection gallery

·           Construction of roof tiling works

·           Installation of steel balustrade at roof

·           Installation of movement joints

·           Construction of block works

·           Minor Installation of building service, T&C

RO and Electrical Building

·           Installation of Glass House

·           Minor Installation of building services, electrical switchboards and cables

·           Minor Installation of mechanical pipework and raised Floor,

·           PV Panel Installation, T&C

Chiller plant & Main Electrical Building

·           Minor Installation of building services, electrical switchboards and cables, Pressure Test, T&C

Others

·            Construction works of extended access road

 

Appendix D.3

Other Factor Might Affect the Monitoring Results

Other Factors might affect the monitoring results

Reporting Period

Aug 2024

Sep 2024

Oct 2024

Nov 2024

N/A

N/A

N/A

N/A

 

Appendix E

 

Summary of Exceedances

Table E1 Summary of Exceedance in Sep 2024

Date of exceedance

Monitoring Station

Tide

SS Level (mg/L)

Action Level

Limit Level

 

07/09/2024

WSR33

Flood

5.33

Y

N

WSR36

5.33

Y

N

NF1

5.33

Y

N

12/09/2024

WSR4

Ebb

5.08

Y

N

NF1

5.17

Y

N

14/09/2024

WSR3

Ebb

3.67

Y

N

NF2

4.17

Y

Y

 

17/09/2024

WSR3

 

Ebb

4.83

Y

N

WSR4

6.17

Y

Y

WSR16

5.83

Y

Y

WSR36

4.67

Y

N

WSR37

4.67

Y

N

 

19/09/2024

WSR4

 

Ebb

4.50

Y

Y

WSR33

5.67

Y

Y

WSR36

5.50

Y

Y

WSR37

5.17

Y

Y

NF1

6.17

Y

Y

NF2

5.67

Y

Y

NF3

5.17

Y

Y

21/09/2024

WSR3

Flood

4.25

Y

Y

24/09/2024

WSR37

Flood

4.75

Y

Y

26/09/2024

WSR37

Ebb

4.42

Y

Y

NF3

4.42

Y

Y

 

28/09/2024

WSR2

 

Ebb

3.42

Y

N

WSR3

3.83

Y

Y

WSR4

3.33

Y

N

WSR36

4.50

Y

Y

WSR37

5.50

Y

Y

NF1

4.67

Y

Y

NF2

4.50

Y

Y

NF3

5.83

Y

Y

Table E2 Summary of Exceedance in Oct 2024

Date

Station

Tide

SS Level (mg/L)

Action Level

Limit Level

03/10/2024

NF1

Ebb

4.67

Y

Y

NF2

3.75

Y

Y

 

05/10/2024

WSR1

 

Flood

6.67

Y

Y

WSR2

5.17

Y

N

WSR3

5.58

Y

Y

WSR4

7.83

Y

Y

WSR16

6.50

Y

Y

WSR33

7.00

Y

Y

WSR36

5.5

Y

Y

NF1

5.33

Y

N

10/10/2024

NF1

Ebb

3.50

Y

N

12/10/2024

WSR16

Ebb

4.83

Y

N

 

15/10/2024

WSR1

Ebb

4.75

Y

N

WSR33

5.67

Y

Y

NF2

4.58

Y

N

17/10/2024

NF3

Ebb

5.17

Y

N

19/10/2024

WSR1

Flood

52.67

Y

N

WSR2

18.67

Y

N

 

22/10/2024

WSR4

 

Flood

3.25

Y

N

WSR16

4.08

Y

Y

WSR33

3.50

Y

Y

WSR37

3.33

Y

Y

NF2

3.25

Y

Y

 

24/10/2024

WSR1

 

Ebb

10.00

Y

Y

WSR2

8.67

Y

N

WSR3

10.67

Y

Y

WSR4

11.00

Y

Y

WSR16

7.75

Y

N

WSR33

6.83

Y

N

WSR36

6.08

Y

N

WSR37

8.00

Y

N

NF1

10.67

Y

Y

NF2

8.83

Y

N

NF3

7.00

Y

N

 

26/10/2024

WSR1

 

Ebb

4.92

Y

Y

WSR2

5.17

Y

Y

WSR4

4.58

Y

Y

WSR16

5.42

Y

Y

WSR37

4.42

Y

Y

NF2

4.08

Y

Y

 

29/10/2024

WSR1

Ebb

4.83

Y

Y

WSR2

4.83

Y

Y

WSR4

6.83

Y

Y

WSR16

6.00

Y

Y

 

31/10/2024

WSR16

Ebb

4.00

Y

Y

WSR33

4.50

Y

Y

WSR36

3.92

Y

Y

NF1

4.17

Y

Y

Table E3 Summary of Exceedance in Nov 2024

 

Date of exceedance

Monitoring Station

Tide

SS Level (mg/L)

Action Level

Limit Level

 

02/11/2024

WSR2

 

Ebb

4.67

Y

N

WSR4

5.17

Y

Y

WSR16

6.17

Y

Y

WSR33

6.17

Y

Y

WSR36

7.00

Y

Y

WSR37

7.33

Y

Y

NF1

4.83

Y

Y

NF2

4.75

Y

Y

 

05/11/2024

WSR2

 

Flood

4.83

Y

Y

WSR3

3.58

Y

Y

WSR4

3.83

Y

Y

WSR16

4.58

Y

Y

WSR37

4.33

Y

Y

NF1

3.50

Y

Y

NF2

4.42

Y

Y

 

7/11/2024

WSR4

 

Ebb

3.75

Y

Y

WSR16

4.08

Y

Y

WSR33

4.42

Y

Y

WSR36

4.75

Y

Y

WSR37

3.75

Y

Y

9/11/2024

WSR37

Ebb

3.42

Y

Y

 

16/11/2024

WSR1

 

Ebb

6.00

Y

N

WSR3

6.83

Y

Y

WSR16

6.83

Y

Y

WSR37

7.00

Y

Y

NF2

6.33

Y

Y

NF3

6.83

Y

Y

23/11/2024

NF3

Ebb

5.42

Y

Y

 

26/11/2024

WSR16

 

Ebb

3.92

Y

N

WSR36

3.83

Y

N

WSR37

4.58

Y

Y

NF2

3.75

Y

N

NF3

3.83

Y

N

28/11/2024

WSR37

Ebb

4.08

Y

N

 

30/11/2024

WSR1

 

Ebb

3.50

Y

Y

WSR3

3.42

Y

Y

WSR16

4.33

Y

Y

WSR33

3.25

Y

Y

WSR36

3.92

Y

Y

WSR37

7.17

Y

Y

NF1

4.33

Y

Y

NF2

9.00

Y

Y

NF3

4.08

Y

Y

 

 

Contract No. 13/WSD/17

Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report

 

Appendix F Waste Flow Table

Contract No. 13/WSD/17

Environmental Management Plan for Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant

 

Appendix F - Monthly Summary Waste Flow Table

 

Name of Department: WSD Contract No.: 13/WSD/17

 

Monthly Summary Waste Flow Table for 2024 (year)

 

Month

Actual Quantities of Inert C&D Materials Generated Monthly

Actual Quantities of C&D Wastes Generated Monthly

Total Quantity Generated

Hard Rock and Large Broken Concrete

Reused in the Contract

Reused in other Projects

Disposed as Public Fill

 

Imported Fill

 

Metals

Paper/ cardboard packaging

Plastics

(see Note 3)

 

Chemical Waste

Others, e.g. general refuse

(in '000kg)

(in '000kg)

(in '000kg)

(in '000kg)

(in '000kg)

(in '000kg)

(in '000 kg)

(in '000kg)

(in '000kg)

(in '000kg)

(in '000kg)

Jan

4978.345

0.000

0.000

4667.745

310.600

0.000

0.000

0.000

0.000

0.000

77.800

Feb

22561.796

0.000

0.000

21883.006

678.790

0.000

0.000

0.000

0.000

0.000

53.480

Mar

81.140

0.000

0.000

0.000

81.140

0.000

0.000

0.000

0.000

0.000

52.260

Apr

57.130

0.000

0.000

0.000

57.130

0.000

0.000

0.000

0.000

0.000

47.390

May

91.370

0.000

0.000

0.000

91.370

0.000

0.000

0.000

0.000

0.000

77.260

Jun

49.190

0.000

0.000

0.000

49.190

0.000

0.000

0.000

0.002

0.000

60.780

Sub-total

27818.971

0.000

0.000

26550.751

1268.220

0.000

0.000

0.000

0.002

0.000

368.970

Jul

60378.440

0.000

0.000

0.000

60378.440

0.000

0.000

0.000

0.000

0.000

42.820

Aug

57.390

0.000

0.000

0.000

57.390

0.000

0.000

0.000

0.000

2.460

33.980

Sep

834.890

0.000

0.000

0.000

834.890

0.000

0.000

0.000

0.000

0.805

27.020

Oct

78.140

0.000

0.000

0.000

78.140

0.000

0.000

0.000

0.000

0.000

71.810

Nov

237.790

0.000

0.000

0.000

237.790

0.000

0.000

0.000

0.000

0.000

62.300

Dec

Total

89405.621

0.000

0.000

26550.751

62854.870

0.000

0.000

0.000

0.002

3.265

606.900

w

 

Notes: (1) The performance targets are given in Section 1.69 of Specification B

1.     The waste flow table shall also include C&D materials that are specified in the Contract to be imported for use at the Site.

2.     Plastics refer to plastic bottles/containers, plastic sheets/ foam from packaging material

 

1 頁,共 1

 

Appendix G Complaint Log

Table G1 Statistical Summary of Environmental Complaints

 

Reporting Period

Environmental Complaint Statistics

Frequency

Cumulative

Complaint Nature

1 September 2024

-

30 November 2024

 

0

 

2

 

N/A

 

Table G2 Statistical Summary of Environmental Summons

 

Reporting Period

Environmental Summons Statistics

Frequency

Cumulative

Details

1 September 2024

-

30 November 2024

 

0

 

0

 

N/A

 

Table G3 Statistical Summary of Environmental Prosecution

 

Reporting Period

Environmental Prosecution Statistics

Frequency

Cumulative

Details

1 September 2024

-

30 November 2024

 

0

 

0

 

N/A

 

 

Contract No. 13/WSD/17

Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report

 

Appendix H

 

Event/ Action Plan for Water Quality Exceedance

 

 

Contract No. 13/WSD/17

Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant Quartertly EM&A Report

 

Table H1 Event and Action Plan for Water Quality Monitoring

 

 

 

Contract No. 13/WSD/17

Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report

 

Appendix I

 

Event/ Action Plan for Construction Noise Exceedance

Contract No. 13/WSD/17

Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report

 

Table I1 Event and Action Plan for Construction Noise Monitoring

 

 

Contract No. 13/WSD/17

Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant Quarterly EM&A Report

 

Appendix J

 

Event/ Action Plan for Coral Monitoring Exceedance

 

 

Contract No. 13/WSD/17

Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant

Table J1 Event and Action Plan for Coral Monitoring

 

 

The copyright of this document is owned by Acuity Sustainability Consulting Limited. It may not be reproduced except with prior written approval from the Company.

Acuity Sustainability Consulting Limited